Birnbaum v. Pierce CountyBirnbaum v. Pierce County
- Reporters:
- , ,
- Before:
- Appelwick
¶1 Pierce County approved Birnbaum’s permit application five years after she submitted it. Birnbaum sued pursuant to chapter 64.40 RCW, alleging that the County exceeded legally established time limits and made arbitrary and capricious requests for additional information. The trial court dismissed the claim under CR 12(b)(6). We affirm.
FACTS
¶2 On February 23, 2005, Wendy Birnbaum filed an application with Pierce County (County) for a conditional use permit to build a recreational vehicle park and campground. The County held a public hearing on August 2, 2006. On September 21, 2006, the hearing examiner issued a report and decision determining that Birnbaum did not provide sufficient information. Specifically, the decision stated that “[t]he applicant has not presented sufficient evidence to allow the Examiner to make the findings required.... The site plan does not provide sufficient detail of proposed uses, buffering, setback, access, and design.” Further, the hearing examiner found that the application did not “provide sufficient analysis of the impact of traffic” and “should be returned . . . for further review.” But, it allowed that “ [i] n the alternative, the applicant may consider this decision a final denial of the conditional use application for purposes of appeal.”
¶3 Birnbaum did not appeal. Instead, on December 8, 2006, she submitted a revised plan and requested a new public hearing. A hearing was scheduled for May 31, 2007, but continued to June 6, 2007. For unknown reasons, the public hearing was not actually held until December 16, 2009. On March 15, 2010, the hearing examiner approved the permit.
¶4 The final approval indicates that Birnbaum submitted another new site plan on July 13, 2008, and subsequent plan revisions on August 17, 2009, December 14, 2009, and January 19, 2010. There is no information in the record linking these revisions to demands for additional information or detailing what they contained.
¶5 Thirty days after the final decision, Birnbaum filed a complaint against the County. She alleged that the County failed to act within time limits established by law and made repeated demands for additional information that were arbitrary, capricious, unlawful, and exceeded its lawful authority.
¶6 The County filed a motion to dismiss under CR 12(b)(6). The trial court granted the motion to dismiss solely on the basis that granting the permit was adequate relief.
DISCUSSION
¶7 We conduct de novo review of an order granting a CR 12(b)(6) motion to dismiss for failure to state a claim upon which relief can be granted.
Cutler v. Phillips Petroleum Co.,
I. Action for Damages under Chapter 64.40 RCW
¶8
¶9 Birnbaum makes claims under each statutory prong. She primarily argues that the County exceeded applicable time limits. She also claims that the County’s demands for additional information were arbitrary, capricious, unlawful, and exceeded its lawful authority.
A. Damages under the “Failure to Comply with Time Limits” Prong
¶10 Birnbaum’s primary claim is that the County failed to comply with established time limits.
¶11 The County argues the 30 day limitations period began to run when the 120 day period expired and thus expired long before Birnbaum filed her complaint. In contrast, Birnbaum argues that her complaint was timely because she could not file her lawsuit until the County issued its final decision. Birnbaum’s reading is simply untenable.
¶12 The statutory language is unambiguous. An act occurs when there is
either
a final decision
or
a failure to act within established time limits.
¶13 Here, Birnbaum herself argues that there is no adequate administrative remedy for failure to timely process a permit. Thus, the limitations period began when the 120 day time limit was exceeded. Birnbaum filed her application on February 23, 2005. The hearing examiner approved the permit on March 15,2010. It is beyond dispute that she knew the 120 day time limit had been exceeded far longer than 30 days when she
¶14 Birnbaum argues that
Califas
and
Hayes v. City of Seattle,
¶15 In
Califas,
we concluded that an action for damages is not ripe until the city has, in fact, acted.
¶16 Insofar as Birnbaum sued the County for damages based on failure to comply with established time limits, the County’s CR 12(b)(6) motion to dismiss was properly granted.
B. Damages under the “Final Decision” Prong
¶17 The question remaining is whether Birnbaum has stated a claim for damages based on arbitrary and capricious actions or delays under the final decision prong of the statute. An “act” for this purpose is “a final decision by an agency which places requirements, limitations, or conditions upon the use of real property in excess of those allowed by applicable regulations in effect on the date an application for a permit is filed.”
¶18 Birnbaum’s complaint does not allege that the final 2010 permit approval places requirements, limitations, or conditions upon her real property that gave rise to her damages. Rather, she seeks damages for costs and delays that occurred while the County processed the application,
before the permit issued.
When the statutory definition of “damages” is given its plain meaning, it authorizes damages
only for expenses and losses that are incurred
after
a cause of action under the statute arises.
¶19 Birnbaum argues that her claim should survive because case law contemplates delay damages and, specifically, a claim for arbitrary delay occurring prior to a final decision which may be brought once the permit decision is final. That position is not supportable.
¶20 In
Callfas,
we considered the propriety of a “continuing violation” claim when the
¶21 Rather, the
Hayes
and
Mission Springs, Inc. v. City of Spokane,
¶22 Under the final decision prong, the final decision is the act that triggers the cause of action. The definition of “damages” limits recovery to those damages that occur after the cause of action accrues. Simply put, the statute does not contemplate damages — for delay or otherwise — under the final decision prong that occurred prior to the final decision.
¶23 Insofar as Birnbaum’s claims were based upon arbitrary and capricious requests for more information and delay prior to the final decision, the claim seeks damages not recoverable under this prong of the statute. Dismissal of these claims under CR 12(b)(6) was proper.
II. The Adequate Relief Theory
¶24 The trial court determined that because the permit was granted, Birnbaum received adequate relief and, pursuant to
Brower,
was not entitled to damages under chapter 64.40 RCW. The Browers filed a short plat application with the Pierce County Planning and Lands Service Department (PALS).
Brower,
¶25 This court reasoned that an applicant cannot bring a claim unless (1) it has exhausted all administrative remedies and (2) the relief granted by the administrative remedy is inadequate.
Id.
at 563-64. The Browers administratively appealed the adverse wetlands exemption decision and obtained the relief they sought: reversal.
Id.
at 561. Because the Browers received adequate relief, they had no cause of action — and no right to damages
¶26 However, Brower does not stand for the proposition that as a matter of law, the grant of a permit is adequate relief that precludes every action for damages under chapter 64.40 RCW. The Brower court was not asked to decide that question. Here, adequate relief from exhaustion of administrative remedies was not available. Unlike Brower, the County’s alleged arbitrary and capricious requests for more information were part and parcel of the permit review process and were not the subject of an administrative appeal or other form of exhaustion of administrative remedy. Likewise, there was no administrative remedy to exhaust for the claimed violation of the 120 day time limit. Brower does not apply here.
III. Collateral Attack and Collateral Estoppel
¶27 The County also argues that Birnbaum’s lawsuit is an impermissible collateral challenge to the 2006 decision that should have been brought as a Land Use Petition Act (LUPA), chapter 36.70C RCW, claim. Further, it argues that the lawsuit is barred by collateral estoppel because challenging the hearing examiner’s 2006 decision requesting more information would be a second litigation of issues already decided.
¶28 The 2006 decision stated:
The request for a conditional use permit to allow establishment of a campground and associated recreational uses is hereby returned to Pierce County Planning and Land Services and the Pierce County Environmental Official for further review as set forth above. In the alternative, the applicant may consider this decision a final denial of the conditional use application for purposes of appeal. Upon completion of review of the above items and the preparation of a more detailed site plan, this matter may be rescheduled for hearing with notice as in the first instance and specific written notice to parties of record.
Birnbaum did not treat it as a final decision and exercise her option to appeal. She exercised her option to submit a revised plan, which the County treated as part of the original application, not as a new application. Moreover, Birnbaum is challenging the County’s requests for more information that occurred between the 2006 decision and the 2010 approval, not the request for more information in the 2006 decision itself. It belies logic to say that her claims were barred before the County even made the requests.
¶29 We agree that if this were a challenge to the 2006 decision, it would be precluded under one or more theories. However, the County’s arguments are based on a mischaracterization of Birnbaum’s claims. Accordingly, Birnbaum’s lawsuit is not an impermissible collateral attack on the 2006 decision that should have been brought as a LUPA claim. Likewise, her claim is not collaterally estopped.
IV. Attorney’s Fees
¶30 Both parties request attorney’s fees pursuant to RAP 18.1 and
¶31 We affirm.
Reconsideration denied May 25, 2012.
Review denied at
Notes
Birnbaum argues that this conclusion cannot be correct because any available damages would be minimal and it is too difficult for an applicant to keep track of tolling periods and when the time limit has expired. These are limitations which flow from the language of the statute. We are not at liberty to rewrite them.
Califas
stated, “Indeed, a permit applicant like the Callfases would have a claim under chapter 64.40 RCW for delay damages, as we noted above, without a writ once the tardy permit was issued.”
Callfas,