*2 COLEMAN, Before GOLDBERG and MORGAN, Judges. Circuit Judge: GOLDBERG, Circuit admiralty In this case we must decide post whether the -Gutierrez sufficiently expan- unseaworthiness is longshoreman moving sive embrace a point on a the dock toward operation part the total vessel as longshore- The the vessel. man, Law, plaintiff-appellant Bill 11, 1967, on December working gang of a stevedore en- gaged of the SS SAGA- HILL, MORE HILL. The SAGAMORE operated by Victory owned and a vessel Carriers, (Victory), was Inc. docked at Mobile, Port Alabama. Law’s em- Corporation ployer, Gulf Stevedore charge loading op- (Gulf), was in eration. indicates that The record as a worked years prior
ten or twelve specific The exact situs and function of days he his work On some varied. drove vessel; on board a forklift machine days on the dock as some he worked man; days up” and on some “hook he a forklift machine drove dock. day he accident was of his driv- On ing forklift machine—one employer, dock. He Gulf—on using carry a forklift alongside hook-up point 1863, 10 S. v. Waterman Gutierrez ruling the district on the motions of bun- consisted landing issue— court one considered aircraft metal-mesh dles up pick from whether a bundle mats. Law pile located extended to Law.2 pile dock —the that Law was from the vessel— concluded approximately feet along- en- point hook-up therefore was it to the and take *3 ship, gaged and of the not taken in ship. were The mats side the scope of not directly the forklift hence that he was within vessel from onto the Having Instead, warranty set them of seaworthiness. Law would machine. point, hook-up un- of the doctrine dock at thus concluded down subsequently applicable this be taken they was not and longshoremen granted by case, of motions vessel other aboard the the court gear equip- by motion Victory and use of the vessel’s and and denied Gulf ment. of Law. transporting of contending one appeals, Law was While Law now pile holding from the of mats the bundles that he was court below erred in protection hook-up point, overhead scope came loose Agreeing machine rack of the forklift Law’s seaworthiness. causing him, allegedly in- contention, and fell on and we reverse remand. complains. juries The of which now has The of unseaworthiness doctrine commonly rack, protection overhead correctly twen- called “a child of rack,” is a metal “headache called the jurisprudence.”3 tieth-century federal the driver’s seat positioned above frame Brought by Brown’s to life Mr. Justice falling objects. protect him Osceola, 1903, 189 in famous dictum The investigation accident after Law’s 760,4 158, 483, di- U.S. 47 L.Ed. S.Ct. allegedly the four bolts revealed negligence concepts in vorced from the rack have secured were which should Co., Steamship Mahnich v. Southern missing. L.Ed. 321 U.S. and nurtured in the bosom complaint district filed a Law largely since, sympathetic judiciary injuries alleging ever experienced the doctrine has unremit- by the SA- the unseaworthiness
caused
Judge
ting growth
negligence
expansion.5
and
As
HILL and the
GAMORE
court,
recently
subsequently
for
this
shipowner
Coleman
wrote
Victory.
growing
against
concept,
complaint
doctrine
is a
third-party
“[t]he
filed a
"
Victory
constantly
undergoing
seeking
indemnity
redefinition
Gulf,
protected
dis-
en-
After
risks of
held liable
Law.
larged
changing
by
technology
Victory
covery
filed mo-
both
Gulf
technique.”
summary judgment,
to which
board
Dillon M. S. Orien-
tions for
filing
Inventor,
by
Cir.1970,
responded
a cross-motion
tal
Law
judgment.
summary
979.
for
pass
proper
appliances
appurtenant
2. The court did
ship.”
the forklift machine
or not
at 487.
of whether
189 U.S.
in fact defective.
unnecessary
purposes of
5.
find it
We
opinion
comprehensive
this
to delineate a
Note,
of Unseaworthiness
3.
The Doctrine
development
historical overview
Courts, 76 Harv.
in
Federal
the Lower
We
unseaworthiness.
(1963).
L.Rev. 819
however,
note,
this
task has been
by
undertaken with admirable
results
Brown’s four
Mr. Justice
The second of
opinion
For
propositions
some commentators and text writers.
Court
in his
analyses
following:
example, excellent historical
can
“That
the vessel and
was the
Black,
English
are,
found
Gilmore and
Amer-
both
her owner
Chapter
(1957),
indemnity
Admiralty,
law,
VI
for in-
of
Tetreault, Seamen,
ican
liable to an
consequence
juries
Seaworthiness and the
seamen
received
Rights
Workers,
Harbor
-39
Cornell-
(1954).
supply
keep
L.Q.
in order
failure to
L.
Supreme
decisions have
Court
Two
appli-
at bar. Ed.2d
further extended the
to the case
particular
relevance
cability of
Shipping
the doctrine of unseaworthi-
Co. v. Sier
Seas
The first
longshoremen,
acki,
ness to
66 S.Ct.
Court
Supreme
made
clear that the doctrine
Gutierrez
Sieracki
L.Ed.
injuries
question whether
sustained
relevance
off
considered
Court
seaworthiness,
obligation
tra-
the vessel. The
“the
slipped
Gutierrez
on the dock on beans
ditionally
of a
an owner
owed
bags
spilled
which had
out of defective
seamen,”
U.S. at
during
longshoremen
of a
of beans
“extends
from the vessel. On these
facts
doing
jured
work
independ-
Court concluded that
employed
ship]
but
[the
scope
was within
stevedoring
contractor whom
ent
*4
holding
seaworthiness,
duty
“the
to
that
load or unload the
has hired to
owner
provide
gear,
seaworthy ship
a
89,
The
ship,”
at 875.
id.
66 S.Ct.
at
cluding cargo
applies
containers,
long-
to
af-
in the
this
Court answered
ship
unloading
shoremen
whether
firmative,
longshoreman
holding that a
standing
ship
they
pursue
or on the
injured
could
a vessel
on board
pier.”
215,
at
against
83
373 U.S. at
S.Ct.
remedy
his
for unseaworthiness
1191,
(emphasis add-
remedy
Accordingly, the Court 347 U.S. performing function 1120, reversing per “when man 3 Cir. a curiam Ed. a per board service on essential maritime see Italia Societa of his Navigazione Oregon circumstances fortuitous Steve v. Azioni di shipowner by a employment steve- Co., 1964, doring doring not determine present contractor should In L.Ed.2d 732. rights.” Id. at shipowner of his case, therefore, the measure cannot be by liability 66 S.Ct. at the mere exonerated machine fact that subsequent decision Court’s by the than rather Corp., the stevedore Steamship Waterman Gutierrez determine question will Secondly this this second swer shipowner. —and scope of the apparent harsh- he whether principle ameliorates just discussed —a of seaworthiness. principle ness assaying question, find in to a we shipowner liable this held bring ap- third- a reported two distinct for unseaworthiness approach for in- against problem. proaches the stevedore One party action injury longshoreman’s minority define view —is demnity (cid:127) —the exceedingly steve- narrow a breach was occasioned shipowner) limiting (to fashion, it to mechanical dore’s Ryan begin performance. Steve- activities which workmanlike Steamship lifting doring onto the vessel. Pan-Atlantic act Co. approach is Drum Illustrative of this theory E.D.Va.1966, Plovba, gold this is under L.Ed. 133. indemnity Drumgold disposed Victory opinion from Gulf seeks 983. The long- Finally, actions, separate note present one case.6 of two rejected specifically (Drumgold) contended shoreman who this circuit arguments (1) injured the doctrine of while that he had been equip- applies the other (Hyter) the traditional contended that ment which is gear (2) of a rejected applies only equipment is at- To con- contentions. both *5 touching opinion, ship. vey or the These the full the court’s
tached to
flavor of
Judge
arguments
quote
in
laid
rest
in extenso therefrom:
were
to
we
scholarly
Thornberry’s
well-reasoned
“Drumgold,
and
longshoreman,
em-
a
was
Barge
opinion in Deffes v. Federal
Shipping
ployed by Rogers
and
Terminal
Inc.,
1966,
422,
5
361 F.2d
Cir.
Corporation,
stevedore, when
a
denied,
Grain
cert.
Continental
Co.
in
At
the time
October
Deffes,
385
17 L. question
U.S.
stevedore
a
the
was
application
the
grain
Ed.2d 433. Thus the
aboard the defendant’s
present
in the
doctrine
case cannot be
KRAJINA,
BELA
the
docks of
(1) by
equip- Cargill,
defeated
the fact
the
Inc.,
City
Chesapeake
forklift machine
pursuant
ment here involved —a
a
to
contract
between
the
product
technology
or
—is a
modern
shipowner.
and
stevedore
the
As a
(2) by
fact
duty
the
the forklift
of the
in
stevedore’s
the
physically
touching
arranging
stowage
attached to or
vessel and
for the
ship.
grain,
furnish,
to
se-
shifting
place
cure and
concepts
boards
With these relevant
furnish-
ship’s
grain
prevent
ing
backdrop,
in
hold
order to
turn to the funda-
we
shifting
from
while at sea.
mental
us:
Bill
before
Was
working
had
been
he
aboard
when
in
the SAGA-
employer
received
from his
MORE HILL
his in-
orders
when
sustained
go
(stevedore)
purpose
juries
to
ashore for the
on December
1967?
an-
Our
Liability
Ryan
significant
in-
suit has not been unfortunate.
result of the
One
generally
demnity
involving
shifted back
the steve-
in
land-
to
suits,
doring company through
injuries
indemnity
recently by the
noted
based
company
and that
then
an incen-
Ha-
has
Ninth
in Gebhard v. S. S.
Circuit
improve
Legislator,
tive to
unload-
its
waiian
Cir.
ing equipment.
(See
Italia
Societa
1312:
per
Navigazione
Oregon
“Although
di
landward
extension of
Azioni
(1964)
Stevedoring Co.
376 U.S.
criticized
732;
(e. g.,
11 L.Ed.2d
S.
v. Waterman
Skibinski
“
Baby’:
Proudfoot,
Corp.
(2d
1966)
‘The Tar
Maritime
Cir.
Injury
Indemnity
(Judge Friendly dissenting),
Actions”
Personal
cert.
445-46.)”
(1968)
(1967)
20 Stan.L.Rev.
denied
975),
re-
18 L.Ed.2d
the overall
rigged
obtaining
controlled
Atlantic &
specially
Gulf Steve-
truck
dores,
generally
It is
Inc.
conceded that
He was
the stevedore.
shifting
operation of
forklift machines on
the truck with
structed
load
pier
necessary adjunct
bring
or dock is a
the truck
boards and thereafter
any
completing
alongside
or-
pier
in
the vessel
onto the
ship.
placed
taken from
There
could be
der that
the boards
stevedoring gang;
being
in the holds. men
used
the vessel and
aboard
Plaintiff,
instructions,
following
vessel and 8
these
on the dock.
shifting boards, The
of cork
bales
are lifted out
bundles
obtained two
means
hold and then lowered
the dock where
loaded same orí the truck
brought
sling-
rigging,
truck
special
are unfastened
hooks
ers,
alongside
pier,
following
and un-
which the bales
pier.
shifting
placed upon
onto the
loaded
towmotors
forklifts and
boards
Hyter,
away.
crane
plaintiff,
intended that
the vessel’s
taken
pier
lift the
boards
unhooked the hooks on
of cork
the bale
Plaintiff,
ship.
towmotor, operated by
the deck
a fellow
when
longshoreman,
the truck’s
up
use
thereafter directed
ran
backed
over
purpose of mov- Hyter.
and hoist
boom
While the condition of
ing
shifting
the side
closer
disputed,
boards
brakes on the
vessel, thereby
positioning
argument
purpose
will assume for the
There is
crane.
under the
boards
were defective.
brakes
tending
to establish
evidence
respective plaintiffs
“The
contend
known,
knew,
have
stevedore
that the
must
truck,
the defective condition
Drumgold
the truck
be extended to
Plaintiff,
standing legs.
its boom
Hyter. They rely
towmotor
attempting
put
truck’s
down
Lauritzen,
Spann
Cir.,
upon
F.
load,
stabilizing legs
found
lift
2d
386,
den. 382
capsized,
legs
truck
defective and
Matson
Huff v.
*6
water,
falling
a result
as
into the
Navigation
Co., Cir.,
9
F.2d
338
ship’s
injured.
was
85
cert.
U.S.
13
den. 380
the truck
later
to raise
crane was
used
Barge
L.Ed.2d
Deffes
Federal
regu-
truck was
of the
out
water.
Cir.,
Inc.,
larly
by
in connection
used
the stevedore
den.
Def-
Continental Grain Co. v.
but,
course,
operations
with
fes,
U.S.
operated
pier
never taken
and
on the
433, Metzger
17 L.Ed.2d
and
Kir-
v. SS
is some evidence
aboard a vessel. There
Torm, D.C.Md.,
sten
ship’s mate de-
to the effect
the
that
They point
to the
also
celebrated
use of the
clined to allow the
of Gutierrez v. Waterman S.S.
use
crane and this
necessitated the
fact
83 S.Ct.
truck,
factor is not essen-
but this
Oregon
and Italia Societa etc.
tial to this memorandum.
Stevedoring Co.,
U.S.
748,
“Hyter
longshoreman and, on
is a
volving
ter
er to
lantic & Gulf
September
having
perform unloading operations
contracted with
Stevedores,
of cork
from defendant’s
employed At-
Inc.;
the
shipown-
the lat-
by
the
any
merit,
“* * *
ship’,
#
manner
the
[*]
if the
They
engaged
warranty
(cid:127)*
urge,
longshoreman
‘in
#
and not without
the service of
seaworthiness
[*]
[*]
is
vessel,
applies
anywise
YOZGAT,
is
con-
such service
SS
docked at
while
contemplated
B,
Norfolk, Virginia.
Northside,
or
Pier
nected
the
with
contemplated
pier
job
slinger
removal from the
on the
already
pier
and,
apron
engaged
such, plain-
while
as
stowage
purpose
by
allegedly
a warehouse
tiff
was struck
defective
an
purpose.
owned,
any
transfer
operated
or for
other
and
which was
ship’s duty
deciding
to load
attendant
to the
“Assuming
the cor-
without
rulings
Spann,
assumption
Huff,
unload.
If such
incorrect
is
rectness
constantly
be
confronted with
Deffes,
not of
we will
this Court
is
alleging
claims
doctrine
opinion
seaworthiness
cargo,
example,
load-
vessel because of
about to be
For
so
can
extended.
ship,
technically
ed aboard
which falls in a ware-
longshoreman
thereby injuring
pier
house
if he is instructed
stevedoring
going
employee of the
In
purpose
concern.
a truck
take
Drumgold we do not
rope
believe
city
or wire
to secure a
into
insofar,
operation,
the war-
as
in connection with
concerned,
ranty . of
seaworthiness
particular
operations
aof
or
shifting
commenced until
boards
While so
brakes
being
physically
and,
at
defective
the truck become
vessel,
moved from the stevedore’s truck to the
point many
miles
Hyter
In
unload-
deck.
we feel that
longshoreman
injured by
of an
reason
ing terminated,
argue
insofar
Plaintiffs
concerned,
when
render
defective brakes would
truck’s
seaworthy
unseaworthy.
effect,
bale
cork in a
condition
what
vessel
slingers
properly
detached
plaintiffs
do is
to extend
wish
pier awaiting
at
rest on the
re-
injured
all
the benefits
It
accruing
moval
another area.
these
seaman
points
Texaco,
Hopson
of seaworthi-
the Jones Act. See:
stopped.
started
hold-
ness
Such a
Inc.,
L.
ing
Gutierrez, Huff,
does no
violence
Ed.2d
Spann, Deffes,
Metzger,
relied
all
long-
injury
“In Gutierrez the
upon
plaintiffs.
merely
places
slipped
sustained
shoreman was
when
upon
a reasonable limitation
the extent
spilled on
occa-
on loose beans
the dock
warranty.”
F
unseaworthy condition of
sioned
.Supp.
984-985,
(footnotes
986-987
aboard the
omitted).
during unloading
spillage
oper-
resultant
judice
In the case sub
the district
agree
clearly
that Gutierrez
ations. We
court embraced the narrow definition of
extends
the seaworthiness
“loading.”
The final order entered
‘loading
unloading’ a
following
the court below included the
whether aboard
language:
not, however,
pier. We do
find that
*7
presented
“[T]he
loading operation
Drumgold
had com-
long-
Court for
is
decision
whether a
we further
menced —and
find that
cargo
removing
shoreman
from stor-
Hyter
operation in
termi-
age
by operating
to dockside
a forklift
respective
longshore-
nated —when the
performing
ship’s
machine
is
work
injured. Manifestly
items
men
seaworthy
and therefore
entitled to a
giving
injuries
equipment
of
rise to the
vessel. After careful
of
consideration
were never
intended to
used aboard
applicable law,
the facts and the
they were,
best,
conveyors
ship;
mere
plaintiff,
Court concludes
Bill
bring equipment
ship’s
needed to the
Law,
engaged in
was not
work
(Drumgold),
already
side
or to remove
ship
and not covered
cargo
(Hyter).
unloaded
another area
of seaworthiness.
authority
find no
cause
We
which would
every piece
equipment
us
hold
“The Court’s conclusion is
based
every activity leading up
plaintiff’s
the ‘status’
and not
to or fol-
work
lowing
loading
unloading opera-
injury.
or
his situs
the time
cargo
positioning
tion must
be covered
under the
in turn
loaded
seaworthiness.
are
which
would be
We
concerned
cargo
ship
ship’s equipment
The-
and the
onto
vessel.
loading
plaintiff’s
operation.
directly
loaded from
In the immediate
plaintiff
ease,
plaintiff
loading
did the
assist in
forklift nor
was not
car-
cargo
go
into the hold
aboard the vessel in the sense of
sense,
simplest
‘ship’s
theory
In the
the vessel.
work’
of recov-
bringing
doing
ery against
all
the defendant for unsea-
cargo
loaded on the
to the dock
worthiness must fail.”
a truck driver who
vessel. Would
apparent
thus
is
the district
dock in his truck and un-
drives to the
court concluded that Law was not “load-
freight
turn
be-
loads
which in
will
ing” the SAGAMORE HILL because his
entitled to
come
vessel be
job moving
landing
the aircraft
mats
—
seaworthy
truck
vessel? Would his
hook-up point adjacent
to the
to the ves-
ship?
appurtenance
be an
preceded
sel—entailed activities which
True,
plain-
thinks not.
Court
lifting
the actual
act of
the car-
the vessel
tiff’s association with
go onto the vessel.
loading operation
prevalent view,
The more
however, is
hypothetical present-
is closer than the
found in cases which define the terms
above,
seaworthi-
ed
but to extend the
“unloading”
in a more
plaintiff’s work
ness doctrine to
pragmatic and less ritualistic sense.
Il-
the doctrine to
would also extend
Byrd
lustrative of these cases is
of situations
unlimited number
Export
American
Isbrandtsen
intended.
was never
Inc., E.D.Pa.1969,
F.Supp.
actu-
was not
us, Byrd
Like the case now before
the time
al
vessel at
injury
volved an
to a
en-
say
easy
It is
gaged moving cargo by
means of a
assisting
contributing
point
machine from one
on' the
aboard the
point
dock to another
nearer the vessel.
apply
But
the same rationale can
The court held that
persons
perform
innumerable
operation
was involved in
required
work
at the
injury.
vessel
time of his
We
duty.
to ‘service’the
for sea
The quote
opinion:
the court’s
liability
unlimited.
summary
“This
a motion for
A line must
As stated
be drawn.
judgment
filed
ship-
the defendant
Knudsen,
Daniel v.
Hilda
Skibs A/S
longshore-
owner
in this action
affirmed 368
man. Defendant contends that
(3rd
1966):
C.A.
plaintiff’s deposition conclusively es-
plaintiff’s
‘While
have
work
plaintiff’s
tablishes that the
accident
unloading process
contributed to the
could have
only by
been occasioned
ei-
philosophical sense,
in a
it was not
possible
ther of two
causes and that
unloading in the sense that it was a
responsible
defendant was not
for ei-
work. We
ther cause.
aware that the recent trend
deci-
deposition
“Plaintiff’s
discloses that
in the Su-
sions in this Circuit and
Givens,
longshore-
he and Otis
another
preme
Court has been to widen
*8
man,
engaged
attempt
were
in an
to
coverage.
ambit
move from the back to the front of
However,
end
to
there has
be
pier,
truck,
the
a forklift
which was
unloading process
somewhere
intended to
loaded
be
aboard defend-
liability imposing
in the sense of
cargo.
ant’s
attempt
vessel as
ship’s work.’
by backing up
was undertaken
another
certainly ap-
truck,
“The
statement
above
identified as No.
plies
loading as well
prospective cargo,
as
so that the
just
ship;
as
latter could
towed
be
forward. As
unloading,
plaintiff
there must
an end to the
be
bent down between the two
beginning
there must
rope,
be
trucks to
attach
tow
No. load-
work
constituted
which
catching plaintiff between
up,
backed
Weyerhaeuser
ing.’
Litwinowicz
know
does
the two.
F.Supp.
Co.,
Steamship
time
at
was
Givens
Otis
where
(E.D.Pa.1959).
says
last
817-818
injured, but
plaintiff was
getting
No.
off
Givens
observed
plaintiff
conclude that
“Since
gear
No
before
engaged
essentially
in a
was
was
which
No.
attached
was
using equipment
operation
and was
Stevedores,
& Gulf
Atlantic
purpose,
was
for that
which
Inc.
adopted
temporarily
least
if
even No.
asserts
“Defendant
ship,
must be
motion
the defendant’s
plaintiff
Giv-
into
947 was backed
(foot-
denied.”
plaintiff
because
rolled into
ens or
omitted).
note
condition,
de-
defective
of some
see,
vein,
holdings in a similar
For other
liable,
held
be
because
cannot
fendant
Legisla
e.g.,
Hawaiian
v. S. S.
Gebhard
plaintiff
activity
which
Thomp
1303;
tor,
9 Cir.
yet
was,
pier
engaged
on the
then
Steamship
3 Cir.
Calmar
son v.
ship.
operation of the
denied,
379 U.
331 F.2d
must,
concedes,
it
“Defendant
184;
whether
the acci-
it
immaterial
Hagans v. Ellerman
Bucknall Steam
&
away
pier
from
dent occurred
Co.,
cf.
3 Cir.
ship,
was ac-
S.D.Tex.1968,
Michalos,
Olvera v.
engaged
tually
F.Supp. 9.
loading opera-
includes
Steam-
v. Waterman
tion. Gutierrez
align ourselves
We choose to
ship Corporation,
83 S.
“loading”
the cases
define
(1963); Ha-
curring pastor- some urban enclave pasture pier.
al from the far removed contrary, activities had On Law’s COMPANY, & BABCOCK WILCOX continuity job proximity to and with the Assignee of the Interference Parties loading cargo at hand —the task Dungey Frendberg HILL. His SAGAMORE job specific performance was inte- so CORPORATION, FOSTER WHEELER grally op- entire woven into the Assignee the Interference Parties separated eration be cannot two Gorzegno, Pai, Appellant. Weber & except by hyperteehnical erection No. 19087. legal If and unrealistic barriers. “unloading” terms are to Appeals, United States Court of reality terms associated with rather Third Circuit. conceptual mere than microcosms with- Aug. 25, Argued adjuncts beyond beam, out 14, 1970. Sept. Decided have no choice but to conclude that Rehearing Denied Oct. Law was HILL. SAGAMORE We therefore hold that on the facts of this case —a
longshoreman, intimately involved in the as he moved the back the front was within the dock — scope of seaworthiness.
Since we have concluded that the doc- applica- trine of here ble, plaintiff op- must afforded the
portunity prove truth of his alle- gations. We therefore remand the ease proceed-
to the district court for further
ings opinion. consistent with this
Reversed and remanded. Seaworthiness, enlightening 7. For discussion of Risk Distribution (1966). longshoremen, Note, risks incurred see Yale L.J. 1174
