408 Pa. 66 | Pa. | 1962
Opinion by
These appeals arise from a construction contract for the erection of a commercial building in Union-town. Essentially the controversy resolves itself about the interpretation of a section of the contract wherein the defendants (Appellants at Nos. 216, 217 March Term, 1961) are denominated “the first party” and the plaintiffs (Appellants at No. 6 March Term, 1961) are “the second party”.
The defendants maintain the contract is a “no lien” contract while the plaintiffs contend the language used does not deny them the right to file a mechanic’s lien. The paragraph of Article XXI is as follows : “In the event at any time any obligations incurred by the second party in connection with or as the result of the performance of this subcontract are unpaid, whether due dr to become due, the first party is. authorized to make such payment direct out of any moneys' payable-.
The court below, in opinion of the Court en banc, said: “We construe this. whole paragraph as relating
We do not so interpret the language of this provision of the contract. While the primary intention of the parties may have been to give defendants protection against liens or obligations which are primarily the obligations of plaintiffs, the quoted portion of the contract clearly waives the plaintiffs’ right to file a mechanics lien.
The instant case is clearer than the contracts in Wood v. U. S. Steel Corp., 383 Pa. 158, 118 A. 2d 199 (1955). There it was held the language was sufficiently clear to constitute a waiver of right of subcontractor to file mechanics lien. In these appeals the parties themselves are the signatories. The mechanics’ liens Act of June 4, 1901, P.L. 431, §15, 49 P.S. §71 provides: “The right to file a claim may be waived by agreement between the claimant and the party with whom he contracts, or by any conduct which operates to equitably estop the claimant.” Parties may and do waive their rights to file mechanics’ liens. Carocci v. Piccone, 361 Pa. 93, 63 A. 2d 65 (1949).
The instant matter is an express waiver of the right to file a mechanic’s lien and not an implied waiver.
We need not consider the other questions raised by defendants pertaining to joinder of claims under the written contract and for extra work done by oral agreement and the charge of improperly lumping instead of a detailed statement nor the question raised by plaintiffs for interest on their claim.
Judgments at Nos. 216 and 217 are reversed and Appeal at No. 6 is dismissed.