310 Mass. 651 | Mass. | 1942
This is an appeal from the order of the Appellate Division for the Northern District dismissing the report of the trial judge, who found for the defendant on the ground stated that it was not negligent. The first count of the plaintiff’s declaration is for negligence, the second is for a nuisance based upon the violation of G. L. (Ter. Ed.) c. 164, § 70, and the third is for nuisance in that the defendant unlawfully made an excavation in a public way.
There was evidence that at about 10:40 a.m. on Saturday, December 30, 1939, a service man of the defendant went to a house where it had been notified that gas was leaking. Some time later in the morning the matter was referred to the defendant’s main office, and, before noon, the defendant began to dig a trench in one of the public streets of Newton, and found a leak in the gas main that constituted a dangerous condition. The defendant neither sought nor obtained any permit to open the trench. The city hall was closed from noon on Saturday until the Tuesday following. The main was repaired, and the defendant “back-filled” the trench on January 3. At about 12:30 a.m. on January 15, when it was raining very hard and had been raining for hours, the plaintiff sustained injuries when the automobile that he was operating went into a hole that was two feet by two feet in area and one foot in depth around which there were no safeguards. Although the evidence does not so state, the parties have assumed, and the trial judge found, that this hole was where the defendant had excavated some two weeks before. Although the surround
The trial judge refused to give several of the plaintiff’s requests for rulings, and in each instance gave his reasons therefor. We are of opinion that there was error as to the second request, and, inasmuch as there must be a new trial and as the consideration of this second request necessarily deals with some of the questions involved in the other requests, it is unnecessary to consider them.
The second request was that there was evidence to warrant a finding for the plaintiff. The judge denied this request “because . . . [he found] as a fact that the. defendant was not negligent.” It is unnecessary to consider whether the request comes within the purview of Rule 27 of the District Courts (1940), requiring specification. It was reviewed by the Appellate Division and is before this court on this appeal. Milmore v. Landau, 307 Mass. 589, 590, and cases cited. The request was proper, and it was error to deny it, unless, as matter of law, it was inapplicable, or unless the judge, by clear and definite findings, has demonstrated that it was inapplicable or immaterial because of the findings. Home Savings Bank v. Savransky, 307 Mass. 601, 603, 604, and cases cited. Where, as here, the plaintiff alleged as one ground of recovery that the defendant had created a nuisance that caused the plaintiff’s injuries, it is apparent that the reason given by the trial judge for the
General Laws (Ter. Ed.) c. 164, § 70, provides, in substance, that a gas company may, with the written consent of the aldermen or selectmen, dig up and open the ground in the ways of a town, so far as necessary to accomplish its objects, but that such consent shall not affect the right or remedy to recover damages for an injury caused to persons or property by its acts; that it shall put all such ways in as good repair as they were in when opened; and that upon failure so. to do within a reasonable time it shall be guilty of a nuisance. The evidence disclosed that the trench was not filled by the defendant until Wednesday, January 3, and that this work was not completed until 2:30 p.m. on that day. The inference is warranted that during the time that this work was in progress, a permit could have, been procured if, as we do not decide, it then would have availed the defendant. The judge had the question of nuisance, squarely presented, inasmuch as four requests, posited upon nuisance, were refused on the ground that an emergency had arisen which justified the defendant in digging the trench without a permit. The reasons given - for the refusal of these requests, involving as.they do a finding that an emergency had. arisen and that therefore the defendant was justified in..digging the trench without a permit,. do not cure any, possible error in the refusal to give the second
The defendant contends that there was no evidence of any ordinance of the city of Newton that required the defendant to obtain the permit required by the statute in question, and relies upon the provisions of § 75 of said c. 164, whereby the aldermen or selectmen may regulate, restrict and control all doings of gas and electric companies “subject to this chapter” which may, in any manner, affect the health, safety, convenience or property of the inhabitants of their towns. Said § 70, however, seems to be complete in itself and to require a permit to open the public ways apart from any question of an ordinance. See Boston v. A. W. Perry, Inc. 304 Mass. 18, 21, 22; Cheney v. Barker, 198 Mass. 356, 366. We are of opinion, however, that it is not necessary to go into this question, inasmuch as it does not appear that it was raised at the trial.
It could have been found that the defendant did not leave the street in as good repair as when it was opened; that for about twelve days the trench was left in this condition; and that during a heavy rain, the surface settled to the extent of one foot. We think it follows from this that it could have been found that a nuisance was created by the defendant. Accordingly, there was error in the denial of the plaintiff’s second request. If a nuisance existed, it was not necessary to show as a ground for recovery that it was negligently maintained. The plaintiff was required to show that his particular loss or damage was caused by the nuisance. Stone v. Boston & Albany Railroad, 171 Mass. 536, 544. Jones v. Hayden, ante, 90, 95.
Finally, the defendant contends that the judge found that the work of filling the trench was not improperly done. There is no express finding to this effect. It is true that the judge stated that there was no evidence before him as to how the trench was filled, that he found that the defendant was justified in digging the trench without a permit, that
The case at bar is distinguishable from Stoddard v. Winchester, 154 Mass. 149. In that case recovery was sought for damages sustained through a defect in a public way that the defendant was bound to keep in repair, and there was no contention that the town had notice, or might reasonably have had notice, of the existence of the alleged defect;
The order of the Appellate Division dismissing the report is reversed, the finding for the defendant is vacated, and the case is to stand for trial. Home Savings Bank v. Savransky, 307 Mass. 601, 607.
So ordered.