60 A.D. 470 | N.Y. App. Div. | 1901
The plaintiff, who was the servant of a contractor for the brick work of a building, went into a room thereof where the defendant, an independent contractor, was laying a floor, fell through the floor and suffered an injury. The fact that there was no contract relation between plaintiff and defendant did not deprive the former of a cause of action. Eor there was an obligation upon the defendant to
The defendant’s method was to lay down a false floor of wooden beams or supports, then over this a net wiring of expanding metal, and then a layer, of concrete off cement. After a few days the cement hardens, and then the strength developed by the combination of the “ set ” concrete and the steel of- the expanding metal makes the floor fit for usé; The defendant began to lay this floor about a week béfore the accident, but had laid, the finish coat of cement such a short time before it that the cement had not become hardened or “set” at the time of the accident; The false flooring is a- temporary support .which is taken away when the cement becomes hardened. Before the accident (according to one witness the day before) a part of this false floor had been removed, On the day of the accident there was presented, then, to the eye of the plaintiff the floor of the room, ■ apparently finished. That apart of this temporary support had been taken away was not apparent to him, inasmuch as the false floor was entirely beneath the surface of the floor, and the removal had been made from the room or cellar below. It is conceded that the accident was due to the fact that the part of the false floor had been improperly and prematurely taken away so as to weaken the floor before it had hardened and had, thereby, become usable. ‘The learned counsel for the defendant contends that there was not- evidence sufficient to submit the question to the jury whether this had been removed by the defendant. The witness Neild, an employee of the owner of the building, testified that- he saw one of the men of the defendant taking out the centers (i. e., a part of the false .floor), but on-cross-examination showed he did not speak from positive knowledge but upon the inference that none other would do this thing. Hart, the general foreman of the laborers employed by the owner of the building testifies that one-half of the centers Or supports were taken out the morning after the cement was put in, and that “ the foreman ” came there with a man and a vragon for that purpose. It appears that there were three sets of men at work about the building, namely.
The plaintiff testified that he had to go into the room in. order to -'build up a window from which bricks had been taken in order to •let out machinery; that he had to finish some work .therein, joining the old and the new, and there was no other place for doing the work. It could not be said as matter of law that the plaintiff was chargeable with want of ordinary care in entering through this open door upon .this apparently completed floor, which, according to some qf the witnesses, afforded the only access to his work. There is also evidence which warranted the jury to find .that the plaintiff, on the day when the concrete was first laid, had asked and had obtained leave of Shaw, the foreman of the defendant, to go. on the floor to put a scaffold there, and that, with such permission, he and his fellow-workmen then went in there, and put up the scaffolding. No evidence is offered that the plaintiff knew and none appears to make him chargeable- with knowledge that after this time a part of the support of the floor had been removed so as to make it a pitfall or a trap.
I find no merit in the exceptions taken.
The judgment and order must be affirmed, with costs.
Judgment and order unanimously affirmed, with costs.