159 Wis. 256 | Wis. | 1915
The primary question presented here is this: Did the trial court err in holding that the clause printed on each of the hills of lading, exempting the initial carrier from liability for damages not occurring on its road, was not a part of the contracts of carriage ?
The place of the contract was the state of Illinois and the law of that state governs as -to the nature and validity thereof since there was no evidence showing a contrary intent. That is elementary. International H. Co. v. McAdam, 142 Wis. 114, 124 N. W. 1042.
Does the proposition stated fall within the field of validity and interpretation, — that of what the real contract between the parties was ? In answering this it does not matter, necessarily, what would be our conclusion if the place of the contract was Wisconsin, nor what it would be as an original proposition, as regards an Illinois contract. The courts of that state have settled the law there, that without express assent to a restrictive provision, something other than merely accepting the paper and delivering the freight, as was done in
The subject has been reviewed in several courts and by text-writers, as indicated by the authorities cited to our attention, all holding that in Illinois the particular question falls within the field of validity and interpretation, — in short, of that of what the contract is, and not in that of performance or remedy for a breach. Hoadley v. Northern T. Co. 115 Mass. 304; Hartmann v. L. & N. R. Co. 39 Mo. App. 88; Powers M. Co. v. Wells-Fargo & Co. 93 Minn. 143, 100 N. W. 735; 1 Hutchinson, Carr. (3d ed.) § 208.
True, as said by the Massachusetts court in the cited case, what appertains to validity and interpretation and what to mere performance and remedy, is sometimes not easily determined. But the particular matter has been determined by the Illinois court for Illinois contracts, and was, in effect, written into those in question. Such determination has been, in general, followed in other jurisdictions, though con
The exemption provision in the contracts being out of the case, the nest question is whether such contracts were for a through service, rendering the Alton road liable for. the default of the connecting carrier.
The contract in each case was made by receiving the freight and delivering the usual freight receipt, specifying the point of origin of the freight, the terminal point' beyond the line of the receiptor, the connecting line required.to- complete the transit, and the rate for the entire carriage. As said before, the law of Illinois must be considered as embodied therein; but that makes no difference on this point. Reference to Schneider v. Evans, 25 Wis. 241, which did not involve such a contract as the one before us, seems beside the case. It is otherwise as to Peet v. C. & N. W. R. Co. 19 Wis. 118, as regards the question before us. The latter with Tolman v. Abbot, 78 Wis. 192, 41 N. W. 264, and other cases in this court establish the unwritten law on the subject for this state, substantially following the English rule as to what constitutes a through contract. 4 Elliott, Railroads, § 1434. Other
So, regardless of what the obligation of a railroad company would be under such a contract as the one in question made in this state, by the law of Illinois the agreement was for a through transit with full common-law liability.
The point is made on behalf of the appellant Chicago, Milwaukee & St. Paul Railway Company that if respondents have any .cause of action as to such company, it is to redress a wrong sounding in tort, which cannot be joined with proceedings to redress a breach of contract, — the wrong complained of as to the Alton Company. There does not seem to be merit in that proposition. It may be that, in general, a mere unreasonable failure of a connecting carrier to receive freight tendered from another road would be a breach of duty, having more the cast of a tortious wrong than a breach of contract. But, where a connecting carrier is not only in duty bound to receive goods so tendered, but holds itself out to the public for the performance of such service, and is designated by the initial carrier, in the contract of affreightment for a through rate, as the connecting line, and the latter assents thereto by force of a custom (1 Elliott, Railroads, § 303; 4 id. § 1443a), or by placing refusal to accept the freight upon some ground inconsistent with contractual obligations to do so, or by accepting it and demanding and receiving part
The foregoing covers all the questions in the case except those involving matters of fact, requiring jury interference for their solution. All were duly submitted and found in respondents’ favor, and the findings have believable evidence and reasonable inferences in their support.
It may be that the learned trial court did not, with consummate definiteness, instruct the jury on the subject of whether the Milwaukee Company unreasonably maintained an embargo against receiving the freight from the Alton line after February 4, 1910. But it seems that the jury must .have understood from the course of the trial that the railroad company had a right to refuse to receive the freight into its possession, if conditions on the delivery track, not attributable
This case was submitted to the jury upon the theory that, if, through fault of the Milwaulcee Company, a continued occupancy of the delivery track by cars of the first lot, leaving no room thereon for the particular-cars, prevented completing the transit until the property therein became worthless, and nevertheless, it refused to make the delivery because of such occupancy, then it committed a wrong. The findings of the jury are to the effect that, from the 4th day of February, 1910, until the property in question became worthless, during which time the cars in question were at the point of transfer to the Milwaulcee Company, the refusal of the latter to receive the freight and complete -the transit was not justifiable, — not justifiable, we understand, by reference to the evidence, because the responsibility for the conditions on the delivery track was with such company. The trial court said in clos: ing the case: “There is much testimony on the question,” which is quite true, and further instructed as follows:
“You will remember, gentlemen of the jury, the testimony given by the several witnesses as to what occurred after or at about the 1st of February, and from that until the 3d or 4th day of February, 1910, with reference to the blockade which was declared, it being claimed by the Chicago, Milwaulcee <fi St. Paul Railway Company that that blockade was justifiable because cars were upon the industrial track of the American Malting Company and prevented the shipping in or placing*267 in of other ears at that time, and was not being disposed of by that company, and for that reason they claim they were entitled to maintain the blockade. Yon will remember the testimony on the part of the plaintiff by the witnesses and the correspondence with reference to what occurred at or about that time, the direction, if any, which was given to the Chicago, Milwaukee & St. Paul Railway Company as to the disposition of those cars, and the effect of such direction, if it was given, may also be considered by you, in determining whether or not it was justifiable, the company claiming that it was justifiable because material upon the track was not being disposed of so as to open the track; on the other side, the plaintiff claiming that it was not justifiable because they had informed them that the material was valueless, that it should be taken out and dumped and permit the other twenty-one ears this suit is about to be moved up and disposed of. Now, you will have that testimony in mind together with all the other facts and circumstances, and all the other evidence that bears upon that question, and answer the question which is here submitted by 'Yes’ or 'No.'’ ”
The whole matter was thus plainly placed before the jury. The answer to the question of whether the Milwaukee Company was justified in refusing to complete the transit promptly after February 4, 1910, was made to turn on whether it was responsible for the blockade on the delivery track. On the one side it .was claimed .that the occupancy of such track was by cars of material which had been spoiled in transit and subsequently placed therein by the railroad company, and that respondents refused to receive them on that account and did nothing respecting them except to try and help the railway company out of its dilemma by, at its request, endeavoring, without success, to save some of the freighted property; that it was up to the Milwaukee Company from about February 4, 1910, to rescue itself from the situation by dumping such property out of the cars as worthless, or in some way clearing the way for the particular cars, and that it finally did so but too late. There was conflicting evidence in respect to the matter. It was peculiarly a jury
It is urged that the cars which blocked the delivery track were occupied by respondents and so they became responsible for the blockade thereon. That is upon the theory that, a delivery at the place for unloading is a delivery to the consignee. The authorities cited in support of the proposition, and principle as well, condemn it. It takes something more than mere delivery of a carload of freight at the unloading place to constitute a delivery of the subject of the transit into possession of the consignee. Reasonable opportunity for determining whether the carrier has performed its contract or not is required. If the property is found upon inspection, with reasonable diligence, to have been rendered worthless, or to have been materially injured while in the possession of the carrier, the consignee is not bound to accept the setting out of the car as a delivery of its burden. The consignee is not obliged to accept regardless of condition. Tie is entitled to reasonable time and opportunity to inspect the property and to reject it if rendered worthless or materially injured in the transit, or to take it without acceptance as having been transported according to contract. 2 Hutchinson, Carr. (3d ed.) § 133; 4 Elliott, Railroads, § 1528. That is elementary. It is laid down, as indicated, by most courts and text-writers. The authorities cited by counsel for appellant Milwaukee Railway Company are in harmony therewith.
So it does not follow, merely because the cars which caused the blockade were placed on the delivery track for the consignee, that the responsibility of the railway company, ipso facto, terminated, or that it was terminated because of some of the cars having been unloaded by the consignee. If within the reasonable time for inspection, the property was rejected as having been spoiled in transit, and the rejection was persisted in, the consignee only relenting to the extent of ac
It is suggested that, as matter of latv, tbe Milwaukee Company should not be held liable for damage to material in transit which was accepted by tbe Alton Company after it received notice of tbe embargo. About half tbe cars in question were so received. Tbe last of tbe cars reached tbe transfer point about tbe time tbe embargo should have been lifted. There is nothing to indicate that tbe Alton Company bad any reason to expect tbe necessities of the Milwaukee Company would cause any considerable delay, certainly not that delay would be caused by its fault. Had tbe property accepted for transit after notice of the embargo reached it at East St. Louis, become worthless before termination of justifiable continuance of tbe embargo, it alone would be liable for tbe loss. In receiving the cars before notice of termination of tbe embargo, it took tbe risk of loss without right of action against tbe Milwaukee Company in case of tbe latter justifiably refusing to accept such cars at tbe delivery point until tbe subject of tbe transaction became worthless.
When a railroad company, from .the reasonable necessities of tbe situation, having regard to self-protection and duty to tbe public, declares an embargo, in form, to continue until further notice, or by custom to so continue, it is up to tbe shipper and initial carrier by reasonable inquiry to find out whether there has been a change in tbe situation before sending forward freight. Riddle, Dean & Co. v. B. & O. R. Co. 1 Int. Comm. Rep.778. That would bold good until lapse of such time as to render further continuance of tbe embargo clearly unreasonable; but would not preclude a carrier, circumstanced as tbe Alton was in this instance, from accepting freight for transportation, as here, at its own risk of tbe embargo being actually lifted by tbe act of tbe connecting car
A railroad company must have reasonable ground for instituting an embargo, or it is illegal. The carrier cannot declare an embargo as a shield against its inexcusable fault nor unreasonably continue it as such shield. If legal when instituted its continuance is illegal when there is no basis for it other than its own culpable negligence or wilful neglect. Barnes, Interstate Transp. § 352.
Other questions are suggested by counsel for consideration, some of which are covered by the previous discussion and others are not deemed of sufficient importance, in view of the conclusions already stated, to warrant extending this opinion. The major questions are whether the expressed exemption of liability became a part of the contracts of affreightment, whether the contracts were for a through transit, and whether the Milwaukee Company was responsible for the condition which moved it, during the embargo period, to refuse to deliver the twenty-one cars within the period after the 4th of
By the Court. — Judgment affirmed on both appeals.