History
  • No items yet
midpage
Bernard Johnson, Inc. v. Continental Constructors, Inc.
630 S.W.2d 365
Tex. App.
1982
Check Treatment

*1 direct appeal, appeal this dismissed

want jurisdiction. Nothing this stated in however,

opinion, should construed to

рrejudice right attempt appeal provisions out-of-time 44.08(e)

of Tex.Code Crim.Pro.Ann. art.

(Vernon 1966). JOHNSON, INC., Appellant,

BERNARD CONSTRUCTORS,

CONTINENTAL

INC., Appellee.

No. 13522. Texas, of Appeals

Court

Austin.

Feb. 1982.

Rehearing April Denied

The appellant’s plea trial court denied privilege hearing appel- after and sustained controverting plea lee’s to the effect that County proper venue in Travis as to both exception defendants under four of exception provides, article 1995. That rath- simply purposes, er for our if two counties, defendants reside in different suit brought county where either Appellee proved pri- defendant resides. against Department, ma facie case County, “resident” of Travis and contends must, therefore, exception four, Ap- in the county. submit venue pellant interpretation resists based given exception Stockyards four in National v. Maples, Bank 95 S.W.2d (1936). Appellant appellee admits was not re- establish, evidence, quired extrinsic prima against appellant, facie case the non- defendant; rather, resident the issue of present venue in the circumstances must be solely upon рroposition this determined allegations appellee’s peti- law: Do the Anderson, Graves, John T. Dougherty, controverting plea tion and show a cause of Hearon, Garwood, Austin, Moody & ap- for (1) against appellant action which is either: pellant. joint against claim and the (2) Department; grow- a cause of action Pappas, Russell, Chris Wyckoff, C. Dunn ing so out of the same transaction and Frazier, Houston, for intimately against connected with the claim Department the two should be POWERS, Justice. joined under “the rule intended to avoid a Appellee, Constructors, Inc., Continental multiplicity of suits?” Id. sued, Texas, County, Travis the Texas An examination of controvert- Department Parks and Wildlife ing plea incorporates by reveals that it ref- Johnson, lant Bernard Inc. The suit arose ap- erence all the contained in out of construction of a bulkhead turn, pellee’s petition. petition, in as- at Lake Livingston, Texas under a contract Department, serts the resident between apрellee Department. defendant, two causes of action in contract: The contract called for construction of the (1) appellee fully performed the bulkhead plans specifications prepar- bulkhead to contract and its work thereunder had been ed by provi- and contained other finally accepted by Department; allegedly gave appellant sions which certain completion required the work extra fill architect/engi- and duties as “the appellee supplied; the bulk- material neer.” expressly required head contract the De- Appellant interposed plea privilege material; partment pay the extra County, to be sued in Harris its “residence” and, Department breached the bulkhead for venue purposes. it; Tex.Rev.Civ.Stat.Ann. pay by refusing art. 1995 The “residence” failed, although the bulkhead built to con- Department, purposes, for venue Travis plans specifications, whereupon County. Department re- requested it; further, alternative, build agent representa- Pleading unnamed and in the Defendant, Department tive of the represented that Plaintiff would show that the Johnson, Department Incorporated, Bernard failed to pay would for the rebuild- ing; bulkhead; responsibilities delegated and, rebuilt the Specifi- it under the Bulkhead Contract. breached this concomitant oral cally, properly said Defendant failed to contract by refusing pay the reasonable *3 supervise and administer the Bulkhead value of work in making the re- failure, Project. As a said result of such quested repairs. thereby Defendant breached said contract With alleged the claims by causing damages Plaintiff’s as herein ref- appellee against appellant, the non-resident erenced. defendant, petition reveals an intent to Appellee appellant does not contend be- allege a cause of action in negligence and generally came liable on the contract be- one for breаch of contract. appellee tween the Department. Nor In setting forth its claim negligence, appellee appellant does contend became appellee makes the following allegations: contractually appellee by bound to virtue of appellant engaged by was the Department express Rather, contract between them. to serve as architect on the bulkhead appellee appellant claims that because fur- project; appellant prepared the pertinent “job specifications” nished and assumed plans specifications; under the terms of obligations specifically assigned ap- contract, the bulkhead appellant was made pellant express ap- in the contract between responsible administration pellee Department, appellant there- of the contract as “representative” of by became contractually bound in favor of Department construction; and, during appellee obligations those with- negligent, the negligence be- Thus, out negligence. so far as we are able ing alleged in the following words: determine from briefs and Plaintiff would show that said Defendant rather allegations, appellee’s indistinct failed to properly administer the Bulk- ultimately claim is one for negligence only; Project. head Due to the failure of said negligence being to avoid such Defendant to properly process however, change said, (1) origin to have an either orders and administer Project, said Plain- express contract made appellee between tiff suffered extensive delays and the in- Department, in the common creased costs resulting therefrom. of negligence.1 Said law Defendant abrogated responsibilities its showing any Essential to “cause of ac- in supervising and administering the tion,” is, cognizable claim in the Project. Bulkhead The acts and/or omis- State, courts of our are allegations suffi- part sions on the of said Defendant con- cient to invoke a rule of substantive law stitute negligence as that term is under- which, alleged, under the circumstances stood in law. negligence proxi- Such vests in plaintiff right imposes mately caused damages, Plaintiff’s which upon the corresponding duty defendant a Plaintiff would greatly show exceed the which he has breached. MacDonald v. jurisdictional minimum limits of this Trammell, 163 Tex. S.W.2d court. (1962); Phoenix Lumber Co. Houston Appellee’s claim for breach of contract is Water S.W.

stated as 47; follows: McDonald, Texas Tex.R.Civ.P. put 1. One promissory assumption is hard to understand what in ex- of such duties argument appellant, by change intends as- No form of consideration. suming upon any the duties to it in the claim is made that relied thereby appellee; express implied promise became liable in contract to relevant the made proposition and there is appellee’s appellant. put no citation for that We the best face we can on appeal. nothing aрpellee’s pleading briefs on There is and briefs when we state appellant’s suggests proposition opinion. or briefs which in the text of the id., care, skill, expedience, and Civil Practice (rev.1981); degree site 2.02 § faithfulness, factual alle- the matters which were as- plaintiff’s 6.12. Whether gations right, express set forth a and a signed except by breach cannot be determined ref- Ap- between the erence to the substantive law. We inquire provi- refers to these contract pellee’s brief requisite duty first whether on them in their quotes some of sions and part lant’s arisen force of a could have entirety. It is inconceivable admittedly to which he was not a against appellant could maintain its action ordinary sense. the contents of the proving without at trial resulting contract and the bulkhead A DUTY BASED UPON CONTRACT upon appellee therein. placed said to be cases, sub- any action is said to be in appellee’s allega The substance of contract, even an action on the tiоns, stance liberally interpret when we them and *4 neg- intendment, it is an action supply though is that denominated every reasonable Inter- ligent performance of the contract.2 appellant perform requi- failed to with the ments, should, appellee point, clarify forth a cause of has not set 2. We at this several mat- statutory question appellant’s of invoked a rule of as to defeat ters which bear the ultimate action so county appellee’s pleadings privilege of its “resi- whether the substantive could be liable to to be sued appellant law under which dence.” artfully appellee is not whether has issue example, pleaded it is of For a cause action. Appellee’s petition controverting plea nei- and whether, appellant suggests, ap- as immaterial pellee any provision in the ther set forth nor refer to allege a of an element of cause failed to places upon appellant which bulkhead contrаct Rather, negligence. issue is action for fact, specific duty. only specific a act of appellee’s allegations, taken as when whether negligence alleged by appellant appellee is that true, invoke a rule of substantive law properly “process” change failed to We the orders. wrong appellee it will relief to for the afford purposes for the of that assume discussion appellant. attributes to Under the not consider the actual contract aid of required appellant to bulkhead contract case, may Stockyards we rule of “process” remaining allega- such orders. The provisions in negligence by appellee tions of made are that although appellee’s allegations, the con- appellant negligently performed general at the was introduced in evidence tract itself “supervise” to “administer” contract and hearing part of the and is before us as venue project. appellant failed the bulkhead to take Because Depart- proved against prima facie case exception generality special of ment, The issue before the resident defendant. general negligence, these claims of we are de- venue, deter- to be us is one not of mined prived interpretative rule that of the valuable allega- solely by reference specific negligence, allegation re- the one of practicality justice as- orders, of this tions. The specting “processing” change Stockyards questioned pect been has allegations accordingly. general limits the more appellate ignored some intermediate even courts. 354. We note pellant’s Lawyers Corp., Stone v. Title Ins. 554 S.W.2d McDonald, 4.10.1, supra, at 353- (Tex.1977). n Nevertheless, appellant objected at the venue alleges ap- immediately that hearing rela- that there existed no contractual assigned obligations were contractual tionship appellant appellee, and between Department, “representative” as of the to it with the that connection was owed any duty by appellant that owed claimed any duty necessary implication (the Depart- “runs” to the “State of Texas” Department ment). Appellant try by therefore did not con- Appellee also intended for its benefit. “duty” question. aspects sent Buchanan v. 688 the of the See those “delegat- responsibilities alleges were that such Jean, 141 Tex. 172 S.W.2d appellant by Department. must We ed” to assume the truth antithetical (1943),evaluating in similar circumstances They allegations. are of these plaintiffs controverting plea as to whether contracting being appellant trespass it “set out action” Moreover, appel- ordinary party sense. tempted exception nine of article 1995. We are intend to that it did not briefs make clear lee’s allege appellant rehearing to remand the case for venue party the con- was such quеstion presentation of the confused because Department. appellee and the us, between in Buchan- of the issues before as was done allegations, general lib- Nevertheless, thrust of proceed The erally interpreted, an. as best we can negligently us, pri- is that under the marily upon we have before pow- supervisory very one or more of exercised ers sometimes the basis that even under the assigned in similar by ap- to architects general allegations pellee, negligence made vary in kind and supplying Such intend- contracts. all reasonable Printing national Pressman & sentative” of the Department. Assistants’ If Smith, Union v. negligent 198 S.W.2d was indeed in the performance of (1947). any duty assigned to in the bulkhead imputed would be rule, As a a suit to the Department. Then the breach of not be maintained therefore, just Montgom would be liable person who is not a party to the ery Ward & Co. held liable contract, particularly a non-party who is repairman’s negligence performance in his duties the terms of the con obligation contractual owed Mont tract. George, Jones v. 61 Tex. 345 gomery Ward & Co. in This Scharrenbeck. Carruth v. Valley Ready-Mix ‍‌‌‌​‌​​‌‌‌​​‌​​​​‌​​‌​​​‌​​​​​‌‌‌‌‌‌‌​‌​​​​‌‌‌​​‍Concrete however, say, is not to would 221 S.W.2d 584 (Tex.Civ.App. — Eastland liable for his own because of ref’d); writ 17A C.J.S. Contracts said to arise from his contractual §§ As between the con undertaking. Appellant, being a con themselves, tracting parties it is well estab tracting party, promised nothing lished that each owes a duty to the other to implication which could be erected the perform care, contractual obligations with of law that promised he also skill, expedience reasonable and faithful provision negligence.3 without ness, either personally through one for Any appellant’s on part must obliged whom the responsible. A originate therefore not in contract between breach gives that case rise to a others but in the common law. *5 cause of action for negligence against other contracting party. Montgomery It perti is well understood that a Ward & Scharrenbeck, Co. v. 146 Tex. nent may significance contract have with (1947). Here, S.W.2d 508 it is not al duty relationship to a imposed and leged appellant was a “contracting party,” governed by the common law. For exam though in appellee’s briefs we are ap ple, told plaintiff who is a party to a pellant somehow contractually became obli may contract sue a defendant who is a gated to appellee on at least answer, some of the contracting party. In the defend terms. We draw may plead ant any duty he owes is one sparse allegations that appellant was another, al solely by created his contract with legedly negligent capacity his “repre- owed; as and, to whom alone the duty is be- degree. They vary degree negligence, sometimes notwithstanding negli- to own that his they such actually an extent that are different gence may imputed employer be to his or his point, Manett, example, kind. We to principal respondeat under the doctrine of su- Bldg. Corp., Seastrunk & Buckner v. Terminal perior, making the latter liable as well. In this (1931), 120 Tex. 39 S.W.2d 1 where the appeal, original question we deal with the contracting parties assigned to the architect is, be, duty imposed upon whether a or should specific provision arbitrary powers, corollary with a actor, law; or, the tract under con- required which that the architect be law, duty whether such a was undertaken neutral and disinterested as between the con- by the actor’s contract. tracting parties. hand, On the other the archi- relating The substantive to law breaches of may actually tect be a mere consultant to one contract, society’s exists because of interest contracting party other, or the with no actual having perform person promises, whether power parties. contracting at all over the work or the express reason, implied or in fact or law. For this possible relationships Other between architect, actions for breach of contract are inher- the parties contracting the work and the ently possible against promissors only. pointed opin- are out in the text of the case, upon present given ion. In substantive law of ty’s rests socie- the nature of appellee’s allegations, conjecture it would be evaluation and conclusion that certain in- part on particular Thus, our to negli- assume the existence terests gence be should free from harm. relationship kind of the exist- law formulates and sets rules of conduct any specific power appellant ence of vested in interests, protect which are enforced to by the terms of the contract. ordinarily without will in- reference to the parties. tention of the affected duty imposed by 3. For breach of a the common protection public law for the benefit or at large, employee agent is held liable for his party not a to the contract. Jones v. “privity

cause of сontract” exists be- no Valley Ready- he owes no plaintiff, George, supra; tween himself and the Carruth C.J.S., plaintiff upon Co., supra. which supra; 17A Mix Concrete not the may predicated.4 action Such legal was not in contem- Because instance, case before us. In this a contract- contract, no it owed plation party (ap- ing party (appellee) sues a defendant However, contract-based pellant) party who is not a light, viewed in its most favorable upon founded said to have arisen con- also be viewed as argument may lee’s provisions required virtue of contract which ought there tending proposition non-party defendant certain duty placed upon the be a common-law Appellee pertinent raises the con- tasks. not a con- though even it was appellant, impose liability; appel- tract as a sword had, and because tracting party, lant does not raise it as a shield from liabili- exercised, affirmatively contol over ty. Appellant interpose “privity does virtue of process by in the construction defense, contract” as a in a far differ- provisions. unspecified certain but sense, saying ent in effect: “I was not a liberally interpreted, Appellee’s allegations, plain- to the contract which the argument. will allow the sues; therefore, not, by my prom- tiff I did ise, obligate myself respecting to him THE A DUTY BASED UPON words, duty upon he In other sues.” LAW COMMON contends, correct- believe enforced, reported cases We from the know ly, may contractual duties not be circumstances, contracts between building who is and construction in these one (Second) Torts which deline- 4. House v. Houston Waterworks (1895); City of Wichita Fails of one who furnishes S.W. 179 ates the Swartz, (Tex.Civ.App. persons 57 S.W.2d 236 who fore- information to business —Fort Rev., writ); truth, Tex.Jur.2d Part Worth rely seeably the information. Negligence, 9§ holding precedent in Texas for there was “privity” permitted in misrepresenta- The defense of is not doctrine of innocent under the tion, personal injury, suits whether Note, pointed out in Torts —Profession- *6 upon upon a claim of a claim of or May Negligence be Liable al —Accountants is, liability, liability regard to strict that without Negligence, Texas L.Rev. Third Parties for 50 Gehring, S.W.2d 787 fault. Strakos v. 360 “Privity (1972). un- survives 411 of contract” Co., (Tex.1962); Darryl 440 v. Ford Motor lawyers in favor of as a defense diminished (Second) (Tex.1969); S.W.2d 630 Restatement injury by parties said for economic sued third (1965). What then of suits § of Torts 324A by proximately the law- been caused to have injury seeking recovery for an economic yer’s negligent performance under his contract brought by appellee one not as the suit Manning, 613 S.W.2d Beil v. with his client. to the contract? 1981, (Tex.Civ.App. Tyler n.r. writ refd 335 e.); Bryan — may any duty It is that in such a case obvious Law, 587 435 S.W.2d Amidei v. & others, not arise out of the contract between 1968, writ); (Tex.Civ.App. Worth —Fort may reasonably but it be said that a contract Trevino, (Tex.Civ. S.W.2d 763 Martin v. 578 of affairs between others has created a state n.r.e.); 1978, App. Corpus writ refd Christi — ought law where there to be a common Note, Attorney-Client Negligence—An Attor- may by — be affeсted the care in favor of one who May ney Parties for Mal- be Liable to Third contracting of a attendant acts or omissions party. Contract, Privity v. practice Lucas Without appellate court One Texas intermediate 821, 583, Cal.Rptr. 364 15 accountant, may 56 Cal.2d example, Hamm, has that an held (1961), negligent per- (1962). parties P.2d 685 be liable to third for his 1046 40 Texas L.Rev. “privity having of a contractual owed to formance of contract” The defense ‍‌‌‌​‌​​‌‌‌​​‌​​​​‌​​‌​​​‌​​​​​‌‌‌‌‌‌‌​‌​​​​‌‌‌​​‍of client, “privity may law, contract” not by and that it obvi- the common been established action, interposed by to such an by be as a defense may the ously or abolished statute injury. brought for an economic judicially recover the defense law. When common James, Shatterproof Corp. 466 S.W.2d v. Glass abolished, carefully and under task is done the 1971, (Tex.Civ.App. writ refd 873 n.r.e.). Worth policy. upon public Id. —Fort a rationale in case was asserted that Supreme Court Texas not find that the We do demonstrably law, originating in the common one in suits generally doctrine abolished the has scope specifically limited the for the court negli- upon brought by parties the third based to, jurisprudential of such and found its gent performance of a contract in, provisions of the Restatement basis the

371 (the drawn, Department here) carefully owner a con- professionally and and and here), tractor (appellee may in vary greatly specifications are clear and from powers assigned super- and duties to a precise, is an that ac- incidental benefit vising by agreement architect of the con- crues to contractor. tracting parties. The authority architect’s Rolland, Co., Landscape v. Valley Inc. 218 parties connection with and the work 120, Va. 237 122-123 S.E.2d varies accordingly.5 words, generally speaking, any duty other any If generality expressed can be with power assigned to the architect to the capacity assigned the su- building contract is for the benefit of the pervising contracting par- architect employed owner who the architect. ties, might perhaps be this: jurisdictions judicial- some have Courts in The duty of the architect protect is to ly upon duty of imposed architects a ordi- owner to the end that of the quality nary in favor of care the contractor. These workmanship goes into project, power courts done so have based quality kind and of the materials possessed over the contractor said to be used, that are will be in accordance with the architect. We find of these some cases the plans specifications upon which lacking logical analysis; particularly be- the owner agreed. and architect have they ignore cause what seems us fun- undertakings These by the architect are proposition: protect damental the architect’s rela- designed to and enhance the profit parties tion to the and the work is one other interest of con- tractor. The specified by fact will contracting parties contractor their profit benefit and plans bargained-for agreement.6 that are long as the So See, Lonergan agreement owner); v. San Antonio Loan Trust & contractor Co., (1907) (imply Eisele, Assoc., Tex. 104 S.W. 1061 & Conforti Inc. v. John C. Morris ing to, merely that the architect was a consultant N.J.Super. 341, (1980) (im- 418 A.2d 1290 of, representative the owner acted posing duty upon “design professional” solely, for his benefit others interested in the and not for the benefit of status, apparently upon ground the sole of his Manett, work); Seas assumptions stated indi- with Corp., trunk Building & Buckner Terminal upon the cate an unarticulated reliance supra (setting forth the other where extreme action, of untary assumption based the affirmative and vol- expressly required the architect was to be a duty, of a out in Restate- set large neutral and disinterested arbiter dis with (Second) (1965)); ment of Torts or 324 cretionary powers in relation to the construc Assoc, Normoyle-Berg Village of Deer work); City tion of San Antonio v. McKenzie Creek, Ill.App.3d N.E.2d 559 Co., Construction 136Tex. S.W.2d (apparently solely upon based the status of the (1941) (whеre the contract between the owner engineer and without to his reference engineer and the contractor to an contract), under the as was the case duties decision-making of arbitration and Bros., *7 in Detweiler Inc. Graham v. John & particulars involving numerous tion the construc 1976); and, F.Supp. (E.D.Wash. 412 416 David- work, holding engineer’s the court that the Hanover, County son v. 41 & Jones of New duty to make a decision is owed to both con 661, (1979) (based N.C.App. 255 S.E.2d 580 tracting parties, engineer’s the and failure to upon working relationship the of the contractor decision, so, requested make a not when to do does architect, and building but without reference to the prohibit by estoppel making his a later decision, pleaded having it not been in and later such decision be set not case). judicial conduct, aside in allow the of his review so as to recovery by against the contractor the contrast, following In the decisions make at owner, except showing aon that the decision inquiry assigned least some into the role to the fraud, was the result of misconduct or by contracting parties: Krieger architect the v. gross part imply mistake as would bad faith on the Co., Inc., 50, J. E. 282 Md. 382 A.2d Greiner architect). Stevens, (1978) and 1069 Vonasek v. Hirsch & Inc., 1, (1974), 221 815 both 65 Wis.2d N.W.2d See, e.g., Moyer, Graham, A. R. Inc. v. 285 of looked to if the contract determine 1973) (Fla. (holding So.2d 397 in a answer duty assigned had been a in favor the architect of question certified requisite duty that the architect had the specific plaintiff respect with to the the corollary power as a of the him; and, complained by Craig wrong of supervision belonging direct architect, and control to the Co., Mass. Everett M. Brooks degree without reference to the of (1967), separate looking con- N.E.2d 752 to two such control or the nature of it as established contracting parties presump- rule should not be founded have freedom to con- wish, power tion that the architect has over the they respect with to the ar- general or in performance, contractor’s in role, vary chitect’s and these will any particular of the work. considerably general applica- and no rule of bility may logically be which is stated Appellee argues that a should be simply upon the status of the de- imposed upon just corollary architects as a fendant as “an architect” or what contractors, one they to the control exert over Graham, supra, customary relationship believes to be the Moyer, A. R. Inc. v. citing work, architect, Rogers Rogers, and United between the the the owner States contractor; (S.D.Cal.1958).7 particularly F.Supp. any provisions tracts to determine if reflected a Dame Law. A well-reasoned by holding assumed the Malpractice: architect and the A article is Architectural Con- negligence architect in liable on the basis that it Approach, tract-Based 92 Harv.L.Rev. reasonably was would foreseeable that the contractor (1979) recognizing variety relationships rely upon non-negligent the architect’s owner, possible the contractor and between the performance duty assigned of a to him in the architect, often the different role contract. times, in the insufficien- to the architect cy recent Eng’rs. Associated Architects & v. Lubbock assigning stereotype to ‍‌‌‌​‌​​‌‌‌​​‌​​​​‌​​‌​​​‌​​​​​‌‌‌‌‌‌‌​‌​​​​‌‌‌​​‍the architect a (Tex.Civ. Glass & Mirror 422 S.W.2d 942 upon conjecture suggesting that based and App. e.), ref’d n. r. in- writ —Amarillo relationships many take so since “architectural negligence brought volved two claims of forms, appropriate it is much to allocate more sub-contractor, the architect parties’ risks on the basis of the contracts as preparation plans first for modified their later conduct.” The writer of specifications negli- and gence and the second for allowing this article advocates the contractor rejecting skylights according in furnished in two situations: action for plans specifica- to the architect’s defective and (1) duty of where the architect breaches the tions, being seemingly the claims allowed as a imposed upon performance of him in his care provision matter of course and with no discussion of the architect’s contract contained duty question, point unless that be the owner, reasonably with the when it is foreseea- preserved court declined to discuss by point because rely upon that ble that the contractor would undertaking by architect, Systems, of error. In I. I. Inc. v. O. architect; Cleveland, City and where the (Tex.Civ. 615 S.W.2d 786 conduct, responsi- App. assumes a writ refd n.r. issue with the [1st Dist.] —Houston e.), bility, reasonably the court referred wherein it is foreseeable that engineer’s duty depends rely upon non-negli- comment that upon the contractor would gent performance particular agreement “the entered into undertaking by of that is, employer,” with his tween the the contract be- Id., at 1085-86. architect. engineer and the owner. The court case, present In the we note from suspended the with discussion the comment any way rely that it does not that the contractor failed to offer evidence that upon any provisions contained engineer unreasonable the cir- agreement between the cumstances, compliance or not in with the skill fact, appellee lant. does not mention the requirements registered engineers. terms of that contract nor otherwise refer to it. widely importance The text writers differ they assign provisions would to the contract case, 7. In the latter the court stated: contractor, agreed upon by the owner and the policy impel Considerations of reason the with to the architect’s authority position that the conclusion duties, particularly resulting he “control” supervising of a ought architect are such that he has the circumstances in which the contrac- prime labor under a injury alleged tor’s economic curred. The writer’s to have oc- supervise project due contractor to with opinions vary ignor- circumstances, though even care under the ing provisions altogether giving the contract relationshiр is with the his sole contractual Davidson, controlling Compare them effect. *8 Altogether too much control owner.... over the contractor Architects, Liability (June The 13 Trial necessarily in the rests 1977) Allen, Liability and of Architects and supervising for him hands of the architect Parties, Engineers to Third Ark.L.Rev. 454 (under duty). placed such a not to be (1968), taking opposing positions. these Some stop the work alone factors, of the architect to propose an orchestration of various power of economic life or including is tantamount to a applicable provisions. the J. only just Acret, It is Engineers: death over the contractor. Architects and Their Profes- authority, such a relation- Responsibilities, such ship, exercised in sional 10.2 & 10.3 §§ carry legal responsibili- Earley, Liability Engineers commensurate of Architects and to ty. New-Approach, Third A Parties: 53 Notre Appellee’s brief contractor, informs us that the con- care to a who labors under a gave appellant owner, duties which “аllowed contract between himself and the the great architect latitude in controlling assigns when the contract to the architect the labor Project.” force on the Bulkhead supervision the and administration Appellee quotes provisions five from the project representative the the own- er, contract between Department the ap- and the architect is not himself a con- pellee which are claimed to tracting party. Similarly, appellee’s illustrate this brief kind of working relationship between the makes clear its contention that the contracting parties argued and appellant. As for it need not be connected earlier, not, mentioned any specific power we may in this ven- to the architect ue appeal, provisions consider contract.9 The sum and of this substance of contract, appellee’s argument introduced is prove prima this facie case essential defendant, but unarticulated syllogism: resident Deрartment. The Stockyards prohibits case All architects control the work of the our doing contractor; so.8 architect; appellant is an therefore, appellant controlled the con- Nevertheless, appellee’s brief makes suf- project. tractor’s work on the bulkhead ficiently clear the intention of pleadings its against appellant. deduced, The inten- From the control so tion was to invoke a rule of the urges common this Court to make the legal determi- law —one admittedly yet not promulgated nation that a placed upon should be by the Supreme Court of appellant Texas —which and architects generally, based would hold that an architect owes a perhaps social, economic, upon the and mor- F.Supp. at contracting party, 135-136. But see 92 Harv.L. and in each instance where Rev., (criticizing Rogers Rogers). at 1085 appellant & assigned right duty, it is protection manifest that he exercises it for the Appellee quotes provisiоns 8. incorporate which Department only. or accommodation of the into the plans appellant’s contract documents the nothing suggesting There is in the contract specifications; require appellant and power part appellant stop any the work or approve, owner, any samples with the and Moreover, expressly shop of it. drawings the contract required by the contract docu- ments; “solely responsible appellant makes the all sequences itself repre- make the owner’s means, methods, during construction, techniques, authority sentative act construction with provided procedure, coordinating owner to the extent and for documents, portions unless otherwise modified all of the work.” The contract be- by written instrument which shall be shown to appellant Department tween and the is not (appellant); provide ap- contractor that the incorporated reference appellee in the contraсt between pellant “will advise and consult with the owner Department, despite appellee’s (the all the owner’s instructions to contrac- contrary. assertion to the will) tor provide through (appellant); be issued Rogers The rationale of United States v. verify that the shall the sub- Rogers, supra, applicable is therefore not to the completion project, stantial following of the case, present any power actually given ap- days the owner will within ten calendar pellant severely here is limited and unrelated to inspection make a final and when the work is alleged. importantly, the circumstances More acceptable found ments, under the contract docu- give weight were we to to that it fully performed, and the contract is entirely must refute the claim payment. owner will make a final “great brief that was allowed give any weight Were of appellee, provisions we to controlling latitude in the labor force on the Department the contrаct between the Project” entirely Bulkhead subvert do, which we we would find argument lee’s for a new rule of the common that, entirety, assigns approximately law based an architect’s control of the specific nine matters to the attention of the work, at least insofar as the contract here in- (appellant), only give architect three of which volved is advanced as an illustration of the kind any power the architect at all over the contrac- of control said to necessitate the new common (appellee); tor and that these are insub- law rule. stantial or bear no connection whatever to the alleged given circumstances to have rise to Any negligence processing with appellee’s injury. Otherwise, within its four change manifestly orders is a claim founded corners, unquestionably the contract makes the solely upon a contract-based representative Department to do what itself do as a could *9 grounds al course, sometimеs cited in decisions in opportunities Of the architect’s jurisdictions other justification as for im- proportionately increase posing such a Appellee’s reasoning cases given where the architect plenary ignores the allegation contained in its own contractor, power over provision as in a pleading any supervisory or adminis- assigns which power to an architect trative authority assigned to the means, methods, prescribe the techniques, case, it, in this exercised was in sequences procedure of construction appellant’s capacity representative as of the and to coordinate all parts of the work. owner, without explaining why appellee then, however, Even questions bedrock should not be bound by expression remain: contracting parties assign did the contractual intent. More importantly, how- ever, such plenary power to the brief, architect for the reasoning in its and in the conclusion it reach, would have ig- us benefit of the owner only or for both con- nores the proposition that major premise or, tracting parties; should a care (“all architects control the work of the con- imposed upon be the architect in favor of tractor”) can never universally be true. notwithstanding contractor the inten- The contracting parties, they if assign any tions of contracting parties? power architect, at all may assign readily We possession concede that of a degree kind or they control deem power, another, of one may kind or furnish necessary or desirable in the circumstances. Appellant’s reasoning jurisprudential is therefore uncon- a imposing upon basis for vincing. empowered the one so corresponding duty of exercising ordinary it with care toward

As indicated previously, jurisdic- some tions adopted and, upon have those whom it generally, works. theory See apparently, have even promulgated gen- The Duty to Act Shapo, M. In the eral arсhitects, rule that merely upon based us, however, case before as by appel- made status as their architects, upon or based allegations, lee’s is specifically alleged stereotype court, of architects held by the was, that appellant under the terms of the owe a duty of care to the contractor in the bulkhead “representa- made the circumstances we have before us in this Department. public tive” of the We see no case. We find no such rule of substantive policy why contracting parties reasons law in jurisprudence of our State. We may not so limit or qualify appellant’s rela- may ourselves, not promulgate it as dis- tionship to themselves and to the work and cussed below. why interpret we should not so any power We do not see general how a rule of relied upon appellee as a basis for its claim. application may be stated of the ar- kind Therefore, appellee’s pleadings even if gued appellee. When shall reasonably interpreted be implying spe- amount and kind of control be deemed suf- cific or general power assigned appellant, ficient to impose the duty? May any kind power is relevant to the specific cir- degree of control in particular cumstances giving appellee’s injuries rise to sufficient, no matter how minimal or (which we do not believe the are unrelated to the injury alleged? Any such general rule of application, do), based an sufficient that power qualified assumed control of the architect so as to be for the accommodation and contractor, over the invariably must result protection and not for injustice particular an in a case when the benefit of assigns no control to the architect Though parties, not raised with respect particular to a aspect of the point possible out that it is for one to incur contractor’s work occurs, wherein the injury another, of care toward in certain is, nevertheless, the architect held to a circumstances, simply by the former’s em- general duty said to be justified barking upon undertaking. Restate- by the existence of his over the contractor. (Second) ment of Torts 324A §§

375 (1965).10 Supreme imposed power necessary Our Court has to create a new and a the requirement, however, that a cause of new cause of action in the circumstances negligence action for alleged, does not exist in such where Supreme the Court of Texas circumstances unless the affirmative under has established and never contrary revoked taking pursued is for the benefit of the one legal principles, being applicable there injured by and, negligent performance; statute which either authorizes the action requirement additional injured that the or principles. otherwise disestablishes such person must have injury suffered not from State, Refining Humble & v. Oil Co. 158 merely but from his reliance 1942, (Tex.Civ.App. S.W.2d 336 — Austin upon the undertaking. Savings Colonial ref’d). writ It is our under the com Taylor, Association v. (Tex. 544 116 S.W.2d decisis, mon law doctrine of stare as it was 1976). Given the by ap- made court, of the trial to follow the pellee, it would be pure conjecture and Supreme decisions of Court of Texas therefore unreasonable for us to conclude directly (1) which are on point, ‍‌‌‌​‌​​‌‌‌​​‌​​​​‌​​‌​​​‌​​​​​‌‌‌‌‌‌‌​‌​​​​‌‌‌​​‍viz. If the appellee intended plead such a cause of action is not maintainable pleading without action. While we would missing assume a contract, proving gist of element any cause of action inartfully the action is for breach of the pleaded, we do not believe we can reason nonfeasance, by either malfeasance or it is ably every assume element of a cause of substance an action for action antithetical to the pleadings. contract; performance of the International

With respect Printing then to Pressmen & Assistants’ alle Union gations negligence, Smith, (2) we supra; hold that its alle a suit for breach of con gations did not invoke a may rule of substantive not be per maintained a law, applicable circumstances, contract; to the son who is not a rule vests in appellee right a impos George, supra; Jones v. Valley Carruth v. es the defendant a corresponding Ready-Mix Co., if, supra; Concrete alleged, impos circumstances the law es no duty upon pro the defendant for the As an additional ground for our tection plaintiff, any act or omission holding allegations have not by the defendant does not amount to ac invoked a rule of the substantive law which negligence. tionable Light Denison & Pow places right, a and in Patton, 621, er v.Co. 154 540 S.W. corresponding duty, we cite the proper role (1913). court, this appellate intermediate insofar requests us to create a new foregoing We believe the established of the kind contended for by appellee. principles This possibility defeat the Court not judicial exercise the action, raw injury, for economic said provides: 10. Section involving 323 injury ment in cases economic physicаl Ajax Mfg. Corp. harm. Hardware undertakes, gratuitously One who or for con- Corp., (2nd v. Industrial Plants 181 sideration, 569 F.2d to render services to another Ball, Hunt, Hart, 1977); Cir. Roberts v. Brown recognize necessary which he should as person Baerwitz, Cal.App.3d Cal.Rptr. 57 protection things, of the other’s (1976); Co., Holding Abel subject Inc. Amer. liability physical to the other for N.J.Super. Dist. Tel. resulting A.2d harm from his failure to exercise Greenfield, Schwartz v. Stein & Weis- undertaking, reasonable care to his (a) inger, if 90 Misc.2d N.Y.S.2d 582 failure to exercise such care increas- Taylor imposed liability harm, (b) es case cited above the risk of such the harm is fire, by clearly suffered for destruction of a house case because of the other’s reliance physical undertaking. plaintiffs “thing.” harm imposes imposed important Section 324A That case also condition similar physical person undertaking harm suffered that the defendant’s affirmative third when actor, circumstances, plaintiff. in similar undertakes benefit of the We are not Taylor opinion to render services fоr another. informed whether By analogy, suppose, encompasses some have al- courts relevant cause of action economic recovery theory injury. lowed under the of the Restate- Rolland, arise virtue of duty imposed in the Co. v. 218 Va. 237 S.E.2d 120 *11 common (1977); law or the contract between Blecick v. District School No. 18 of 115, the Department, County, Cochise 2 ap- Ariz.App. 406 P.2d pellant 750 was not a party. my judgment, In the cases where a duty Holding as do appellee’s allega- that upheld has been are the better reasoned action,” tions do set forth a of “cause Rogers cases. Rog United States v. required we are not to address the interest- ers, 132, F.Supp. (S.D.Calif. 161 135-136 ing issue of whether such claim is a 1958), the court stated: “joint” of action to brought of policy impel Consideration reason and against Department, or a cause position conclusion that and au- of action so intimately connected with the thority supervising of architect are such joined other that twо may “under ought that he to labor under a the rule intended to multiplicity avoid a prime supervise contractor Stockyards suits.” Bank National v. Ma- project with due care under the circum- ples, supra. stances, though even his sole contractual reasons, For foregoing we reverse the relationship owner, is with the . .. Alto- order of the trial court and remand the gether much too control over the contrac- cause for severance of against the claims necessarily tor rests in the hands of the appellant and their transfer to Harris Coun- supervising architect for him not to be

ty, county appellant’s “residence.” placed under a imposed by law to perform without functions PHILLIPS, Justice, Chief dissenting. as they affect contractor. The It is for difficult me to understand how stop architect to the work alone is hold, law, can majority as matter tantamount to a power of economic life that an responsible architect who is or death over the contractor. It is only directing building project just is immune authority, exercised in such all liability tort relationship, carry to a legal contractor whose work commensurate responsibility. he is supervising. especially This is so where impression the case is one of first in also, See v. John Morris Conforti C. Associ Texas and the better reasoned cases in oth- ates, N.J.Super. 175 418 A.2d 1290 jurisdictions er contrary. are to the Conse- Industries, (1980); Shoffner Inc. v. W. B. quently, I dissent from majority hold- Lloyd N.C.App. Construction 42 ing. (N.C.1979); 257 S.E.2d 50 cert. denied Graham, A. R. Inc. Moyer, 285 397 So.2d specifications the bulkhead (Fla.1973). project require provide gen- architect My join “pro-duty” decision to line of eral administration of the contract as the cases is bolstered Texas recent deci Texas Department’s Parks Wildlife rep- Systems, City sion. I. O. I. Inc. v. Cleve resentative. land, (Tex.Civ.App 786 S.W.2d . —Hous There is no Texas case which decides the e.). ton writ ref’d n. r. [1st Dist.] us, question before as to whether an archi- Here, brought a contractor suit tect engineer or owes a in tort to a architect/engineer and others. The Court prime contractor, where on the held no no because of breach of part of the architect engineer or causes the But, the Court assume did that a prime damage. contractor economic duty of skill reasonable care and does run jurisdictions Other are divided on this architect/engineer from an to the contrac question; however, I find that the “no tor: offered witnesses “[the contractor] duty” no policy justifications cases offer city’s to show Ufer’s [the architect] See, rationale. Harbor Inc. v. Mechanical conduct was unreasonable the cir Electric, (D.Ariz. Arizona F.Supp. cumstances, compliance not in with the 1980); Slifer, Wheeler & Lewis v. requirements registered engi Colo. skill and Valley P.2d neers.” Landscape 615 S.W.2d at 790. I conclude that appellant did owe a appellee. ‍‌‌‌​‌​​‌‌‌​​‌​​​​‌​​‌​​​‌​​​​​‌‌‌‌‌‌‌​‌​​​​‌‌‌​​‍Consequent- reasonable care to

ly, a cause of action tort was stated

appellee’s petition venue proper County.

Travis

Because I appellee properly find that tort,

stated a cause of action I need not

consider appellee’s contract claim for venue

purposes. Nevertheless, is well estab plaintiff,

lished that a good who in faith joinable against

asserts claims the same de

fendant, can maintain venue all those county

claims in a proper where venue is Valley one claim. Brazos Harvestore

Systems, Beavers, Inc. v. 535 S.W.2d 797

(Tex.Civ.App. Tyler dism’d); writ — Middlebrook Bradley v. David Manufactur

ing 26 S.W. 935 McDonald, Texas Practice Civil 4.38

(rev’d 1981).

Appellee has shown itself to be within

subdivision 4 of article 1995. Venue as to against

Continental’s claim Bernard John

son is proper in County. Travis Conse

quently, a severance Continental’s

claim the other defendants is not

necessary. Such a decision would serve to

further our general policy state’s of avoid

ing a multiplicity suits. Boyd v. San Bank,

Antonio National 171 S.W.2d 375

(Tex.Civ.App. 1943, writ); Antonio — San Willson, Stevens Tex. 39 S.W.2d CRAWFORD, al., Appellants,

Glacier et INCORPORATED,

PULLMAN et

al., Appellees.

No. C2939. Texas,

Court of Appeals (14th Dist.).

Houston

Feb. Levit, Bel-

Abraham Levit and Soffar laire, appellants.

Case Details

Case Name: Bernard Johnson, Inc. v. Continental Constructors, Inc.
Court Name: Court of Appeals of Texas
Date Published: Feb 10, 1982
Citation: 630 S.W.2d 365
Docket Number: 13522
Court Abbreviation: Tex. App.
AI-generated responses must be verified and are not legal advice.