Bilotta Construction Corp. v. Village of MamaroneckBilotta Construction Corp. v. Village of Mamaroneck
In an action to recover damages for breach of contract, negligence, and fraud, the plaintiff appeals from an order of the Supreme Court, Westchester County (Wood, J.), entered August 9, 1991, which granted the defendants’ respective motions for summary judgment dismissing the complaint.
Ordered that the order is affirmed, with one bill of costs.
"The ultimate guide in determining whether or not the contractor is to be paid for extra work is the contract itself * * * [I]f the parties intended the contractor to rely upon its own investigation, no recovery for extra work may be had, absent a showing of fraud or misrepresentation as to existing conditions” (Savin Bros. v State of New York,
Here, the contract documents contain numerous clauses relieving the defendants of liability and requiring personal inspection of the contract site by the plaintiff. In particular, the contract states that "[t]he Contractor agrees that he shall neither have nor assert against the Owner or Engineer any claim for damages for extra work or otherwise or for relief from any obligation of this Contract based upon the failure by the Owner or Engineer to obtain or to furnish additional subsurface information or to furnish all subsurface information in the Owner’s or Engineer’s possession or based upon any inadequacy or inaccuracy of the information furnished”. In addition, the contract documents state that "[a]t the time of the opening of Bids, each Bidder will be presumed to have inspected the site of the proposed work” and that "the Contractor shall * * * make all detail surveys needed for construction”. The contract documents further state that the data concerning elevations is to be regarded as approximate, with no guarantee of accuracy. Thus, the contract documents made it clear that the existing grade elevations were approximations, that these approximations were not to be relied on by the plaintiff, and that the plaintiff was obligated to conduct its