Belmont County Water Dist. v. State of CaliforniaBelmont County Water Dist. v. State of California
Opinion
Plaintiff Belmont County Water District (District) appeals from the trial court’s judgment denying relief in an action seeking damages for inverse condemnation.
On or about January 15, 1969, subsequent to the issuance of the revocable permit, but prior to the actual construction of the pipeline, the City granted respondent State of California a scenic and recreational easement over a long stretch of land including the parcels where appellant’s facilities were located. The primary goal of the grant of easement was to facilitate the construction of the Junípero Serra Freeway (Interstate Highway 280).
The facts, further disclose that as a consequence .of the freeway construction the pipeline could not be built as originally planned. Although its length remained virtually the same, the pipeline had to be relocated, which resulted in an increase in construction cost. Thus, it was shown at the trial that due to terrain changes appellant had to use the more costly "welded steel pipe instead of ductile iron pipe; that because of the steep slopes erosion control devices had to be built along the pipeline; and also that protective casing had to be installed for that portion of the pipeline which traversed the freeway. The parties stipulated that the increased cost stemming from the aforestated changes amounted to $49,791.63.
After receiving oral and documentary evidence, the trial court sitting without a jury found that appellant failed to prove that the permit was irrevocable and concluded that a permit which is revocable at the will of the grantor does not create an interest in real property which is compensable in a condemnation or an inverse condemnation action. Accordingly, the trial court held respondent not liable for the extra costs under the doctrine of inverse condemnation.
In seeking reversal, appellant launches a two-pronged, attack against the trial court’s judgment. First, it contends that a permit revocable when
Equitable Estoppel:
In connection with appellant’s first argument, we emphasize that under well recognized general rules a license is a personal, revocable and unassignable privilege conferred either by writing or parol to do one or more acts on the land without possessing any interest therein. A license by deed or parol is by definition revocable at the pleasure of the licensor and is generally not compensable in a condemnation proceeding
(State of California
ex rel.
Dept. of Water Resources
v.
Texaco, Inc., supra,
at p. 517;
People
ex rel.
Dept. Pub. Wks.
v.
Lundy
(1965)
To the general rule, however, there is an exception. As the court put it in
County of Alameda
v.
Ross
(1939)
An analytical review of the record persuades us that appellant failed to establish the crucial elements of equitable estoppel and thus fell short of bringing itself within the aforestated exception. In so concluding, initially we underscore that the substantial expenditures upon which appellant purports to rest its equitable right had been made not on the pipeline, the subject matter of the present lawsuit, but rather on the construction of the offset shaft and the two reservoirs which, according to the undisputed evidence, were neither damaged nor in any other way affected by the building of the freeway and the relocation of the pipeline. It must also be noted that at the time of the freeway construction the pipeline was not actually laid down, but existed only on appellant’s plans or drawings. All this leads to the inescapable conclusion that when the relocation was ordered the pipeline provisions of the permit were merely executory; and, contraiy to appellant’s sweeping claim of vast expenditures, the sum spent on the pipeline itself amounted to no more than the comparatively insubstantial costs made for the preparation of partial plans and route surveys.
At the same time the record fails to show that in making the claimed expenditure appellant acted in
reasonable
reliance on the infinite duration of the permit. In this context, it bears emphasis that the permit granted by the City bore the black-letter title “Revocable Permit” and in its dispositive part explicitly provided that
“This grant of permission
does not constitute a deed or grant of an easement by the City, is not transferable or assignable, and
is revocable at any time at the will of the Public Utilities
Commission.” (K 2; italics added.) It is true that appellant introduced extrinsic evidence at the trial to demonstrate that the City had never revoked such a permit before. This evidence, however, created
But quite apart from the foregoing deduction, there is another independent reason why appellant’s claim for compensation must be rejected, It has been long settled that in a condemnation or inverse condemnation action
3
licenses and privileges which are unenforceable against the fee owner are not proper subjects of condemnation
(People
ex rel.
Dept. Pub. Wks.
v.
Lundy, supra;
see also
Placer County Water Agency
v.
Jonas
(1969)
The record here shows that the permit at issue was not only revocable, but also conditional. One of the conditions explicitly exempted the City from any liability for any damages caused to the permittee’s property. The other condition provided that the permittee could not interfere with any use of the land by the City, and if any property or structure erected by the permittee would interfere with such usage, the permittee was bound to alter or remove the same at his own expense. 4
Valuable Right Theory:
Appellant’s alternative theoiy is principally premised on
County of San Diego
v.
Miller, supra.
In that case our Supreme Court expressed the view that the property-contract labeling process is not necessarily determinative in questions of due process compensation. Instead, compensation issues should be decided on considerations of fairness and public policy. Consequently, said the court, the right to compensation is to be determined by whether
the condemnation has deprived the claimant of a valuable right
rather than by whether his right can technically be called an “ ‘ “estate” ’ ” or “ 1 “interest” in the land.’ ”
(County of San Diego
v.
Miller, supra,
at p. 691; see also
United States
v.
Fuller
(1973)
One, as pointed out earlier, appellant’s right under the permit was not only revocable, but also conditional. According to the conditions set out in the permit, appellant was not authorized to interfere in any fashion with the landowner’s use of the property. However, the grant of scenic easement for freeway construction purposes constituted a new use of the land by the City with which the original location of the pipeline would obviously have interfered. Under these circumstances, we cannot but conclude that the scenic easement superseded the original terms of the permit as far as the location of the pipeline was concerned, and as a consequence appellant may not claim to have possessed a compensable valuable right with respect to the original location of the pipeline.
Two, appellant’s claim is not supported by equitable or public policy considerations either. On the one hand, it appears that appellant secured the permit at issue without giving any consideration to the City. Appellant took full advantage of the free permit by building the offset shaft, the reservoirs and the pipeline on the City’s land, and thereby obtained access to a second water supply. In addition, the costly investments made on the principal objects (the shaft and reservoirs) indisputably were not affected by the relocation of the pipeline. On the other hand, the record indicates that the relocation of the freeway which, in turn, necessitated the modification of the location of the pipeline, had taken place upon the demand of the City, the fee owner of the land, and also that the requested transfer of the freeway had cost substantial extra expense to respondent. In acknowledgement of the significant additional expenditures to be incurred by respondent, the City gave assurance that “the right of way for the aforesaid relocation shall be furnished without cost to the State of California as partial consideration for said relocation . . . .” (Italics added.)
From the viewpoint of equity, the importance of this latter clause can hardly be overstated. It is manifestly clear that if we should accede to appellant’s claim and order compensation for the increased construction cost of the pipeline, respondent would have a right of indemnification against the City under the cited clause of the easement instrument. This, in turn, would totally defeat both the spirit and letter of the permit which granted merely a revocable, conditional right to appellant while exempting the City from any liability for damages caused to appellant by any reason whatsoever.
The other line of cases deals with vested irrevocable rights, not incipient or conditional privileges which fail to materialize or are superseded by subsequent events. Thus, in County of San Diego v. Miller, supra, the unexercised option to purchase real property was held compensable in an eminent domain action, because as the court pointed out, the right of option creates a cloud on the optionor’s title, is generally assignable, may be exercised also against the successors of the optionor and, even more importantly, because for the period agreed upon by the parties the option is irrevocable by the optionor (p. 688). In Southern Cal. Edison Co. v. Bourgerie, supra, the building restrictions were found to be compensable under article I, section 14, of the California Constitution because they were established by a valid deed and qualified as “property” within the meaning of the cited constitutional provisions.
Finally, we observe that
State of Arizona, Arizona Highway Dept.
v.
United States
(1974)
The judgment is affirmed.
Taylor, P. J., and Rouse, J., concurred.
A petition for a rehearing was denied January 19, 1977.
Notes
Providing for revocation of licenses, section 519, subdivision (4), of the Restatement of Property sets out that “A licensee under such a license as is described in § 514 who has made expenditures of capital or labor in the exercise of his license in reasonable reliance upon representations by the licensor as to the duration of the license, is privileged to continue the use permitted by the license to the extent reasonably necessary to realize upon his expenditures.” (Italics added.)
The trial court found that “Plaintiff has failed to establish by a preponderance of the evidence that the parties to the Revocable Permit—to wit, plaintiff and the City and County of San Francisco—intended said permit to be irrevocable. Rather, the evidence shows that said permit is intended to be revocable at the will of the grantor, the City and County of San Francisco.” (Italics added.) Implicit in this finding is the further determination that appellant was not justified in relying on the irrevocability of the permit.
An inverse condemnation action is an eminent domain proceeding initiated by the property owner rather than the condemner, and the principles which affect the parties’ rights in an inverse condemnation suit are the same as those in an eminent domain action
(Breidert
v.
Southern Pac. Co.
(1964)
The pertinent part of the permit reads as follows: “This permit is granted subject to the following conditions:
“4. Neither the Citv, nor any Commission, Board or officer thereof shall be held responsible or liable for damage to any property of the permittee installed or located on the properties covered by this permit from any cause whatsoever....
“6. The permittee shall, on receipt of notice so to do and within such reasonable time ' limits as may be fixed by said notice, alter or remove at the expense of said permittee any property or structures covered by this permit to such extent as may be necessary to avoid interference with any pipe, pipe lines, power lines or other structures now or hereafter to be constructed by the City, or with any operations of the City or with any use by the City of the land affected hereby or, if so agreed by the General Manager and Chief Engineer of the San Francisco Water Department and the permittee, the permittee may pay to the City the amount of any expense to which the City may be put as a result of such interference.” (Italics added.)
Paragraph 8, subdivision b, of the instrument provides in part that “Nothing herein shall be deemed to nullify, supersede or affect any unrecorded lien, encumbrance, rights or other interest in the lands described herein which was in existence at the time of the recordation of this instrument.” (Italics added.)