209 Conn. 212 | Conn. | 1988
The plaintiffs, John Bialowans and John Wagner, take this joint appeal from the judgment of the trial court dissolving their prejudgment attachments and discharging the plaintiff Bialowans’s mechanic’s lien on the property of the defendants, Robert O. and Joann Minor. The plaintiffs assign error in the trial court’s interpretation of a lien waiver agreement, upon which the trial court based its decision, and in the trial court’s failure to find a lack of consideration to support the lien waiver agreement.
“WAIVER OF MECHANIC'S] LIEN TO ALL WHOM IT MAY CONCERN: THIS CERTIFIES THAT
We, the undersigned, contractors, sub contractors, material men, et cetera, in consideration of One Dollar received to our full satisfaction of Robert O. & Joann L. Minor of the Town of East Lyme County of New London and State of Connecticut have waived, relinquished and released and do hereby waive, relinquish and release all liens and claims of liens we now have or may hereafter have upon a piece of land and. all the buildings thereon standing . . . for labor done or to be done and materials furnished or to be furnished in the erection, construction or repair of said buildings:”
In July, 1987, the plaintiffs instituted separate actions against the defendants to recover damages for the alleged breach of their respective construction contracts. In conjunction with the filing of their complaints, the plaintiffs each filed a prejudgment attachment lien, pursuant to ex parte court orders, on the defendants’ real estate for claimed work performed and materials supplied in the construction of a residence on the attached property. The plaintiff Bialowans also filed a mechanic’s lien on the property. In August, 1987, the defendants filed two separate motions to dissolve, one directed at each of the prejudgment attachment liens filed by the plaintiffs. The defendants also made an application to discharge the mechanic’s lien filed by the
I
Initially, we address the plaintiffs’ contention that no evidence was offered at the hearing below that the plaintiffs received consideration that would sufficiently support the plaintiffs’ waiver of their lien rights. In response to a motion for articulation filed by the plaintiff Bialowans, the trial court found in its first articulation filed October 16,1987, that there was sufficient consideration to support the plaintiffs’ waiver in that, by signing the waiver agreement, the plaintiffs “ ‘enable^] the [defendants] Robert O. Minor and Joann [Minor] to draw money from the bank to finance the construction in progress.’ ” We find that the trial court’s conclusion is supported by the evidence and correct as a matter of law.
In Townsend v. Barlow, 101 Conn. 86, 89, 124 A. 832 (1924), we stated: “[T]he term ‘waiver of mechanic’s lien’ has by long usage become descriptive of a writing having the purpose and effect of releasing, accord
Thus, the trial court was clearly entitled to conclude, as it did, that the signing of the lien waiver agreement
II
We next address the plaintiffs’ claim that, by signing the waiver agreement, they waived nothing more than their right to file mechanics’ liens on the defendants’ property and that the trial court erred by interpreting the agreement more broadly to include a waiver of the plaintiffs’ right to file prejudgment attachments. We agree that the trial court interpreted the waiver erroneously.
The interpretation of a contract involves a search for the intent of the parties. Lar-Rob Bus Corporation v. Fairfield, 170 Conn. 397, 406-407, 365 A.2d 1086 (1976). Where this intent is expressed in language that is clear and unambiguous, the contract is to be given effect according to its terms. See Leonard Concrete Pipe Co. v. C. W. Blakeslee & Sons, Inc., 178 Conn. 594, 599, 424 A.2d 277 (1979); Collins v. Sears, Roebuck & Co., 164 Conn. 369, 373-74, 321 A.2d 444 (1973). Also, “[a] contract is to be construed as a whole and all relevant provisions will be considered together.” Lar-Rob Bus Corporation v. Fairfield, supra, 407; see Sturman v. Socha, 191 Conn. 1, 12, 463 A.2d 527 (1983); 17 Am. Jur. 2d, Contracts § 258.
Applying these accepted principles of contract interpretation to the present case, we find that the waiver
Accordingly, in view of the parties’ stipulations at the hearing below that there was probable cause to sustain the plaintiffs’ prejudgment attachment liens if said liens were deemed not to have been waived, we remand the case to the trial court with instructions to reinstate
There is error in part, that portion of the judgment dissolving the plaintiffs’ prejudgment attachment liens is set aside and the case is remanded with direction to reinstate the prejudgment attachment liens.
In this opinion the other justices concurred.
In their preliminary statement of issues, the plaintiffs presented the following claims on appeal:
“1. Did the court err in equating a prejudgment attachment with that of a mechanic’s lien?
“2. Did the court err in interpreting a document entitled ‘Waiver of Mechanic’s [Lien]’ as waiving the plaintiff’s right to seek a prejudgment attachment?
“3. Did the court err in its interpretation of Defendant’s Exhibit I?
“4. Did the court err in ordering the dissolving of the attachment and mechanic[’s] lien when there was no consideration for the waiving of the mechanic’s lien?
“5. Did the court err in dissolving the mechanic’s lien and prejudgment attachment where the defendant misrepresented the purpose of the waiver form?”
The first three issues submitted by the plaintiffs are essentially indistinguishable in that they challenge the trial court’s interpretation of the lien waiver agreement; thus, we will treat these claims as a single issue for purposes of this appeal. Furthermore, the fifth issue was not briefed by the plaintiffs and, therefore, we deem it abandoned. Keating v. Glass Container Corporation, 197 Conn. 428, 430 n.3, 497 A.2d 763 (1985); O’Connor v. Dory Corporation, 174 Conn. 65, 70, 381 A.2d 559 (1977).
On direct examination by.his attorney, the plaintiff John Wagner testified as follows:
“Q. Would you indicate to the Court the circumstances under which you signed [the lien waiver], what happened.
“A. Mr. Minor drove up one afternoon and presented the document, and told me that the bank had asked him to get this signed before they would release funds.
“Q. Did he promise you money?
“A. Yes, he said he would pay his bills.
“Q. Did he indicate he would pay from proceeds of what the bank was going to disburse?
“A. He told me he couldn’t pay until he got money from the bank.’’
As between the plaintiff John Bialowans and his attorney, the following colloquy took place:
“Q. How did you happen to sign [the lien waiver]?
“A. I was approached by Mr. Minor, and he said I had to sign it to get some disbursements from the bank so that they could give him some money.
“Q. So the bank could give him some money?
“A. Right, to pay me.
“Q. To pay you?
“A. Right.”
The stipulation entered into between the plaintiff John Wagner and the defendant Robert D. Minor that there is probable cause to sustain Wagner’s prejudgment attachment lien is not in the printed record. It is in the court file, however, of which this court may take judicial notice. Krawiec v. Kraft, 163 Conn. 445, 451, 311 A.2d 82 (1972).