73 Wis. 416 | Wis. | 1889
The only question raised by the demurrer is whether the complaint above set forth states facts sufficient to constitute a cause of action upon contract. The contract was only to be let after the state, through its board of commissioners, had procured and adopted “suitable and proper plans, drawings, and specifications ” for the construction of the two wings of the capítol. Sec. 3, ch. 252, Laws of 1882. Such commissioners were expressly “ authorized to employ an architect or superintendent to superintend the work on said building as it progressed,” and for which he was to receive from the state such compensation as the commissioners should determine. Id. sec. 4. Such architect was thereby required, at the close of each month, to
The contract is given above. It appears that it required all the materials to be furnished and all the work to be done according to such plans and specifications, and agreeably to such directions as might be given from time to time by such architect, and to his full and entire satisfaction; that it expressly authorized the state or its architect to vary from such plans and specifications, either by adding thereto or diminishing therefrom or otherwise, and the value of such alterations w-ere to be ascertained by him and to be added or deducted from the contract price named therein as the case might be; that such alterations and additions, as well as the work contained in the plans and specifications, were to be completed January 1, 1884; that any doubt or doubts as to the quality of materials being-used or the workmanship thereon, or as to estimating allow-
Under the pleadings, we must assume that the plaintiffs proceeded in good faith to perform their said contract according to such plans and specifications, and under the direction of the architect, and without any knowledge of any defects or inefficiency; that on November 8,1883, they had a very large portion of said two wings completed, and had placed therein a large quantity of cast-iron materials, furnished by a contractor selected by said architect, and which cast-iron materials had been approved and accepted by the architect on behalf of the state; that by reason and in consequence of defects in such plans and specifications, and without any fault or negligence of the plaintiffs, and on November 8, 1883, the south wing broke down and fell,
Under such a contract, and upon such facts, it is strenuously urged upon the part of the state that the plaintiffs were bound to furnish all the materials and perforin the necessary work to restore the south wing, according to such new or modified and altered plans and specifications, to the point and in the condition where it was when it fell, at their own' cost and expense. In other words, the contention is that the plaintiffs assumed the risk of the sufficiency and efficiency of the plans and specifications, and the ma
The case most'relied upon in support of such contention is Thorn v. Mayor, L. R. 1 App. Cas. 120, affirming S. C. 44 L. J. Exch. 62. The facts in that case were to the effect, that the city of London desired to remove an existing bridge over the Thames at Blackfriars, and eréct a new one in its place. Accordingly its engineer prepared plans of such intended new bridge, and specifications of the works to be executed. The specifications stated, in effect, that the accuracy of the drawings of the existing bridge was not guarantied; that the city should not be liable for any extra •work in removing more than indicated in the drawings; that the contractors were to take out their own quantities, and satisfy themselves as to the nature of the ground through which the foundations were to be carried; that no surveyor was authorized to act for the city, and that no information given was guarantied; that piers Avere to be put in by means of wrought-iron caissons, as shown on the drawings; that the contractors were to assume all risks and responsibility in the sinking of such caissons, and to employ their own divers or other efficient means for removing and overcoming any obstacles or difficulties that might arise in the execution of the work; that the quality of the concrete was put under the control and direction of the engineer; that extra or varied work Avas to be certified, accounted, and paid for at prices named. Thorn, having taken the
The value of such decisions as authority, however, is somewhat impaired by reason of the uncertainty as to the precise grounds upon which they were based. This grows out of the fact, so common among English decisions, especially of the present day, of rendering numerous opinions in the same case. Thus, in that case, there were five different opinions rendered in the Exchequer Chamber, and four in the House of Lords. Each of these opinions puts such decision upon grounds differing more or less from some if not all the others. The conclusions of each court, therefore, are to be found in the general average. The prevailing opinions in each of those courts seem to go on the theory that the contract was for the building of the bridge on piers; and that although the contract referred to the plans, etc., in which the caissons were specifically
The facts of that case distinguish it from the one at bar in several particulars. In that case the caissons so specified were not included in the thing contracted for, but were only referred to in the specifications as a means to be employed in the construction of the piers. Here the defects and inefficiency were in parts of the structure contracted for. In that case the city’s engineer only had control and direction as to a small portion of the work, in which the caissons were not included, but the construction was almost wholly under the control and supervision of the contractor and his engineer and employees. Here, as indicated, the state’s architect was to inspect, approve, and accept the materials •and workmanship as they went into the building, and did ■so accordingly, with full power to modify and alter plans .and specifications. In that case the defective parts were mover accepted by the city. Here they were inspected, ac
By the Court.— The demurrer to the complaint is overruled, with leave to answer within twenty days.