214 N.W. 47 | Minn. | 1927
Plaintiff brought this action against the two defendants as principal and surety on the bond to recover the balance due him for the work performed. Barrett answered, admitting plaintiff's claim. The surety company answered, admitting the execution of the contracts and the bond, but resisted liability, claiming that the notice required by G.S. 1923, § 9705, was not served and that the complaint failed to state a cause of action against it, that the findings of the *307 trial court were no broader than the complaint and therefore insufficient to sustain a judgment against it. From an order denying its motion for a new trial, the defendant surety company appealed.
The statute provides that no action shall be maintained on any such bond unless, within 90 days after the completion of the contract and acceptance by the proper authorities, the claimant shall serve upon the principal and his sureties a written notice specifying the nature and amount of his claim and the date of furnishing the last item thereof, nor unless the action is begun within one year after the service of such notice.
On November 20, 1925, plaintiff mailed to the surety company, at its main office in the city of Milwaukee, a notice stating that the work of construction was completed in the month of September, 1925, that there was due him thereon a balance of $8,356.52, that the same had not been paid, and that he would look to the surety for payment under the bond. While the physical work may have been completed prior to the time stated in the notice, the fact remains that the commissioner of highways accepted the job on November 7, 1925. The statute is silent as to the manner of service of such notice. The surety company is a foreign corporation and the notice might have been served upon its agent. However, the purpose of the service of such a notice was accomplished. It is not questioned but what the surety company received the notice mailed to it at Milwaukee. The record discloses that, following the mailing of the notice by plaintiff, the surety company corresponded with the bank with which plaintiff transacted his banking, with reference to the nonpayment of the check which Barrett had given to the plaintiff. The notice was sufficient to inform appellant of the default on the part of the principal in the bond, which is the very purpose of the requirement of such notice. 25 C.J. 1101; Crystal Ice Co. v. United Surety Co.
As to the sufficiency of the complaint, it appears that a copy of the subcontract is contained therein. The main contract between the defendant Barrett and the highway commission is attached to the bond which included the original proposal of Barrett for the work to be done and the payments to be made therefor. *308
Section 9285, G.S. 1923, provides that:
"In every stage of an action, the court shall disregard all errors or defects in the pleadings and proceedings which do not affect the substantial rights of the adverse party, and no judgment shall be reversed or affected by reason thereof."
Section 9281, G.S. 1923, provides that:
"No variance between the allegations in the pleading and the proof is material unless it has actually misled the adverse party to his prejudice in maintaining his action or defense on the merits. * * * When the variance is not material, the court may direct the fact to be found according to the evidence."
Full force and effect must be given to the statute. Dressel v. Brill,
The principal finding of the trial court is "that the allegations set forth in the complaint of the plaintiff herein are true." We have just had occasion to criticize the practice of drafting findings by the short cut method of reference to a pleading which is found true. War Finance Corp. v. Erickson, supra, page 276. While the findings are extremely vague, yet we hold them sufficient to authorize the judgment as entered. It is alleged in the pleading that plaintiff did and performed all of the requirements of his contract and of the contract between Barrett and the highway commission, and that there was due and owing him thereon the sum of $8,356.52, that no *309 part thereof has been paid, and that the same is due him under and by virtue of the contracts and the bond set forth in the complaint, with interest from November 9, 1925. The finding, in effect, is that such allegations are true. Respondent might well have applied to the court for more specific findings. The highway commissioner, the defendant Barrett and the plaintiff treated all work done as within the terms of the contracts. The final estimate of the highway department and the recapitulation sheet upon which final payment was made to Barrett include the items mentioned as part of the construction job. There is no evidence to the contrary.
The court did not go beyond nor are the findings outside the issues made by the pleadings. The parties were properly before the court and given an opportunity to be heard upon the matters covered by the judgment.
Affirmed.