ORDER GRANTING IN PART AND DENYING IN PART DEFENDANTS’ MOTIONS TO DISMISS AND/OR COMPEL ARBITRATION
THIS CAUSE came before the Court upon Defendant Waterline Development LLC’s Motion to Dismiss Complaint and/or Motion to Compel Arbitration (dkt #24), Defendant Joseph D. Grosso, Jr., P.A. and Joseph D. Grosso, Jr.’s Motion to Dismiss (dkt #25), and Defendants Mas-tercraft Development LLC, Mastercraft Services, Inc., and Perry Lap’s Motion to Dismiss Complaint and Compel Arbitration (dkt # 26).
UPON CONSIDERATION of the Motions, the Responses, the pertinent portions of the record, and being otherwise fully advised in the premises, the Court enters the following Order.
I. BACKGROUND
This action arises from a failed agreement concerning the construction of three single-family homes. 1 On September 17, 2005, Dr. Ari Ben-Yishay and his wife, Barbara Ben-Yishay (together the “Ben-Yishays”) entered into a Construction, Purchase and Sale Agreement (the “First Agreement”) with Defendants Mastercraft Development, LLC (“Mastercraft”) and Mastercraft Services (“MS”). Perry Lap (“Lap”), the managing member of Master-craft and president of MS, negotiated the Agreement on behalf of Mastercraft and MS. Under the agreement, the Ben-Yish-ays were to purchase a lot and pre-con-struction home to be built by Mastercraft and MS in Tesoro Preserve, located in Port St. Lucie, Florida. The Ben-Yishays were unaware that the lot was under the control of Defendant Waterline Development, LLC (“Waterline”), which was also a managing member of Mastercraft.
Under the First Agreement, the Ben-Yishays were to pay $2.5 million for the lot and construction of the home, with construction to be completed within 12 months after issuance of all applicable building permits. The Ben-Yishays were obligated to deliver $250,000 as an earnest money deposit. However, the Ben-Yishay’s decided to make an additional earnest money deposit of $250,000, making the total amount deposited $500,000. The funds were allegedly to be placed in escrow with Defendant Joseph D. Grosso, Jr., P.A. (“Grosso PA”) acting as escrow agent. The balance was to be paid at closing. In addition, the Ben-Yishays agreed to lease the newly constructed home to Mastercraft and MS as a model home for $12,000 per month for 18 months. On September 17, 2005, the Ben-Yishays issued a check payable to Mastercraft for $250,000. On January 15, 2006, the Ben-Yishays issued a second check for $250,000 payable to Mas-
In March of 2006, the Ben-Yishays decided to purchase a second lot and pre-construction home in Tesoro Preserve, to be built by Mastercraft and MS. On March 29, 2006, a Second Construction, Purchase and Sale Agreement (the “Second Agreement”) was entered into. Under the Second Agreement, the Ben-Yishays were to pay $3.2 million for the lot and construction of the home, with construction to be completed within nine months after issuance of all applicable building permits. The Ben-Yishays were obligated to pay $320,000 as an earnest money deposit, allegedly to be placed in escrow with Grosso PA acting as the escrow agent. The balance was to be paid at closing. In addition, the Ben-Yishays agreed to lease the newly constructed home to Mastercraft and MS as a model home for $15,000 per month for 18 months. On April 5, 2006, the Ben-Yishays issued a check for $320,000 payable to Mastercraft.
In July of 2006, the Ben-Yishays decided to purchase a third lot and pre-con-struction home in Tesoro Preserve, to be built by Mastercraft and MS. On July 14, 2006, a Third Construction, Purchase and Sale Agreement (the “Third Agreement”) was entered into. Under the Third Agreement, the Ben-Yishays were to pay $1.75 million for the lot and construction of the home, with construction to be completed within nine months after issuance of all applicable building permits. The Ben-Yishays were obligated to pay $175,000 as an earnest money deposit, allegedly to be placed in escrow with Grosso PA acting as the escrow agent. The balance was to be paid at closing. In addition, the Ben-Yishays agreed to lease the newly constructed home to Mastercraft and MS as a model home for $8,000 per month for 18 months. On October 9, 2006, the Ben-Yishays issued a check for $175,000 payable to Mastercraft. As an incentive to enter into the Third Agreement, the Ben-Yishays were offered an incentive package, which provided certain discounts and benefits to each of the three lots purchased.
By May of 2007, no construction had commenced on any of the three lots. The delays were attributed to revisions in the plans and by the inability of Mastercraft and MS to obtain financing. In August of 2007, Mastercraft and MS offered to reduce the price of the lots if the Ben-Yishays would obtain financing for construction. The Ben-Yishays declined. On October 7, 2007, the Ben-Yishays, Master-craft and MS agreed that if financing was not obtained within six weeks, the earnest money deposits, totaling $995,000, would be returned. The Ben-Yishays never received the money, and no accounting of the use of the funds was provided.
On February 6, 2008, the Ben-Yishays filed a Complaint (dkt # 1) alleging anticipatory repudiation and breach of contract against Mastercraft and MS with respect to the First, Second and Third Agreements (collectively, the “Agreements”). The complaint also alleged fraudulent misrepresentation against Mastercraft, MS and Lap; fraudulent inducement against Mastercraft, MS and Lap; conversion against Mastercraft, MS and Lap; imposition of an equitable lien or constructive trust as to property owned by Waterline, Mastercraft, and MS; and breach of fiduciary duty against Grosso PA and Joseph D. Grosso, Jr. (“Grosso”).
II. STANDARD OF REVIEW
A motion to dismiss for failure to state a claim merely tests the sufficiency of the
III. ANALYSIS
The validity of an arbitration agreement is covered by the Federal Arbitration Act (“FAA”).
See Weeks v. Harden Mfg. Corp.,
[A] contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction, or the refusal to perform the whole or any part thereof, or an agreement in writing to submit to arbitration an existing controversy arising out of such contract, transaction, or refusal, shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.
9 U.S.C. § 2 (emphasis added). The FAA also provides:
If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such arbitration, the court in which such suit is pending, upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in the proceeding with such arbitration.
9 U.S.C. § 3.
“The FAA establishes a ‘federal policy favoring arbitration ... requiring that [courts] rigorously enforce agreements to arbitrate.’ ”
Davis v. Prudential Sec. Inc.,
Each of the Agreements contain an identical arbitration provision which provides:
RESOLUTION OF DISPUTES BY ARBITRATION. All claims and disputes relating to this Agreement shall be governed by and submitted to binding arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (the “AAA”). Both parties agree that arbitration shall be the sole and exclusive forum for resolving all claims and disputes relating to this Agreement. This Agreement shall be governed by, construed, and enforced in accordance with the internal laws of the State of Florida, without regard to principles of conflicts of laws, and any proceeding arising out of or relating to this Agreement will be brought in the courts of record of the State of Florida in the County where the Property is located.
First Agreement, ¶ 18; Second Agreement, ¶ 15; Third Agreement, 1115. The Agreements are contracts providing for resolution by way of arbitration of claims and disputes arising out of the contracts. Therefore, under the terms of § 2 of the FAA, the arbitration clauses in the Agreements are valid, irrevocable and enforceable, absent an applicable defense under state contract law.
However, pursuant to the language of the arbitration clause itself, only controversies “relating to” the Agreements are subject to arbitration. Arbitration clauses that require arbitration for disputes “relating to” a contract are considered to be broad provisions.
See Sunkist Soft Drinks, Inc. v. Sunkist Growers, Inc.,
A. Arbitration of Claims Against Mas-tercraft and MS
Plaintiffs assert claims for anticipatory repudiation against Mastercraft and MS (Counts I-VI); breach of contract against Mastercraft and MS (Count VII-XII); fraudulent misrepresentation against Mas-tercraft, MS and Lap (Count XIII-XV); fraudulent inducement against Master-craft, MS and Lap (Counts XVI-XVIII); conversion against Mastercraft, MS and Lap (Counts XIX-XXI); equitable lien and/or constructive trust against Waterline, Mastercraft, and MS (Counts XXIV-XXVI); and breach of fiduciary duty
Plaintiffs’ claims of anticipatory repudiation and breach of contract against Mastercraft and MS (Counts I-XII) are referable to arbitration because they are indistinct from the obligations contained in the Agreements. Plaintiffs’ conversion claims against Mastercraft and MS (Counts XIX-XX) are also referable to arbitration because the Agreements governed the manner in which the funds forming the basis of the conversion claim were to be held and disbursed. First Agreement Addendum, ¶ 1(c); Second Agreement, ¶ 1(b); Third Agreement, ¶ 1(b). Therefore, the conversion claims against Mastercraft and MS also relate to the Agreements and are referable to arbitration.
See Bullard v. Capital
One,
F.S.B.,
Plaintiffs’ fraudulent inducement claims against Mastercraft and MS (Counts XVT-XVII) also relate to the contract and are referable to arbitration. The FAA’s “statutory language does not permit the federal court to consider claims of fraud in the inducement of the contract,” unless the claim goes directly to the making of the arbitration agreement itself.
Prima Paint Corp. v. Flood & Conklin Mfg. Co.,
Likewise, Plaintiffs’ fraudulent misrepresentation claims against Master-craft and MS (Counts XIII-XIV) are also referable to arbitration. A claim that a party made false statements knowing that another party would rely on those statements is referable to arbitration.
See Senti,
Plaintiffs’ claims for equitable lien and/or constructive trust against Master-craft and MS (Counts XXV-XXVI) must
Plaintiffs argue that the arbitration clause is not valid because the contract as a whole evinces a lack of mutual obligation to submit to arbitration. When a contract contains an arbitration clause, “ ‘both parties must be bound or neither is bound’”
Hull v. Norcom, Inc.,
Here, the Agreements contain a default provision which states that in the event of a default by the Ben-Yishays, Mastercraft and MS may “proceed in equity to enforce Seller’s rights.” Plaintiffs assert that the default provision creates a lack of mutuality that is fatal to the validity of the arbitration clause. However, the arbitration clause states that all parties “agree that arbitration shall be the sole and exclusive forum for resolving all claims.” Even if Mastercraft and MS may seek equitable relief outside of arbitration in the event of default, both parties have agreed to arbitrate with respect to all other claims. The fact that the parties may not be bound in exactly the same manner does not affect the validity of the arbitration clause. Therefore, the arbitration clause is valid because all parties have provided consideration through their promises to submit to arbitration.
B. Motion to Dismiss and/or Compel Arbitration as to Claims Against Lap
Plaintiffs’ claims against Lap include fraudulent misrepresentation (Count XV), fraudulent inducement (Count XVIII), and conversion (Count XXI). These claims are brought against Lap, the managing member of Mastercraft, an LLC, and president of MS, a corporation. “A director or officer of a corporation does not incur personal liability for its torts merely by reason of his official character; he is not liable for torts committed by or for the corporation unless he has participated in the wrong.”
Aboujaoude v. Poinciana Dev. Co. II,
1. Fraudulent Inducement
Plaintiffs have failed to state a claim against Lap for fraudulent inducement because the claim is barred by the economic loss rule. “The economic loss rule bars a tort action where a defendant has not committed a breach of duty apart from a breach of contract ... absent personal injury or property damages.”
New Lenox Indus., Inc. v. Fenton,
Plaintiffs cannot state a claim for fraudulent inducement because the claim is barred by the economic loss rule. Each of the allegedly fraudulent representations on which Plaintiffs allegedly relied are the same obligations memorialized in the agreement. Moreover, the Agreements contain a merger clause which explicitly and unambiguously supercedes all prior verbal and written agreements. First Agreement, ¶ 23; Second Agreement, ¶ 20, Third Agreement, ¶ 20;
see Topp,
2. Fraudulent Misrepresentation
Likewise, Plaintiffs’ claims for fraudulent misrepresentation are barred by the economic loss rule. “ ‘Misrepresentations relating to the breaching party’s performance of a contract do not give rise to an independent cause of action in tort, because such misrepresentations are interwoven and indistinct
from
the heart of the contractual agreement.’ ”
Cayenta Canada, Inc. v. Orange County, Fla.Bd. Of County Com’rs,
No. 01-cv-1232-Orl22KRS (ACC),
This analysis is not affected by the fact that Lap, a member of Master-craft and officer of MS, was not a signatory of the Agreements. The rationale of the economic loss rule is to limit “a party to the recovery of purely economic damages suffered in a contractual setting.”
Delgado v. J.W. Courtesy Pontiac GMC-Truck, Inc.,
3. Conversion
Plaintiffs’ conversion claim against Lap is not barred by the economic loss rule. An obligation to pay money based on a breach of contract is generally barred by the economic loss rule because it does not entail a breach of duty apart from the obligations of the contract.
Bookworld Trade, Inc. v. Daughters of St. Paul. Inc.,
Plaintiffs’ conversion claim against Lap cannot be referred to arbitra
However, resolution in arbitration of the conversion claims against Master-craft and MS is likely to give rise to a factual inquiry and findings germane to the conversion claim against Lap. Therefore, the conversion claim against Lap will be stayed pending resolution of the claims referred to arbitration.
See Lisa. S.A. v. Mayorga,
C. Motion to Dismiss Claims Against Waterline
Plaintiffs bring a claim for equitable lien and/or constructive trust against Waterline (Count XXIV). “ ‘To impose a constructive trust, there must be (1) a promise, express or implied, (2) transfer of the property and reliance thereon, (3) a confidential relationship and (4) unjust enrichment.’ ”
Whiting-Turner Contracting Co. v. Elec. Mach.,
No. 06-CIV-114-T-17-MSS (EAK),
Plaintiffs have also failed to sufficiently plead a claim for an equitable lien. An equitable lien is “a charge or encumbrance upon the land ‘so that the very thing itself may be proceeded against in an equitable action, and either sold or sequestered under a judicial decree, and its proceeds in the one case, or its rents and profits in the other, applied upon the demand of the creditor in whose favor the lien exists.’ ”
Lake Placid Holding Co. v. Paparone,
D. Motion to Dismiss Claims Against Grosso PA and Grosso
Plaintiffs have sufficiently pleaded claims for breach of fiduciary duty against Grosso PA and Grosso (Counts XXVII and XXVIII). With respect to the earnest money deposits, each of the Agreements states that “[b]uyer hereby acknowledges that the Deposit shall not be held by Seller and shall be used in connection with the construction.” First Agreement Addendum, ¶ 1(c); Second Agreement, ¶ 1(b); Third Agreement, ¶ 1(b). Plaintiffs assert that the portion of this provision stating that “the Deposit shall not be held by Seller” required the funds to be placed in escrow, thereby giving rise to a fiduciary duty that the funds be disbursed according to the terms of the Agreements. Grosso PA and Grosso contend that they owed no fiduciary duty to Plaintiffs because the provision concerning the use of the earnest money deposits simply means that Master-craft and MS were free to use the funds to begin construction. Grosso PA and Gros-so further contend that this interpretation is supported by the fact that the Agreements called for the earnest money deposits to be delivered to Mastercraft and MS, and that the checks were made payable to Mastercraft.
The proper interpretation of this provision is not a matter that can be resolved on a motion to dismiss for failure to state a claim. Interpretation of a clear and unambiguous contractual provision is a question of law properly decided on summary judgment.
See Lockheed Martin Corp. v. Galaxis USA, Ltd.,
222 F Supp.2d 1315, 1323 (M.D.Fla.2002). However, a motion to dismiss for failure to state a claim merely tests the sufficiency of the complaint; it does not decide the merits of the case.
Milburn,
However, the claims already referred to arbitration, although comprising distinct claims against different Defendants, arise
IV. CONCLUSION
For the foregoing reasons, it is
ORDERED AND ADJUDGED that Defendant Waterline Development LLC’s Motion to Dismiss Complaint and/or Motion to Compel Arbitration (dkt #24) is GRANTED IN PART. Count XXIV is hereby DISMISSED. It is further
ORDERED AND ADJUDGED that Defendant Joseph D. Grosso, Jr., P.A. and Joseph D. Grosso, Jr.’s Motion to Dismiss Counts XXVII and XXVIII (dkt # 25) is DENIED. These counts are STAYED pending resolution in arbitration of the Parties’ other claims. It is further
ORDERED AND ADJUDGED that Defendants Mastercraft Development LLC, Mastercraft Services, Inc., and Perry Lap’s Motion to Dismiss Complaint and Compel Arbitration (dkt # 26) is GRANTED IN PART and DENIED IN PART. Counts I through XIV, XVI, XVII, XIX, XX, XXV and XXVI are referred to arbitration. Proceedings on these counts are STAYED pending resolution in arbitration. Counts XV and XVIII are DISMISSED. The motion is DENIED in all respects as to Count XXI. Count XXI is STAYED pending resolution in arbitration of the Parties’ other claims. All surviving claims are stayed for a period of 90 days from the date of this Order. The Clerk of the Court is ordered to administratively CLOSE this case. Upon completion of arbitration, the Parties may seek to reopen this cause for further proceedings on any claim which this Court has not referred to arbitration. If within 90 days arbitration has not been completed, the Parties may seek an extension of time for good cause shown. If the Parties do not seek to reopen the case or seek an extension of time within 90 days, the case shall be dismissed.
