318 Mass. 190 | Mass. | 1945
This petition is prosecuted under G. L. (Ter. Ed.) c. 258 to recover for work done and for damages sustained by the petitioner acting as contractor for the metropolitan district water supply commission (St. 1926, c. 375; St. 1927, c. 321) in respect to “Item 8” of “Contract No. 52,” dated August 24, 1936, relating to the construction of the embankment for the main dam of Quabbin Reservoir. The work out of which this litigation arises was performed during the spring, summer and autumn seasons of the years 1937 and 1938.
The petitioner contends' that no express contract ever came into existence between the parties, or that if such contract did come into existence the'petitioner was induced to enter into it by representations made in behalf of the Commonwealth which were substantially false or which were at least only half truths that by reason of concealment of material facts amounted to fraud, and that the Commonwealth broke the contract after it was made. Claim 1 of the petition is a claim to recover $892,581.30 and interest for breach of contract in several respects which, in so far as they are still pressed, will be dealt with later in this opinion. Claim 2 appears to be a claim for damages for deceit, but since damages cannot be recovered against the Commonwealth in tort, Arthur A. Johnson Corp. v. Commonwealth, ante, 88, 92, this claim need not be further considered. Claim 3 is for an undisputed balance most of which has now been paid. An offer of judgment has been made for the remainder. This claim is no longer in controversy. Claim 4 is to recover $892,581.30 and interest on. quantum meruit for work and materials and rests upon the theory that no express contract ever came into existence or upon the theory of rescission of the contract for the alleged fraud. Long v. Athol, 196 Mass. 497, 506. Claims 1 and 4 are in the alternative. No ques
The case was heard by an auditor whose findings of fact were to be final. Where cases are referred in this way findings of the auditor which are not inconsistent with each other and which are not shown by the report to be erroneous in law are binding upon the trial court and upon this court, except that the auditor's conclusions of fact reached solely by way of inference from other facts are open to review as matter of fact by the trial court and by this court, and either court may draw additional inferences from facts found. United States Fidelity & Guaranty Co. v. English Construction Co. 303 Mass. 105, 109-112. Galluzzi v. Beverly, 309 Mass. 135. See Arthur A. Johnson Corp. v. Commonwealth, 306 Mass. 347, 350, 351.
In compliance with an order of the court the auditor filed a report on questions of liability only. Thereupon the trial judge ruled that the petitioner was not entitled to recover for work performed and furnished in connection with “Item 8,” except as hereinafter stated. He denied a motion of the petitioner that the court determine that the respondent is liable to the petitioner for work performed and furnished and order further hearings upon the question of damages, and he allowed motions of the respondent for judgment in its favor on claims 2 and 4 and that “a final decision ... be entered” in its favor on claims 1 and 3 in so far as they relate to “Item 8” of “Contract 52,” except as to the balance admittedly due of $12,801.64. He then reported his action upon the motions. G. L. (Ter. Ed.) c. 231, § 111. The action of the judge is a decision in favor of the respondent of all issues argued before us.
The embankment of the main dam, now known as Winsor dam, is about a half mile in length and rises to a height of about one hundred seventy feet above the original valley surface. It crosses, the bed of Swift River. Its ends rest upon hills on each side of the river. It is constructed of
The embankment was required to be built by the so called full hydraulic method. The dominating characteristics of this method may be described as follows. The embankment is- built upon a foundation which is in the form of a very broad shallow trough, the lowest part of which is along the center line of the dam. The materials of which the dam is to be composed, such as earth, sand, gravel, and small stones, are mixed with water and sluiced through pipes upon the sides of the trough at their outer edges. The coarsest and heaviest materials come to rest-near what are to be the outside faces of the dam. Finer materials are deposited farther down along the slopes of the trough, called the beaches, while the finest materials of all, called fines, are held in suspension in the water, which gathers in a long, narrow pool running lengthwise of the dam along its center line. The fines are slowly precipitated in the form of thin mud in the center of the dam. The edges of the pool on either side at any given time are determined by the extent to which solid material has been allowed to run down the beaches into the water, that is to say, by the sluicing limits. The pool gradually rises as the dam is built but does not necessarily become deeper, since the deposit of fine material constantly raises the level of its bottom. The coarse materials near the outside of the dam constitute the shoulders and give the dam strength and resisting power but are pervious to water, while the fines precipitated in the pool along the center of the dam be
. It is readily apparent that the safety and usefulness of a structure of the kind described, with its appurtenances, are dependent upon the constant supervision by skilled engineers of the details of the work during the process of erection, and also that much depends upon the sluicing of proper proportions of coarse materials and fines at the different stages of the work. Accordingly, it is not surprising that the contract throughout contains provisions worded in various ways requiring, in effect, that practically all of the work under "Item 8” shall be performed according to the orders and to the satisfaction of the chief engineer or his assistants. These provisions are detailed, explicit, and emphatic. To a large extent the case hinges upon them. To many of them reference will be made later in this opinion. Whenever in this opinion the word engineer is used in quotations from the contract or otherwise, whether in the singular or in the plural, it refers, unless otherwise indicated, to the chief engineer in the service of the Commonwealth and his assistants acting under his authority.
1. The petitioner contends that there was no express contract and that it can recover quantum meruit for the reason that the minds of the parties never met on the matter of the thickness of the core. Section plans of the embankment showed a "theoretical coré line” which was intended to represent the boundary within which all materials should be fines or suitable core material, with no admixture of transitional material, but which the petitioner understood represented only the average line of the core face within which some incursion of transitional material would be permitted in the course of the work. The petitioner cites Vickery v. Ritchie, 202 Mass. 247, Lonnqvist v. Lammi, 240 Mass. 371, and similar cases. See Murphy v. Mitchell, 254 Mass. 18, 21; Andrade v. Hanley, 289 Mass. 335. But findings of the auditor and the plans themselves make it clear that there was at most an ambiguity in the contract (including the plans) which the
Moreover, in this instance the contract itself provided a method by which questions of interpretation should be determined. It contained a clause that the engineer should decide “all questions which . . . [might] arise as to the interpretation of the plans and specifications used . . ..” The engineer interpreted the “theoretical core line” as marking the limit to which material not suitable for the core should be permitted to penetrate in the normal process of sluicing. Certain markings on the plans tend to support this interpretation. The engineer’s decision does not appear to have been arbitrary or made in bad faith. The petitioner is bound by it. Norcross v. Wyman, 187 Mass. 25, 27. Marsch v. Southern New England Railroad, 230 Mass. 483, 493-494. Morgan v. Burlington, 316 Mass. 413, 419-420.
2. We take up next the question of the petitioner’s alleged right to rescind the contract for fraud. Any fraud that could be availed of as a ground of rescission must have occurred before the execution of the elaborate formal contract on August 24, 1936. The contract must be deemed to have been made on that day, even though the “Plan of Operation” for building the. embankment which the petitioner was required by section 9 of the specifications to submit for approval had not then been approved. The contract itself determined the work to be done. The “Plan of Operation” related only to the manner of doing it and
The petitioner’s contention that it was induced to enter into the contract by reason of false representations or of representations of partial truth which amounted to falsehood rests in large part upon findings that the petitioner was caused, by entries upon the plans and by statements of one of the subordinate engineers which in themselves were literally true, to believe that it could build the entire embankment of the modified drift found in the so called lower borrow area, which was convenient and easily worked, whereas in truth the engineers had already decided not to permit it to be built entirely of material taken from that area but to insist that “at least some considerable part of the material” be taken from the so called upper area or some other area containing till, a material less convenient and harder to work.
The auditor found that this nondisclosure was intentional, but that it was not in order to procure a lower bid from the petitioner or from any improper motive. He found that the engineers had reached their decision honestly believing it their duty to build the best possible dam of the best available materials, and believing that the lower area was deficient in fines, and that fines and coarse materials would be found distributed in it in a manner inconvenient for the building up of the core by the intended process. The auditor found that the petitioner relied upon the information furnished, but that no misrepresentation of. fact was made
But the petitioner asks us to disregard the auditor’s conclusion that the petitioner was not misled into making the contract and to draw the opposite inference that the nondisclosure . did materially influence the petitioner to enter into the contract. Even if the auditor’s finding was solely by way of inference from other findings and did not go back in whole or in part to the evidence which was before him and is not before us, we are of opinion that we ought to reach the same conclusion that he reached. As it appeared at the outset, and as it turned out, the lower area was more advantageous to the contractor, and a contractor would use it if he could. But all bidders, including the petitioner, were fully informed through the plans and specifications of the proposed contract that there was no guaranty whatever of the suitability of borrow areas, and that the engineers might order the contractor from one area to another or to mix materials from different areas as they
The petitioner also contends that there was nondisclosure of the decisions or intentions of the engineers in regard to the proposed locations of the edges of the pool as the work advanced, the breaking up of so called intrusions of coarse materials into the core, and the grain sizes of the materials to be placed in the core to secure imperviousness; but in respect to none of these matters are there findings of actual misrepresentation or of fraudulent nondisclosure and of reliance necessary to rescission. Am. Law Inst. Restatement: Contracts, §§ 470, 471, 476, Restitution, § 8. See Williston on Contracts (Rev. ed) § 1487. It was inevitable that the respondent’s engineers would hold opinions or views as to
3. The petitioner’s next contention, that it can recover for breach of contract in the nature of breach of implied warranty, rests principally upon the facts that the plans showed, and the "Information for Bidders” and the body of the contract itself referred to, "permitted borrow” areas as expected from "present indications” and "preliminary investigations” to yield suitable materials; and that the contract suggested several "Plans of Operation,” some of which indicated' the use of the lower area, which was referred to in the construction "studies” as "probably suitable.” But these references must be read in connection with other express statements on the plans and in the contract to the effect that the existence of a sufficiency of suitable material in any one area is not guaranteed; that the contractor will be allowed to borrow from any one area only to the extent that the materials are acceptable and satisfactory (which means acceptable and satisfactory to the engineer); that mixing of materials from different borrow areas will probably be required; and that whenever the, character of the borrow pit materials is unsatisfactory (which means unsatisfactory to the engineer), the contractor shall change the location of his borrowing or mix with other materials. There are many provisions of similar import. Besides these, there are general provisions that
If the petitioner intends to make a further contention that widening of the sluicing limits can properly be described as a breach of warranty, that matter will be dealt with later in considering particular alleged breaches of contract.
4. We now come to the consideration of certain alleged specific breaches of contract of which the petitioner complains. As set forth in its brief, these are four in number. (1) Shortly after the work started the engineer ordered the sluicing limits to be set so wide that the thickness of the core of the embankment was increased beyond the “ theoretical core line” (even as interpreted by the engineer) by an amount which does not exactly appear and which, owing . to the unavoidable irregularity of the faces of the core and to the fact that they are buried in the shoulders, probably cannot be ascertained with any degree of accuracy. So far as the findings of the auditor go they indicate an average increase in thickness of the core of slightly less than ten
In passing upon these alleged breaches of contract by the respondent it becomes necessary first to determine whether the several orders of the engineers of which complaint is made lay within the scope of the very extensive powers which by the express terms of the contract both parties committed to the engineers. Pertinent provisions of the contract defining these powers are here quoted or summar
Comprehensive as these powers are, they did not go so far as to authorize the engineers to do anything whatever that they might see fit. These powers are not so extensive as to enable the engineers to abrogate the contract which the parties executed; nor did their inclusion in the instrument prevent the creation of a contract in the first place. The purpose of such powers is to maintain control over the work as it progresses by the persons selected and to secure flexibility in adapting means to ends. The discretion committed to the engineers must be exercised within the framework of the original contract and for the purpose of carrying out the work originally intended. The engineers could not substitute for the earthen dam at the place specified a
In our opinion all of the orders and decisions of the engineers of which the petitioner complains were within the scope of the powers conferred upon them by the contract. A thickening of the core by a total amount which seems to have been less than twenty feet in an embankment of such immense size, even though it increased the volume of the core as much as twenty per cent, did not, in the circumstances shown, change the general character and identity of the work. This did not increase the width or volume of the whole embankment. It merely increased the bulk of the core at the expense of the shoulders. The number of cubic yards to be placed and paid for remained the same. The contract price per cubic yard was the same for core as for shoulders. The special references to the core hereinbefore quoted from the contract show that alterations in its dimensions by orders of the engineers were within .the contemplation of the parties. The increase in the proportion of the finest materials in the core was likewise comprehended within a fair interpretation of the provisions already quoted. That related directly to the quality of
The order of the Superior Court denying the “Petitioner’s Motion for Order on Auditor’s Report” is affirmed.
So ordered.
See, for example, Chapman v. Lowell, 4 Cush. 378; Evans v. County of Middlesex, 209 Mass. 474, 479, 480; Dubinsky v. Wells Brothers Co. of New York, 218 Mass. 232, 236; Ripley v. United States, 223 U. S. 695, 702.
Palmer v. Clark, 106 Mass. 373, 389. Flint v. Gibson, 106 Mass. 391, 394-395. Robbins v. Clark, 129 Mass. 145. Audette v. L’Union St. Joseph, 178 Mass. 113, 115. National Contracting Co. v. Commonwealth, 183 Mass. 89, 92. Norcross v. Wyman, 187 Mass. 25. White v. Abbott, 188 Mass. 99; Hebert v. Dewey, 191 Mass. 403, 408, 414. Loftus v. Jorjorian, 194 Mass. 165, 169. Handy v. Bliss, 204 Mass. 513, 520. Hathaway v. Stone, 215 Mass. 212, 216. Marsch v. Southern New England Railroad, 230 Mass. 483, 493. Hurley v. Boston, 244 Mass. 466, 470-471. Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. 495, 503. Coleman Bros. Corp. v. Commonwealth, 307 Mass. 205, 216. Morgan v. Burlington, 316 Mass. 413, 419-420. Martinsburg & Potomac Railroad v. March, 114 U. S. 549. United States v. Gleason, 175 U. S. 588, 602. Goltra v. Weeks, 271 U. S. 536, 548. Williston on Contracts, (Rev. ed.) § 797.