Bigler v. . Hall

54 N.Y. 167 | NY | 1873

Lead Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *169 The defendants, by the express terms of the contract, for the breach of which this action was brought, did "agree to deliver, in the Susquehanna river at Binghamton, in rafts, from one hundred and fifty to two hundred thousand feet of pine logs, above the Pratt Tyler saw-mill." The logs were designated as comprised of two lots, lying in specified localities, all of which (except fifty of the poorest, in one lot, and which might be thrown out and not rafted) were to be delivered as above stated. The quantity was to be ascertained by Mr. S.R. Carpenter's measurement of the logs, and the plaintiff was (as it was expressed in the contract) "to pay sixteen dollars per thousand feet, one-half at two months and the balance at three months in good bankable paper, to be dated when the account of measurement is handed in, $200 to be paid within six days of this date, by mail" — evidently meaning that the sum of $200 was to be paid to the defendants by being sent through the mail, within six days from the date of the contract, and that payment of the balance *170 of the price to be paid was to be made, as soon as the plaintiff was informed of the quantity by such measurement, by his two notes of equal amount, to be dated when the account of such measurement was handed in, and to be payable in bankable money, one in two months and the other in three months from their respective dates. The agreement also specified the time when such delivery was to be made. There is no ambiguity or uncertainty in any of its terms. It is a contract for the absolute delivery of the logs at a designated place and time, for a price to be ascertained in a specified manner.

Such being the construction of the contract, and the plaintiff having paid the defendants the whole amount for which he was liable, they were bound to deliver the logs according to its terms, and they were not discharged from the obligation by their inability to do it, in consequence of freshets which caused a loss of some of them. They did not make any provision against such a casualty or accident. It was one which they could have guarded against, and it is not unreasonable to assume that both parties contemplated the possibility of such a contingency in fixing the price to be paid by the plaintiff. Assuming, then, that the legal obligation of the defendants was as above stated, it is immaterial whether the logs were lost through their negligence or not. That question is not involved in the case.

It follows that the judge at the circuit properly ruled that the plaintiff was entitled to recover for what lumber he paid for and had not been delivered to him by the defendants according to their agreement, and as such payment was made at least two years before the day of trial, he, in charging the jury that the plaintiff was also entitled to interest on that sum for one year and ten months, charged more favorably to the defendants than the law required. The error, if any, was to the plaintiff's prejudice and their advantage. They therefore are not aggrieved by it, and have no cause of complaint on account of it.

The plaintiff, in proving the quantity that was not delivered, *171 was not required to do it by Mr. Carpenter's measurement, on the ground or objection taken by the defendants' counsel to other evidence offered for that purpose, that the parties had "agreed upon a mode of measurement between themselves." It was a fact, ascertainable and proper to be established by any witness having sufficient knowledge to testify on the subject.

It may be proper to add, that it does not appear to have been made a question on the trial whether the contract was a contract of sale, but the points litigated seem to have been whether the defendants were absolutely liable for all of the logs that had not been delivered, on the construction of the agreement that he had bound himself, without any qualification of his obligation, to make a delivery of all, or whether they were only liable for such as had been lost or not delivered through their fault or negligence. I have consequently not considered it. It seems to me, however, immaterial. If it can be so construed, and if the logs mentioned in the contract became the property of the plaintiff as soon as they were measured and paid for by him, as the defendants claim on this appeal, it does not follow, as they say, that "from that time they were at his risk." The absolute and unqualified obligation of the defendants to deliver them at the place designated for that purpose still existed, and their failure to fulfill and discharge it, and their duty growing out of it, made them liable for the damages growing out of its breach.

In any aspect of the case the plaintiff was entitled to recover. It follows that the judgment appealed from is not erroneous, and it must, consequently, be affirmed, with costs.






Dissenting Opinion

The logs were designated or identified by their location at the time of the contract, and were to be delivered in the Susquehanna river at Binghamton in rafts. They were to be rafted as soon as the middle of June, 1864, and delivered as soon thereafter as the water should be high enough to run them. They were to be *172 measured in the log by S.R. Carpenter, and paid for at sixteen dollars per thousand feet; one-half at two months and the balance at three months in good bankable paper. Two hundred dollars was to be paid within six days after the date of the contract. The required measurement was made by Carpenter's producing 255,408 feet of lumber, all of which was paid for, at the stipulated price, on or before the 1st day of June, 1864. A portion of the logs were never delivered having been carried away by an unprecedented freshet, it is claimed without any fault of the defendants, and the recovery was had for the supposed difference between the amount of lumber actually paid for and that actually delivered upon the ground that the logs and lumber were at the risk of the defendants until actually delivered, and if the title did not pass to the plaintiff when the lumber was measured and paid for; the recovery should be sustained. It appears to me that everything was done by way of identification, ascertainment of quantity and payment of price to make an executed contract of sale, and that the title passed to the plaintiff. Nothing remained but actual delivery, and that in very many cases, is not essential to the transfer of title to a purchaser. It would hardly be claimed that if a party went to a merchant and selected, purchased, and paid for a valuable article in his line of business, he did not acquire the title because it was left in the merchant's store to be sent to the residence of the purchaser. The case of Terry v. Wheeler (25 N.Y. 520), appears to be decisive of the one at bar. I think, also, the principle of the case of Groat v. Gile, decided by this commission in the year 1872 (51 N.Y., 431) must also be controlling. The actual delivery of the logs as the contract provided was a very important element as it is in almost every contract of sale. Both parties appreciated its importance and were doubtless familiar with its perils. It cannot be supposed that the plaintiff intended to pay for more lumber than he received, or that the defendants took pay for more than they intended to deliver. But a contingency happened which neither party anticipated, and was not specially provided for. *173 The defendants were bound to use their utmost efforts to deliver all the logs for which they had been paid; but they were not insurers. They offered to show that the logs were lost by no fault or negligence on their part, and they should have been allowed to do so, as I think upon that question alone depended their liability.

There should be a new trial.

All concur for affirmance except REYNOLDS, C., dissenting.

Judgment affirmed.