The plaintiffs, hereinafter called respondents, commenced this action against the board of- education of the Jordan school district of Salt Lake county, hereinafter styled appel
In the complaint four causes of action were set up. The only cause of action, however, that is in question here is the third, in which a recovery for damages was sought for certain alleged breaches of said building contract. Judgments were entered on the other causes of action, all of which have been satisfactorily settled.
Con West was made a party defendant for the reason that he refused to join with the other plaintiffs as a plaintiff.
It is not necessary to go into further details respecting the relationship of the parties to the transactions involved on this appeal. Nor is it necessary to set forth the allegations of the complaint. A mere reference to them is sufficient.
The appellant answered the complaint, and in its answer pleaded various defenses to some of which special reference will hereinafter be made. Appellant also set up counterclaims against the respondents, or, at least against some of them.
The case was tried by the court without a jury. ' The court made its findings of fact and conclusions of law on the third cause of action. It found, among other things, that the respondents Con West and Jacob Jensen, as contractors, had suffered damages to the extent of $2,000 by reason of loss of time, etc., in the completion of said school building, which loss of time, the court found, was occasioned through the fault of the appellant. Judgment was entered in favor of Con West and Jacob Jensen under the prayer of the third cause of action. This appeal is^from that judgment.
A number of errors are assigned. The first one to be
A more serious question, however, is raised by other assignments of error. Appellant, in several assignments and in different ways, insists that the court’s findings are not supported by the evidence, that some of the findings are inconsistent and contradictory, and that the conclusions of law and judgment are contrary to the findings of fact.
In order to fully appreciate the effect of the several assignments, it becomes necessary to refer to some of the provisions of the building contract. The court found ' $hat one of the articles of the contract provides that—
“The contractor upon receiving from the architect written notice, and within such reasonable .time as may he named therein, shall remove from the premises all material, whether worked or unworked, and take down and remove from the premises all portions of the work condemned by the architect as unsound or improper, or in any way failing to conform to the contract; and the contractor shall properly replace'and re-execute his work in accordance with the contract and without expense to the owner, and shall bear the expense of making good all work of other contractors destroyed or damaged by such removal or replacement.”
Another article, the court found, is as follows:
“Should the owner fail to provide all labor and material not included in this contract, but essential to the conduct of this work in such manner as not to delay its reasonable progress, or should the contractor be damaged by any act or omission of the owner, the right of the contractor to compensation for the damages suffered, whether in the form of unusual or protracted services or otherwise, is conceded, and the amount of such compensation shall be determined and awarded by the architect (subject to arbitration); but no allowance shall be made unless a claim .therefor is made in writing or by telegraph to the architect within 48 hours of the occurrence of such damage.”
Another article of the contract reads as follows:
“Save only in cases in which an appeal to arbitration is permitted by these general conditions, the final decision of all questions arising under this contract shall be made and given by the architect, and both the owner and the contractor shall be bound thereby, and such decision shall be a condition precedent to any right of legal action by either owner or contractor.”
The court in substance found that the contractors pro
In view of the great length of the findings and the many details contained therein, we have found it somewhat difficult to condense them so as to reflect the salient facts. We are of the opinion, however, that enough of the facts have been stated for the purposes of this opinion.
At the trial respondents, undertook to prove the damages suffered by reason of the delays stated in the findings as follows: When the contractor West was testifying on behalf of respondents, after stating that - the work in reconstructing the wall that was ordered to be taken down and relaid had to be suspended for the reason that the brick which appellant desired were not obtainable for some time, and that by reason thereof the work on the buildings was delayed to the injury of the contractors, he was asked by respondents’ counsel this question: “Did you sustain any damages by reason of this delay in the furnishing of the brick?” He answered: “In the neighborhood of about $4,000.” Appellant’s counsel objected to the answer of the witness and moved to strike it on the ground that the same was improper, etc. The court said that “ordinarily the objection should probably be sustained, but under the circumstances — ” The court made no further ruling at that time, and appellant’s counsel excepted. Respondent’s counsel then propounded this question to the witness: “State the items of your damages.” The witness answered, “Well, the damage was to the amount of $2,000,” Objection was again interposed, when the court said: “Something more than that is required in order to sustain the allegation of damages.” The witness then undertook to give some details respecting the items of damage, but most of his details are
It is made apparent that respondent’s evidence was all based upon the theory that the appellant was responsible for all of the delays, and every witness who testified for them so treated the matter, and their conclusions with respect to damages were all based upon that theory. We desire to call áttention to the fact, however, that much of the delay was caused by the extra work sued for by respondents.
The evidence is also uncontrádicted, and the court in effect found, that the wall and the window sills, all of which were inferior to; and not in accordance with, the specifications, were rightfully ordered removed and replaced. It is manifest, therefore, that the appellant is not chargeable with all of the delays, and yet from the amount allowed by the court it would seem that such was its conclusion. If such was not the' court’s conclusion, then it is most unfortunate that it did not segregate the loss of time that was incident to the contractors’ faults and that for which the appellant alone was responsible.
We remark that from the evidence as it now stands it appears that the appellant may be liable for some damages in causing some unnecessary delays, but the. items of such damages are not of the magnitude that the court found.
The finding that the appellant was the sole cause of the delays, and therefpre liable for the amount of damages found
In view that the judgment must be reversed and the cause remanded for a new trial, we desire to call attention to the fact that, while the court sets forth article 29, which required the contractors to serve notice upon appellant or the architects in ease they claimed any injury or damage, etc., it makes no finding with regard to that provision of the contract; nor is there anything in the record from which we can determine whether there was any waiver of that provision on the part of appellant or its architects, or whether the district court was of the opinion that for some reason it should not be- enforced. In view that appellant’s-counsel complain that the court gave that provision no effect whatever and respondents’ counsel do not present what seems to us a sufficient excuse we have felt constrained to call attention to the matter so that the court may have an opportunity to pass upon the question before this court expresses an authoritative opinion respecting the matter.
Another matter requires attention. The court awarded interest on the amount allowed respondents as damages from the time they were suffered at the legal rate. Appellant’s counsel insist that, in view that the damages were wholly unliquidated and uncertain, no interest could be allowed until after judgment. ' Counsel for both sides have cited numerous cases, but for some reason neither side referred to the cases.of this court, where the question now raised is determined. The question was squarely presented in the ease of Fell v. U. P. R. Co., 32 Utah, 101, 88 Pac. 1003, 28 L. R. A. (N. S.) 1, 13 Ann. Cas. 137, which case is followed in Kimball v. Salt Lake City, 32 Utah, 253, 90 Pac. 395, 10 L. R. A. (N. S.) 483, 125 Am. St. Rep. 859. The doctrine laid down in those cases has been the law of this jurisdiction for more than 15 years, and has been followed many times by this court. Both the bench and the bar of this state should therefore be well acquainted with those decisions and should regard the question as settled. The rule of the court with respect to interest is in harmony with those cases, and must therefore stand.
From what has been said it follows that the judgment of the district court should be and it accordingly is, reversed; and the cause is remanded to said court, with directions to grant a new trial and to proceed with the case in accordance with, the views herein expressed. Appellant to recover costs on appeal.