Case Information
UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
BIO ENERGY (WASHINGTON), LLC, CASE NO. 2:23-cv-00542-LK Plaintiff, ORDER GRANTING MOTION TO v. AMEND COUNTERCLAIMS KING COUNTY, WASHINGTON,
Defendant.
This matter comes before the Court on Defendant King County’s Motion for Leave to File Third Amended Counterclaims. Dkt. No. 52. For the reasons set forth below, the Court grants the motion.
I. BACKGROUND
The facts underlying this dispute are set forth in the Court’s order regarding the parties’ cross motions for partial summary judgment. Dkt. No. 55. Rather than rehashing those facts, the Court focuses on the recent developments that spawned the proposed new counterclaims.
King County (the “County”) filed its second amended counterclaims on September 6, 2023, shortly after Bio Energy (Washington), LLC (“BEW”) shut down its landfill gas processing plant 1 (the “Plant”) from June 30 to July 21, 2023, and on August 11, 2023. Dkt. No. 26; Dkt. No. 53 at 1. [1] On November 21, 2023, the County issued its Notice of Intent to Terminate (the “Notice”) pursuant to Section 13.3 of the parties’ Amended and Restated Project Development and Gas Sales Agreement (the “PDA”) “demanding that BEW cure its default under the PDA” and restart Plant operations. Dkt. No. 53 at 1–2. [2] BEW did not resume operation of the Plant, and on December 18, 2023, it sent the County its “120-Day Written Plan of Action.” Dkt. No. 53 at 2.
Before it received BEW’s December 18, 2023 plan, the County was unsure how long BEW would keep the Plant closed. Id. at 2–3. After reviewing the plan, the County determined that some of the items in BEW’s plan were outside the parties’ control, others could not realistically be accomplished within the 120-day period, and still others were aimed at increasing BEW’s profits rather than necessities for BEW to resume operations. at 2. Thus, the County concluded that BEW intends not to “resume operation of the Plant and will remain closed indefinitely unless the County accedes to certain of BEW’s demands in this litigation.” The County therefore seeks to add a counterclaim for specific performance of BEW’s obligations to accept the County’s landfill gas under Sections 5.2.1 and 5.2.3 of the PDA. ; see also Dkt. No. 52 at 5.
The County also seeks to add a counterclaim for a declaratory judgment that: (1) BEW’s closure of the Plant and refusal to accept the County’s Landfill Gas is a Bio Energy PDA Default Event under Section 13.1.3 of the PDA; (2) the County issued a valid Notice of Intent to Terminate under Section 13 of the PDA; and (3) the County may terminate the PDA pursuant to Section 13.3.2 of the PDA.
Dkt. No. 52 at 5; see also generally Dkt. No. 52-1 (proposed amended counterclaims). 1 II. DISCUSSION
The deadline to file amended pleadings lapsed on August 24, 2023. Dkt. No. 16 at 1. The County filed this motion on January 24, 2024, Dkt. No. 52. Because the County seeks to assert claims based on events that occurred both before and after it filed its previous amended complaint, and because the deadline for amended pleadings has passed, Dkt. No. 16, Federal Rules of Civil Procedure 15(a), 15(d), and 16(b) are implicated.
A. Standards under Rules 15 and 16
Federal Rule of Civil Procedure 16(b) applies to a motion to amend the pleadings after the
deadline to do so has passed.
See Coleman v. Quaker Oats Co.
,
In assessing diligence, the Court may consider “whether the moving party knew or should
have known the facts and theories raised by the amendment in the original pleading.”
Jackson v.
Bank of Haw.
,
Federal Rule of Civil Procedure 15(a)(2) directs district courts to “freely give leave when
justice so requires.” As the language of the rule suggests, the standard for leave to amend is “very
liberal.”
AmerisourceBergen Corp. v. Dialysist W., Inc.
,
A district court should deny leave to amend “only if there is strong evidence of undue
delay, bad faith or dilatory motive on the part of the movant, repeated failure to cure deficiencies
by amendments previously allowed, undue prejudice to the opposing party by virtue of allowance
of the amendment, or futility of amendment[.]”
Sonoma Cnty. Ass’n of Retired Emps. v. Sonoma
Cnty.
,
B. Leave to Amend is Warranted
The County argues that it has been diligent and filed this motion “soon after the final events giving rise to its new proposed counterclaims.” Dkt. No. 52 at 2. Specifically, it filed its motion promptly after BEW (1) “fail[ed] to cure its default by December 21, 2023,” and (2) sent its December 18, 2023 plan confirming its indefinite closure of the Plant. BEW does not dispute the County’s diligence. See generally Dkt. No. 54. The Court finds that the County sought to amend promptly after the events giving rise to its new counterclaims, and has therefore provided good cause under Rule 16 to amend after the deadline.
Turning to Rule 15, BEW does not argue that it will be prejudiced by the proposed amendments or that the County has engaged in undue delay, bad faith, or repeated failure to cure deficiencies in its pleadings. See generally id. The absence of those issues weighs in favor of granting the amendments.
BEW focuses its opposition on the futility factor. at 2–8. It argues that the County’s new counterclaims “are premised on the alleged failure of BEW to accept all landfill gas collected by the County and to run its Plant,” which contradicts the County’s assertion that it is unable to perform under the PDA—as reflected in the County’s declaration of force majeure and contention that it can no longer accept BEW’s Plant Condensate and dispose of it in the leachate lagoons. Id. at 4–5. According to BEW, because the County is not “ready, willing, and able” to perform under the PDA, it is not entitled to specific performance. (quoting, inter alia , O’Connor v. Jackson , 62 P. 761, 762 (Wash. 1900)). BEW argues that the County’s proposed counterclaim for a declaratory judgment is futile for the same reason, i.e., the County’s professed inability to perform has relieved BEW of its obligation to perform. at 6–7.
“Denial of leave to amend due to futility is ‘rare,’ and district courts ordinarily ‘defer
consideration of challenges to the merits of a proposed amended pleading until after leave to amend
is granted and the amended pleading is filed.’”
Wash. Schs. Risk Mgmt. Pool v. Am. Re-Ins. Co.
,
No. 21-CV-00874-LK, 2023 WL 5036075, at *7 (W.D. Wash. Aug. 8, 2023) (quoting
United
States Fire Ins. Co. v. Icicle Seafoods, Inc.
, No. C20-00401-RSM,
Here, it does not appear “beyond doubt” that the County’s proposed amended counterclaims are futile. DCD Programs, Ltd. , 833 F.2d at 188. As BEW notes, the County is permitted to plead potentially inconsistent defenses. Dkt. No. 54 at 2; see Fed. R. Civ. P. 8(d)(3) (“A party may state as many separate claims or defenses as it has, regardless of consistency.”). Thus, the County may plead that it cannot accept BEW’s Plant Condensate while seeking specific performance of BEW’s obligations. Dkt. No. 52-1 at 43, 69–70.
In addition, under Washington law, specific performance may be granted if “a valid
contract exists, a party has [threatened] or is threatening to breach the contract, the terms of the
contract are clear, and the contract is not the product of fraud or unfairness.”
Pardee v. Jolly
, 182
P.3d 967, 973 (Wash. 2008);
see also Shu v. Ma
, No. C21-01432-LK,
III. CONCLUSION For the foregoing reasons, the Court GRANTS the County’s motion to amend its counterclaims. Dkt. No. 52. The County may file its amended answer and counterclaims, with any exhibits, within 14 days of the date of this Order.
Dated this 3rd day of May, 2024.
A Lauren King United States District Judge
Notes
[1] The County’s declaration incorrectly states that it filed its Second Amended Answer and Amended Counterclaims on August 24, 2023 Dkt. No. 53 at 1. 22
[2] The proposed third amended counterclaims and the Declaration of Pat McLaughlin state that certain exhibits are attached to those documents, but they are not. See, e.g. , Dkt. No. 52-1 at 55, 57 (referencing Exhibits 10 and 11); Dkt. 23 No. 53 at 2 (referencing Exhibits A and B). That deficiency is not material for purposes of this motion because the declaration sufficiently describes the exhibits and their contents are not in dispute. However, the County must attach all exhibits when it files it third amended counterclaims in the docket.
[3] Although “[t]he legal standard for granting or denying a [timely] motion to supplement under Rule 15(d) is the same
21
as the standard for a Rule 15(a) motion to amend,”
Elite Semiconductor, Inc. v. Anchor Semiconductor, Inc.
, No. 5:20-
cv-06846-EJD,
