In July, 1965, the plaintiff, a building contractor, and the defendants, husband and wife, entered into a contract whereby the plaintiff, having title to a lot in Ridgefield, agreed to construct on the lot a house according to certain specifications and on its completion to convey the house and lot to the defendants for an agreed price. The expected date of occupancy was November, 1965. Several circumstances, including the failure of the plaintiff to obtain a construction mortgage and changes in plans induced by the defendants, delayed occupancy until July, 1966. The house at that time was substantially completed, but the plaintiff had not totally discharged his obligation in that the specified garage had not been built and various ancillary construction and cleanup work had not been performed. In addition, the artesian well drilled pursuant to the contract failed to provide potable water.
The defendants refused to pay a portion of the contract price and the plaintiff sued for this balance. The defendants filed a counterclaim for their additional expenses and for damages alleged to have resulted from the delay and from the unfitness of the well water.
The court found that the original contract had been modified by a series of mutual oral agreements and that when the defendants occupied the house in July, 1966, “the contract was substantially performed but with much left to be done which was the obligation of the plaintiff under the terms of the contract.” In rendering its judgment on the complaint and the counterclaim, the court took into *466 consideration, so far as it found that they had been proved by a fair preponderance of the evidence, the “extras” provided by the plaintiff, the “credits” to be extended to the defendants, the reasonable extra expenses the court found to have been incurred by the defendants because of the delay, and the cost of the garage which had not been built. The judgment awarded $8765 to the plaintiff on the complaint and $5181.25 to the defendants on the counterclaim. Neither interest nor costs were awarded to any party. From the judgment the plaintiff and the defendants have appealed to this court.
The plaintiff has preserved two claims on appeal. The first is that the court erred in not awarding interest on the judgment from the time that the defendants occupied the house until the date of judgment. In this connection, the court expressly found that the amounts due the parties on the complaint and the counterclaim, respectively, were not liquidated until the date of trial.
“ ‘The determination of whether or not interest is to be recognized as a proper element of damage, is one to be made in view of the demands of justice rather than through the application of any arbitrary rule.’
Bernhard
v.
Rochester German Ins. Co.,
In the circumstances of the present case, the trial court clearly acted within the scope of its discretion. Upon finding that the underlying contract had been orally modified in many respects, that it had been substantially performed but that the plaintiff had failed to fulfill his full obligation, and that many of the difficulties and delays were the result of the plaintiff’s conduct, the court could reasonably conclude, as it impliedly did, that the defendants had not wrongfully deprived the plaintiff of a sum of money. The findings support a conclusion that the plaintiff was at least partly responsible for the defendants’ refusal to pay a portion of the amount due on the contract. Accordingly, we do not find that there was any abuse of the court’s discretion.
The plaintiff’s second properly preserved claim is that the court erred in determining the allowance due the defendants for the construction of a garage in substitution for the one which the plaintiff failed to construct. The defendants sought and received a “credit” for the cost of building their own garage, which was of a type different from that specified in the contract. The plaintiff testified that his cost of constructing the garage as specified in the contract would have been $1500. The court, however, *468 awarded a credit of $2400. The plaintiff claims that the award of the higher figure was erroneous in that there was no evidence to support an award greater than $1500.
As a general rule, contract damages are awarded to place the injured party in the same position as he would have been in had the contract been fully performed.
Bachman
v.
Fortuna,
In their cross-appeal the defendants press three basic claims. The first is that the court erred in refusing to hear testimony concerning their claim for damages for physical and emotional injuries *469 which they assert resulted from the plaintiff’s alleged breach of contract. Specifically, the court sustained the plaintiff’s objection to a question directed to the named defendant on his direct examination : “As a result of the delay in moving into your new house, did you suffer any emotional or physical reaction?” In pressing the claim for this question, the defendants asserted that the plaintiff had failed to notify them of the delay in obtaining a construction mortgage which resulted in “many months of lost time.” They represented to the court: “Now, we take the position that this failure was so wanton and so reckless and so really unnecessary as to almost be culpable and to bring us into the area of almost a tort.”
It is true that in certain limited circumstances compensable tort damages may arise from the breach of a duty which “may be the outgrowth of a contractual relationship between the parties.”
Urban
v.
Hartford Gas
Co.,
The defendants’ second claim is that the trial court erred in failing to award to them as damages the difference in cost between two mortgages. The named defendant testified that in June, 1965, he had received a commitment for a homeowner’s mortgage for $25,700 at 6 percent interest payable over twenty-five years. On August 18,1966, this commitment was cancelled, apparently because the house was not yet completely constructed and the well was contaminated. The defendants procured a new mortgage for $24,000 at 6% percent payable over twenty-five years. Over the objection of the plaintiff, testimony as to the cumulative difference in interest payments for twenty-five years was allowed, but the court subsequently omitted the difference from the judgment awarded on the counterclaim. This omission is claimed as error.
The court found not only that the delays caused by the plaintiff were not the sole cause of the defendants’ loss of their original mortgage commitment but that the parties orally agreed to a series of modifications in the plans and specifications which caused delay, and it expressly found that “[t]he lapse of time between the date of defendants’ first mortgage commitment and its revocation was due in part to delays caused by the plaintiff and in part to delays caused by the defendants.” It is axiomatic that the delay of one party may be excused where it is caused, at least in part, by the acts of the other party. See 13 Am. Jur. 2d 51-55, Building and Construction Contracts, §§ 48-51. We find no error in this portion of the court’s decision.
*471
The defendants’ final claim concerns the well which supplied water for the house. The court found that under the terms of the contract the liability of the plaintiff in providing a well was limited to $1000. The plaintiff drilled and connected a well, but after the defendants occupied the house it was discovered that the water in the well was not potable. This case differs materially from
Sasso
v.
Ayotte,
The judgment as rendered awarded $8765 to the plaintiff on the complaint and $5181.25 to the defendants on their counterclaim. As we have indicated, the only error we find was in the inclusion in the award to the defendants of the sum of $2400 *472 for the construction of a garage when there was no evidence to support an award for this item in excess of $1500.
There is error only in the amount of the judgment awarded to the defendants, and the ease is remanded with direction to reduce the judgment in favor of the defendants by the sum of $900.
In this opinion the other judges concurred.
