194 A.D. 69 | N.Y. App. Div. | 1920
Lead Opinion
On or about the 5th day of August, 1915, the State of New York, through its Commission of Highways, published a notice to contractors calling for bids for the improvement of one and seventeen one-hundredths miles of highway in the city of
When parties exchange promises to perform certain acts upon terms which they have definitely fixed, with the understanding that the promises are to be embodied in a formal contract to be subsequently executed, an enforcible agreement to do the acts specified is thereby made, independently of the execution of a formal contract. (Pratt v. Hudson River R. R. Co., 21 N. Y. 305; Sanders v. P. B. F. Co., 144 id. 209.) It was said by Judge Selden in the first case cited: “If, therefore, it should appear, from the evidence, that the minds of the parties had met; that a proposition for a contract had been made by one party and accepted by the other; that the terms of this contract were, in all respects, definitely understood and agreed upon, and that a part of the mutual understanding was that a written contract, embodying those terms, should be drawn and executed by the respective parties, this is an obligatory contract, which neither party is at liberty to refuse to perform.” It was said by Judge O’Brien in the second case cited: “ In this case it is apparent that the minds of the parties met through the correspondence upon all the terms as well as the subject-matter of the contract, and that the subsequent failure to reduce this contract to the precise form intended, for the reason stated, did not affect the obligations of either party, which had already attached, and they may now resort to the primary evidence of their mutual stipulations.” In our case the formal “ contract agreement,” which the claimant subsequently executed, was on file when the claimant made its bid, and that bid was made, as it was required to be made, to carry out its terms. When the Highway Commission, on the 25th day of August, 1915, sent its notice of acceptance to the claimant, it thereby expressed its assent to all the stipulations, conditions and terms of the “ contract agreement,” and their performance at the prices named in the bid. We have, therefore, at that time a definite offer, an unqualified acceptance, a meeting of the minds, and, therefore, a contract which, upon its approval by the Comptroller, became binding upon both the parties. Unless the
As already noted the Court of Claims has found that the claimant, had it not been unreasonably delayed, could have completed the highway improvement in the fall of 1915. It is an undisputed fact that having been delayed until October 20,1915, it could not thereafter have completed the work that fall. The president of claimant without contradiction testified as follows: “ By the Court: Q. Well, it was too late really to finish the job that fall? A. Yes. Q. Of 1915, wasn’t it? A. From October, it was, Judge, it was too late then.” He testified further that he had a conversation with the division engineer of the Highway Commission, which was as follows: “ Mr. Wait, I got this notification to start this job, but I can’t start it now because I won’t be able to finish it now any more, it is too late. ' Well,’ he says, ‘ I don’t blame you, I don’t think the city of Hudson would stand if you couldn’t finish it,
It is true that claimant by commencing performance in the spring of 1916 waived the breach of contract committed by the State in the fall of 1915 to the extent that the breach would have justified its own abandonment of the contract and a suit for lost profits to be gained from timely performance. It did not, however, waive the breach in the sense that it could no longer sue to recover damages caused thereby. It is the settled law that a contractor who is delayed in commencing work may nevertheless undertake it; that he may complete within a period determined by the contract plus the time of delay; that he may then sue for damages occasioned by the original delay. (Allamon v. Mayor, etc., of Albany, 43 Barb. 33; Weeks v. Rector, etc., of Trinity Church, 56 App. Div. 195; Starbird v. Barrons, 38 N. Y. 230; Cross v. Beard, 26 id. 88; Barnum v. Williams, No. 1, 115 App. Div. 694; Mansfield v. N. Y. C. & H. R. R. R. Co., 102 N. Y. 205.) Any argument made to the contrary is based upon a failure to note that, although conditions may be waived, promises must either be satisfied by performance or extinguished by payment or a seal importing payment. Frequently the performance of a promise by one party to a contract has the double effect of (1) satisfying an obligation and (2) satisfying a condition upon which performance of a promise by the
The judgment should be modified by adding to the recovery the damages which the Court of Claims found were sustained by claimant through its performance of the contract in the year 1916 rather than in the year 1915, and as modified affirmed, with costs to the appellant. An additional finding should be made that the delays occasioned by the State through its Highway Commission necessarily postponed construction of the highway until the year 1916 as actually constructed, and findings 11, 13 and 14 should be disapproved.
All concur, except John M. Kellogg, P. J., and Cochrane, J., dissenting and voting for affirmance, with an opinion by Cochrane, J.
Amdg. State Finance Law, § 16.— [Rep.
Dissenting Opinion
The delay of the State Highway Commissioner until October 20, 1915, did not necessitate the delay of the claimant until'the following year. The court has found at the claimant’s request that it could have completed the work in six weeks which would have made the completion earlier in the year than it was actually completed in the following year. It has also been found at claimant’s request that its road building
I favor an affirmance of the judgment.
John M. Kellogg, P. J., concurs.
Judgment modified by adding to the recovery the damages which the Court of Claims found were sustained by claimant through its performance of the contract in the year 1916 rather than in the year 1915, and as modified affirmed, with costs to the appellant. An additional finding is made that the delays occasioned by the State through its Highway Commission necessarily postponed construction of the highway until the year 1916 as actually constructed; and findings 11, 13 and 14 are disapproved.