Lead Opinion
In this appeal we were originally asked to review two orders of the Georgia Public Service Commission (the “GPSC”), which interpreted the contract between Bell-South Telecommunications, Inc. (“Bell-South”) and MCImetro Access Transmission Services, Inc. (“MCImetro”), and the contract between BellSouth and World-Com Technologies, Inc. (“WorldCom”). Both contracts were interconnection agreements mandated by the Federal Telecommunications Act of 1996, Pub. L. No. 104-104, 110 Stat. 56 (1996) (“FTCA”). The GPSC was asked to interpret the meanings of provisions in each contract which established reciprocal compensation rates for local telephone traffic.
A majority of the judges in active service granted the petition for rehearing en banc filed by MCImetro Access Transmission Services and WorldCom Technologies and vacated the panel opinion in this case. We now address, en banc, the appropriateness of the GPSC’s order and the extent of federal jurisdiction over challenges to that order.
Discussion
To address the natural monopoly in place in the telecommunications industry and promote competition in local telephone service, Congress passed the FTCA in 1996. Pub. L. No. 104-104, 110 Stat. 56. Its regulatory scheme was designed to counteract the deterrence of competition inherent in the high, fixed initial cost of telephone service and the need for all customers to interconnect with one another. Thus, in order to open intrastate telephone markets to competition, it required incumbent Local Exchange Carriers (“ILECs”), such as BellSouth, to share access to loops and exchanges with competing LECs (“CLECs”), like MCImetro and WorldCom. 47 U.S.C. § 251(a)(1).
(e) Approval by State commission.
(1) Approval required.
Any interconnection agreement adopted by negotiation or arbitration shall be submitted for approval to the State commission. A State commission to which an agreement is submitted shall approve or reject the agreement, with written findings as to any deficiencies.
(2) Grounds for rejection.
The State commission may only reject— (A) an agreement (or any portion thereof) adopted by negotiation under subsection (a) of this section if it finds that—
(i) the agreement (or portion thereof) discriminates against a telecommunications carrier not a party to the agreement; or
(ii) the implementation of such agreement or portion is not consistent with*1274 the public interest, convenience, and necessity; or
(B) an agreement (or any portion thereof) adopted by arbitration under subsection (b) if it finds that the agreement does not meet the requirements of section 251 [47 U.S.C. § 251], including the regulations prescribed by the Commission pursuant to section 251 [47 U.S.C. § 251], or the standards set forth in subsection (d) of this section.
(3) Preservation of authority.
Notwithstanding paragraph (2), but subject to section 253 [47 USC § 253], nothing in this section shall prohibit a State commission from establishing or enforcing other requirements of State law in its review of an agreement, including requiring compliance with intrastate telecommunications service quality standards or requirements.
(4) Schedule for decision.
If the State commission does not act to approve or reject the agreement within 90 days after submission by the parties of an agreement adopted by negotiation under [47 U.S.C. § 252(a)], or within 30 days after submission by the parties of an agreement adopted by arbitration under [47 U.S.C. § 252(b) ], the agreement shall be deemed approved. No State court shall have jurisdiction to review the action of a State commission in approving or rejecting an agreement under this section.
(5) Commission to act if State will not act.
If a State commission fails to act to carry out its responsibility under this section in any proceeding or other matter under this section, then the Commission shall issue an order preempting the State commission’s jurisdiction of that proceeding or matter within 90 days after being notified (or taking notice) of such failure, and shall assume the responsibility of the State commission under this section with respect to the proceeding or matter and act for the State commission.
(6)Review of State commission actions. In a case in which a State fails to act as described in paragraph (5), the proceeding by the Commission under such paragraph and any judicial review of the Commission’s actions shall be the exclusive remedies for a State commission’s failure to act. In any case in which a State commission makes a determination under this section, any party aggrieved by such determination may bring an action in an appropriate Federal district court to determine whether the agreement or statement meets the requirements of [47 U.S.C. § 251] and this section.
While § 252 expressly gives state commissions authority to approve or reject interconnection agreements, the statute does not specifically say that this empowerment includes the interpretation and enforcement of interconnection agreements after their initial approval. We agree with all the parties before us, however, that a common sense reading of the statute leads to the conclusion that the authority to approve or reject agreements carries with it the authority to interpret agreements that have already been approved. We find further support for this conclusion in the recent decision of the Supreme Court in Verizon Md., Inc. v. PSC,
The Verizon case involved a public service commission order like the one before
Other circuits have expressly recognized state commissions’ authority to interpret the interconnection agreements at issue. In Bell Atl. Md., Inc. v. MCI WorldCom,
No court has held or suggested that a state commission does not have the authority to interpret and enforce interconnection agreements after they have been approved. Moreover, the entity charged with the implementation of the FTCA, the FCC, has clearly stated that state commissions have the authority to interpret interconnection agreements. In re Starpower, 15 F.C.C.R. 11277. In Starpower, the FCC held that a determination of whether ISP traffic was subject to reciprocal compensation under an interconnection agreement was a determination that a state commission was required to make under § 252(e)(5). Id. In that case, Starpower Communications had asked the FCC to preempt the jurisdiction of the Virginia State Corporation Commission (“Virginia Commission”) to resolve disputes over interconnection agreements between Star-power and Bell Atlantic Virginia and GTE South. Id. As in this case, the dispute in Starpower was over whether calls to ISPs were local calls. Id. Starpower filed petitions with the Virginia Commission against Bell Atlantic and GTE, seeking compensation under the interconnection agreements for calls made to ISPs. Id. The Virginia Commission declined jurisdiction in both of Starpower’s actions. Id. Starpower then petitioned the FCC to hear its complaint. Id. Because the Virginia State Corporation Commission had failed to make a determination concerning the dispute over ISP traffic, the FCC assumed jurisdiction of the dispute.
Moreover, the language of § 252 persuades us that in granting to the public service commissions the power to approve or reject interconnection agreements, Congress intended to include the power to interpret and enforce in the first instance and to subject their determination to challenges in the federal courts. Section 252(e)(6) gives federal courts jurisdiction to review “determinations” made by state commissions. 47 U.S.C. § 252(e)(6). In contrast, § 252(e)(4) abrogates state court jurisdiction “to review the action of a State commission in approving or rejecting an agreement under this section.” 47 U.S.C. § 252(e)(4). The use of the word “determination” in § 252(e)(6) rather than a specific reference to the approval or rejection of agreements leads us to believe that Congress did not intend to limit state commissions’ authority to the mere approval and rejection of agreements. See Russello v. United States,
Given the extensive federal regulation of interconnection agreements and the role state commissions play in their formation, it would be illogical to say that the GPSC's interest in an interconnection agreement is extinguished as soon as the agreement is approved, and that the agreement should thereafter be treated as any other contract.
Additionally, the Supreme Court has specifically held in Verizon that federal courts have jurisdiction under 28 U.S.C. § 1331 to hear challenges to the orders of state public service commissions interpreting interconnection agreements exactly like the one before us.
The resolution of each issue need not depend completely upon an interpretation of federal law. For purposes of 28 U.S.C. § 1331 jurisdiction, all that is required is that there be an arguable claim arising under federal law. As the Supreme Court said in Verizon:
“It is firmly established in our cases that the absence of a valid (as opposed to arguable) cause of action does not implicate subject-matter jurisdiction, i.e., the court’s statutory or constitutional power to adjudicate the case.” ... As we have said, “the district court has jurisdiction if ‘the right of the petitioners to recover under their complaint will be sustained if the Constitution and laws of the United States are given one construction and will be defeated if they are given another,’unless the claim ‘clearly appears to be immaterial and made solely for the purpose of obtaining jurisdiction or where such claim is wholly insubstantial and frivolous.’ ” ... Here, resolution of Verizon’s claim turns on whether the Act, or an FCC ruling issued thereunder, precludes the Commission from ordering payment of reciprocal compensation, and there is no suggestion that Verizon’s claim is “ ‘immaterial’ ” or “ ‘wholly insubstantial and frivolous.’ ”
In this case, as in Verizon, the complaint alleges that the GPSC’s determination is inconsistent with the FTCA and its implementing regulations and also argues that the GPSC erred in its interpretation of the contracts. This involves the same federal question presented in Verizon. Federal courts must resolve the question of whether a public service commission’s order violates federal law and any other federal question as well as any related issue of state law under its pendent state jurisdiction. Thus, pursuant to Verizon, the Georgia Public Service Commission had the authority to interpret and enforce the interconnection agreements that it had approved in the first instance and the federal district court had jurisdiction over this case pursuant to 28 U.S.C. § 1331. Moreover, through the FTCA, Congress conferred upon the public service commissions the power to interpret and enforce the
CONCLUSION
For the foregoing reasons, we conclude that the Georgia Public Service Commission has the authority under federal law to interpret and enforce the interconnection agreements at issue between the parties and that its determination is subject to review in the federal courts. We refer all other issues to a panel of this Court and instruct the Clerk of the Court to assign this case to the next available oral argument panel to resolve the merits of this case.
Notes
. The term "reciprocal compensation rates” simply means that Carrier A would pay Carrier B for any calls made by a Carrier A customer that terminated in Carrier B's network, and vice-versa.
. "Each telecommunications carrier has the duty to interconnect directly or indirectly with the facilities and equipment of other telecommunications carriers.” 47 U.S.C. 251(a)(1).
. "Each local exchange carrier has ... [t]he duty to establish reciprocal compensation arrangements for the transport and termination of telecommunications.” 47 U.S.C. 251(b)(5).
. The plaintiffs in Puerto Rico did not allege a violation of federal law, and the parties did not assert 28 U.S.C. § 1331 as a basis for jurisdiction.
. The court expressly mentioned ''post-approval/rejection determinations” and proceeded to discuss the district court's jurisdiction to review these, not the state commission’s authority to make them. Id.
."If a State commission fails to act to carry out its responsibility under this section in any proceeding or other matter under this section, then the [FCC] shall issue an order preempting the State commission’s jurisdiction of that proceeding or matter ... and shall assume the responsibility of the State commission under this section with respect to the proceeding or matter and act for the State commission.” 47 U.S.C § 252(e).
.The cited decisions relied on an FCC ruling
. An agency's interpretation of a statute is unreasonable and thus does not merit deference if it is "arbitrary, capricious, or clearly contrary to law." Alabama Power Co. v. FERC,
. A state commission's authority to approve or reject an interconnection agreement would itself be undermined if it lacked authority to determine in the first instance the meaning of an agreement that it has approved. A court might ascribe to the agreement a meaning that differs from what the state commission believed it was approving-indeed, the agreement as interpreted by the court may be one the state commission would never have approved in the first place. To deprive the state commission of authorily to interpret the agreement that it has approved would thus subvert the role that Congress prescribed for state commissions.
Concurrence Opinion
concurring, in which BLACK, Circuit Judge, joins:
I concur and join most of the opinion of Judge Barkett. The parties were asked to brief two issues for the en banc court: first, does federal law give state commissions, like the Georgia Public Service Commission (“GPSC”), the authority to resolve disputes between telecommunications carriers regarding the interpretation of the contractual terms of an interconnection agreement that has already been approved pursuant to 47 U.S.C. § 252(e); and, second, if not, does Georgia law give the GPSC this authority.
With respect to the first issue, I agree with Judge Barkett that the most plausible reading of the federal statute is that it contemplates that GPSC not only has the expressly stated authority to approve or reject the interconnection agreement at issue here, but also has the implicit authority to interpret the agreement after it has already been approved. I agree with Judge Barkett. that it would make little sense to grant the obvious authority to interpret the agreement in connection with the approval thereof, but then deny the authority to later implement and enforce same and resolve disputes as to the original interpretation. In so holding, we are joining the numerous circuit courts of appeal discussed by Judge Barkett, and providing appropriate deference to the Federal Communications Commission (“FCC”). See In re Starpower Communications, 15 FCC Red. 11277, 11279, ¶6,
I also agree with Judge Barkett that the district court had jurisdiction pursuant to 28 U.S.C. § 1331 to entertain BellSouth’s claim in the instant case.
BellSouth’s claim in the instant case is that the GPSC order is inconsistent with the Act and its implementing regulations. BellSouth’s claim is indistinguishable from that asserted by Verizon in the Supreme Court case. Verizon had taken the position that “it would no longer pay reciprocal compensation for telephone calls made by Verizon’s customers to the local access numbers of internet providers (‘ISPs’), claiming that ISP traffic was not ‘local traffic’ subject to the reciprocal compensation agreement.” Id. at 1757. After Maryland’s Public Service Commission ruled against it, Verizon filed a complaint in the district court challenging the Public Service Commission’s order, and claiming “that the determination that Verizon must pay reciprocal compensation ... for ISP traffic violated the 1996 Act, and the FCC ruling.” Id. BellSouth’s claim is identical. Like Verizon, BellSouth claims that the GPSC order here, construing ISP calls as “local” and requiring BellSouth to pay reciprocal compensation, violates the Act and its implementing regulations. As in Verizon, BellSouth relies upon the FCC ruling characterizing such ISP traffic as non-local. The instant case being indistinguishable from Verizon with respect to the § 1331 jurisdictional issue, I readily conclude that the district court had original jurisdiction of BellSouth’s claim pursuant to § 1331.
First, BellSouth points out that the interconnection agreement at issue here was mandated by federal statute. 47 U.S.C. § 251(b)(5).
Second, the federal statute mandates that it be nondiscriminatory. 47 U.S.C. § 252(e)(2)(A)(i). This means that the terms of the agreement must be available to all carriers, similar to a tariff.
Third, the statute mandates that the terms of the agreement must be consistent with the public interest, convenience and necessity. 47 U.S.C. § 252(e)(2)(A)(ii). BellSouth implicitly suggests that this provision probably adopts and perhaps federalizes well-established state standards.
Fourth, in addition as a practical matter, even a voluntarily negotiated agreement, as here, is cabined by the obvious recognition that the parties to the agreement had to agree within the parameters fixed by the federal standards set out in 47 U.S.C. §§ 251 and 252. BellSouth reasons that the negotiating parties obviously know that if they do not agree, such standards will be imposed. Section 252(b). Thus, the parties know that they cannot deviate significantly from all of the federally imposed standards. Accordingly, BellSouth argues that significant nondiscriminatory and public convenience standards are absolutely mandatory, and that the rest of the federal standards, including the pricing standards of § 252(d), are as a practical matter “coerced” by the federal statute into such agreements.
Fifth, and significant in light of the particular matter at issue — whether ISP calls are “local telecommunications traffic”— BellSouth points out that the definition of “local telecommunications traffic” is set out in regulations promulgated by the FCC. 47 C.F.R. § 51.701(b). BellSouth argues that the construction of that federal definition presents a federal question.
Sixth, further with respect to the particular matter at issue, BellSouth argues that the FCC has ruled that ISP calls, such as the ones at issue here, are interstate rather than local in nature, and therefore not governed by the reciprocal compensation provision of § 251(b)(5). See Implementation of the Local Competition Provisions in the Telecommunications Act of 1996, Inter-Carrier Compensation for ISP-
Seventh, the Supreme Court in Verizon, indicated in dicta that § 252(e)(6)
Finally, BeUSouth argues that the interconnection agreement at issue here should not be considered an ordinary commercial contract because it reaby constitutes a kind of federally mandated agreement,
Considering BellSouth’s arguments,
In sum, I conclude that the GPSC had authority to entertain this case, and that the district court had jurisdiction under 28 U.S.C. § 1331 to entertain the claim presented by BellSouth.
. Because there is § 1331 jurisdiction, I would not address whether there may also be jurisdiction under 47 U.S.C. § 252(e)(6). To the same effect, see Verizon Md., Inc. v. Pub. Serv. Comm’n of Md.,
. No party suggests that there is any difference in the language or substance of the interconnection agreement in the two cases that would affect the resolution of this case.
. Judge Tjoflat's comprehensive and forceful opinion deserves comment. Whatever the merit of Judge Tjoflat’s position, I respectfully suggest that it is not consistent with Verizon. In attempting to distinguish BellSouth’s claim from that of Verizon, Judge Tjoflat draws a distinction between an argument that the agency order is preempted by a federal statute, on the one hand, and on the other hand, an argument that the agency order violated the statute and its implementing regulations. Judge Tjoflat posits that Verizon held there was § 1331 jurisdiction over the former, but not the latter. I respectfully submit that this attempt to parse the language of the Verizon opinion is not consistent with the opinion itself. Rather, Justice Scalia’s opinion equates the argument that the agency order violated the Act and the FCC ruling, with the argument that the order was preempted by federal statute.
Verizon alleged in its complaint that the Commission violated the Act and the FCC ruling when it ordered payment of reciprocal compensation for ISP-bound calls. Verizon sought a declaratory judgment that the Commission's order was unlawful, and an injunction prohibiting its enforcement. We have no doubt that federal courts have jurisdiction under § 1331 to entertain such a suit. Verizon seeks relief from the Commission's order "on the ground that such regulation is pre-empted by a federal statute which, by virtue of the Supremacy Clause of the Constitution must prevail," and its claim "thus presents a federal question which the federal courts have jurisdiction under 28 U.S.C. § 1331 to resolve.” Shaw v. Delta Air Lines, Inc.,
Id. at 1758. The Court first states Verizon's claim as being that the order "violated the Act and the FCC ruling,” and with respect to that claim the Court stated: "We have no doubt that federal courts have jurisdiction under § 1331 to entertain such a suit.” Then the Court apparently restates the same claim in
Judge Tjoflat also expresses concern that all state public service commission decisions affecting interconnection agreements will be deemed federal questions and will flood the federal courts. I would not address such other claims; I would address only the claim asserted by BellSouth here, which I submit is the same claim presented by Verizon to the Supreme Court. Incidentally, I note that BellSouth never asserts in its briefs on appeal a state law contract claim. Indeed, BellSouth notes that the district court in an “alternative holding" did address a state contract law issue, but BellSouth argues only that such issue is irrelevant because the contract is governed by federal law and the FCC rulings. Thus, the potential claim — a pure state law claim — that concerns Judge Tjoflat has not been argued and is not before us.
. Section 252(e)(6) provides: "In any case in which a State commission makes a determination under this section, any party aggrieved by such determination may bring an action in an appropriate Federal district court to determine whether the agreement or statement meets the requirements of §§ 251 and 252."
. BellSouth points out that federal law requires of BellSouth the following with respect to the interconnection agreements: (1) to negotiate these agreements to discharge their obligations under the federal act; (2) to enter into good-faith negotiations with a CLEC against its wishes and indeed, even if state law would otherwise prohibit such inter-carrier negotiations and agreements; (3) to agree within the minimum terms subject to governmental approval; (4) to publicly file the agreements; (5) to make the same terms and conditions available to any requesting CLEC; and (6) to provide service in accordance with an approved agreement.
. Bell South distinguishes Jackson Transit Auth. v. Local Division 1285,
. Perhaps the best judicial expression of Bell-South's arguments appears in Southwestern Bell Tel. v. Connect Communications Corp.,
. Because I conclude that the district court has original jurisdiction under 28 U.S.C. § 1331, I need not address whether or not there would have been supplemental jurisdiction under 28 U.S.C. § 1367 if BellSouth had also presented a pure state law claim.
Concurrence Opinion
concurring,
I concur in Judge Anderson’s separate opinion. I write to expand upon the deference this Court owes the decisions of the Federal Communications Commission under Chevron, U.S.A., Inc. v. Natural Res. Def. Counsel,
As Judge Barkett states, agency interpretations of the statutes they are charged with administering are entitled to deference under a two-step analysis. First, if Congress has spoken to the precise question at issue, then the unambiguously expressed intent of Congress governs. Id. at 842-43,
At Chevron step one, the precise question at issue here has no clear answer in the statutory text. We granted rehearing en banc to answer the following question:
Does federal law, specifically 47 U.S.C. §§ 251 and 252, give state commissions, like the GPSC, the authority to resolve disputes between telecommunications carriers regarding the interpretation of the contractual terms of an interconnection agreement that has already been approved pursuant to 47 U.S.C. § 252(e)?
No statutory text clearly authorizes or forecloses PSC adjudications of post-agreement disputes. The statute authorizes PSCs to “approve or reject” interconnection agreements submitted to them. 47 U.S.C. § 252(e)(1). The statute goes on, however, to refer to “determination[s] under this section.” Id. § 252(e)(6). While it may be possible to cabin these “determinations” to PSC decisions approving or rejecting interconnection agreements, “determinations” can also be fairly construed to encompass determinations in post-agreement disputes. Congress could have easily avoided this interpretation by replacing the phrase “makes a determination under this section” in § 252(e)(6) with the words “approves or rejects.” In this statutory context, the narrower interpretation is hardly the “unambiguously expressed intent of Congress.” Chevron,
Nor is the deference owed to FCC altered by any dissatisfaction we may have with the quality of the agency’s legal reasoning in Starpower. Agencies derive their authority to interpret the statutes they administer — and thereby bind federal courts — from Congressional delegation. Chevron,
It follows, therefore, that deference to an agency interpretation is not automati
I do not think FCC’s Starpower decision is based on an impermissible construction of the Telecommunications Act, so we must defer to the agency’s interpretation. I concur with the conclusion that the Georgia Public Services Commission has the authority to interpret and enforce the interconnection agreements at issue here.
. Judge Tjoflat now claims the statute is unambiguous, indeed, that it is "clear as a bell.” Tjoflat opinion at 1304. I note, however, Judge Tjoflat’s earlier Chevron analysis concluded that the statute was silent on the precise question at issue. See BellSouth Telecomms., Inc. v. MCImetro Access Transmissions Servs., Inc.,
. Judge Tjoflat asserts Chevron deference is grounded in the expertise of agency decision-makers, suggesting that where agencies fail to exercise their expertise, they are entitled to no deference. Tjoflat opinion at 1304-1305. The Supreme Court in Chevron, however, cited Congressional delegation — not inherent agency expertise — as the source of the authority afforded administrative agencies. See Chevron,
. Judge Tjoflat does not argue that FCC's Starpower decision was procedurally defective or arbitrary and capricious. As discussed above, the ambiguity that exists in the Telecommunications Act means that FCC's interpretation is not manifestly contrary to the statute.
. While Judge Tjoflat says initially that he only "hesitates” to defer to FCC’s interpretation because of its reliance on the precedents of our sister circuits, Tjoflat opinion at 1305, he later cites this as a sufficient reason not to defer. Tjoflat opinion at 1305 ("Any of these five reasons standing alone would eliminate the requirement of deference.”).
. There are certain well known exceptions to this common law understanding of the authority of judicial decisionmaking. See, e.g., Rodriguez de Quijos v. Shearson/American Express,
. For this reason, I think it does not matter that FCC’s interpretation is ”[h]ardly a model of legal reasoning.” Tjoflat opinion at 1305, n. 37. Nor is there any problem posed by litigants’ allegedly "laundering” circuit court opinions through administrative agencies. Tjoflat opinion at 1305. If an administrative agency has been delegated authority by Congress to resolve statutory ambiguities, then we can expect the agency to exercise that delegated authority in good faith. If, in its considered judgment, the agency agrees with the result reached by circuit courts confronting the same issue, it can exercise its authority (consistent with any applicable limitations on that authority) to interpret the statute in accordance with those judicial opinions. The agency’s interpretation would then be entitled to deference, not because of the authority of the precedents it relied upon, but only because of the authority Congress delegated to the agency to make a decision. Within certain limits, see Mead Corp.,
Dissenting Opinion
dissenting,
I. Background
A. The Telecommunications Act of 1996 and reciprocal compensation
In 1996, Congress amended the Communications Act of 1934, see Telecommunications Act of 1996 (“1996 Act”), Pub. L. 104-104, 110 Stat. 56 (codified at 47 U.S.C. § 151 et seq.), in an effort to deregulate the telecommunications industry — especially the local exchanges once thought to be entrenched natural monopolies. Sections 251 and 252 form the heart of the 1996 Act. Section 251 imposes several obligations on incumbent local exchange carriers (“ILECs”).
One obligation that all LECs have under section 251 is the duty to form a reciprocal compensation agreement with competing LECs. See 47 U.S.C. § 251(b)(5). When a customer of LEC A calls a customer of LEC B, LEC B is entitled to demand compensation for terminating the call of LEC A’s customer. One option the LECs have is to agree to a “bill and keep” system of compensation whereby each LEC considers the total termination costs a wash, thereby eliminating the necessity of a billing arrangement and its concomitant
The FCC eventually weighed in, however, in an effort to fix the perceived asymmetry.
B. This dispute
The ILEC in this case, BellSouth Telecommunications, Inc. (“BellSouth”), declined to pay reciprocal compensation fees to various CLECs. The Georgia Public Service Commission (“GPSC”) adjudicated the dispute, holding that the parties were required to compensate each other for the termination of ISP-bound calls.
I would hold that (1) the authority of the GPSC under Georgia law is a state law issue that this court should decline to reach, and that federal law does not preclude PSCs from adjudicating post-agreement disputes if states make the choice to allocate adjudicative power to their PSCs; (2) the district court did not have jurisdiction under 47 U.S.C. § 252(e)(6) for several reasons, not least among which is the fact that the plain language of the statute does not provide for appellate review in the district courts of PSC adjudications of post-agreement disputes; (3) the district court did not have jurisdiction under 28 U.S.C. § 1331 over any of the claims Bell-South now presses on appeal,
II. Section 1331 Jurisdiction
A. Is there section 1SS1 jurisdiction if one assumes, arguendo, that the proceeding before the district court was an “original”proceeding?
There are many claims in this litigation that are allegedly federal in nature. Assuming, for the moment, that the litigation before the district court in this case was an “original” proceeding, it is questionable whether all of BellSouth’s complaints
1. Federal preemption
One contention in BellSouth’s “petition for judicial review” is that the GPSC’s Order violates the 1996 Act and the FCC’s regulations thereunder. Although the “petition for judicial review” is unclear on this point, I think I understand BellSouth to be adopting the position more clearly articulated by the plaintiff in Verizon, where the plaintiff sought relief “on the ground that such regulation is pre-empted by a federal statute which, by virtue of the Supremacy Clause of the Constitution, must prevail.” Verizon,
On appeal, BellSouth no longer disputes that the GSPC could have ordered the parties to pay each other for the termination of ISP-bound calls, and for good reason: the FCC has consistently promulgated regulations, consistent with the 1996 Act’s affinity for voluntary agreements, that enable ILECs and CLECs to enter into reciprocal compensation agreements on the subject of ISP-bound traffic notwithstanding any federal regulations that might deem ISP-bound traffic “interstate” as a matter of law. In the FCC’s first (and now-vacated) ISP ruling, for example, the FCC was careful to note that “parties may voluntarily include this [ISP-bound] traffic within the scope of their interconnection agreements” as those agreements are “interpreted and enforced by state commissions.” Implementation of the Local Competition Provisions in the Tele-comms. Act of 1996; Intercarrier Compensation for ISP-Bound Traffic, 14 F.C.C.R. 3689, ¶12, at 3703,
2. “Coerced” contracts and federal common law
Another argument is that either the rule of decision for all post-agreement disputes is some sort of federal common law of contracts, or else the disputes “arise under” federal law even if state law provides the rule of decision because the agreements are “coerced” by the federal government and they are an integral part of a federal regulatory scheme. Therefore, BellSouth argues, all interconnection disputes can wind up in federal court pursuant to 28 U.S.C. § 1331.
a. “Coerced” contracts
The fact that the interconnection agreements are “coerced” and made pursuant to a federal regulatory scheme is not enough to make run-of-the-mill contract claims— say, a dispute over performance or price— subject to section 1331 jurisdiction. If state law is the rule of decision, then ordinary contract claims would not raise a “federal issue” for district courts to resolve. Indeed, one Supreme Court case has expressly held that a federally compelled contractual provision was not to be construed in federal court under principles of federal law, but rather under state law applied in state courts. See Jackson Transit Auth. v. Local Div. 1285, Amalgamated Transit Union,
Many post-agreement interconnection disputes would raise only state law claims, and any federal ingredient would be so far removed from the issues for judicial resolution that many claims would not even come close to what Justice Frankfurter called the “litigation provoking problem” of a federal element in a state law cause of action. See Textile Workers Union of Am. v. Lincoln Mills of Ala.,
If interconnection agreements are to be interpreted under a federal common law of contracts, then all post-agreement disputes would raise a federal question and thereby satisfy the “arising under” requirement of 28 U.S.C. § 1331. However, there is no compelling reason why federal common law should be the rule of decision in adjudications of post-agreement disputes between CLECs and ILECs.
There is no indication in the 1996 Act that Congress intended the rule of decision to be one of federal common law. The fact that the contracts are “coerced” is inappo-site; as the Court held in Jackson Transit Auth., supra, federally compelled contractual provisions are not necessarily to be construed in federal court under principles of federal common law. Jackson,
Without explicit congressional authorization for the courts to craft common-law rules for interpreting interconnection agreements, state law must be the rule of decision. Professor Chemerinsky describes the presumption against federal common law:
There long has been a strong presumption against the federal courts fashioning common law to decide cases. The Rules of Decision Act, which was part of the Judiciary Act of 1789 and which remains largely unchanged to this day, states that “the laws of the several states, except where the Constitution or treaties of the United States or Acts of Congress otherwise require or provide, shall be regarded as rules of decisions in civil actions in the courts of the United States, in eases where they apply.” 28 U.S.C. § 1652. This law, by its very terms, seems to deny the existence of federal common law; the Rules of Decision Act commands that in the absence of positive federal law, federal courts must apply state law.
See Erwin Chemerinsky, Federal Jurisdiction § 6.1, at 350 (3d ed. 1999) (footnote omitted).
In a narrow category of cases, Congress has authorized federal courts to create a body of common law rules. See, e.g., Textile Workers Union of Am. v. Lincoln Mills of Ala.,
There is no clear congressional intent for courts to craft common law rules in the context of disputes over interconnection agreements. Indeed, the invocation of federal common law would be in considerable tension with the reverse-preemption provision in the 1996 Act and the Act’s scheme of cooperative federalism (both of which are discussed in part III.A, infra) by ceding new authority to the federal courts where none existed before, while simultaneously displacing state law.
A final position BellSouth takes is that (a) the parties intended that their mutual obligations under the interconnection agreement track evolving standards of federal law and (b) federal law provides that ISP-bound traffic is “interstate” rather than “local” and therefore LECs need not pay each other for the termination of ISP-bound calls. This is the argument that BellSouth has advanced throughout this litigation, though one is hard pressed to find it in its “petition for judicial review.” After reciting at length the definitions of various terms under FCC regulations, BellSouth states in paragraph 81 that “[i]t was in the context of the foregoing provisions of law that BellSouth and MFS/WorldCom executed the Interconnection Agreement.” In paragraph 53, BellSouth alleges that “the PSC’s Order holding that the use of local facilities to connect to an ISP constitutes Local Traffic under the Interconnection Agreement is inconsistent with the facts, and contrary to the provisions of the 1996 Act.” I will stretch these sentences, respectively, to mean that (a) the parties intended to track federal law and (b) federal law means X rather than, as the GSPC held, Y. See Lykins v. Pointer, Inc., 725 F.2d 645, 646 (11th Cir.1984) (holding that a district court could exercise federal tort claim liability jurisdiction, despite the plaintiffs failure to allege statutory authority for such jurisdiction, because the requisite facts were alleged). Resolution of this claim boils down to contractual interpretation — namely, whether the parties intended to compensate each other for the termination of ISP-bound calls. It is therefore a state law claim.
This claim, then, squarely confronts this court with the “litigation provoking problem” of a federal issue embedded in a state law cause of action. In Smith v. Kansas City Title & Trust Co.,
In the case at bar, it is unclear whether there would be jurisdiction under the framework established in Merrell Dow. On one hand, the federal element — a mere declaratory ruling by the FCC that ISP-bound traffic is “interstate” — is clearly not a federal cause of action. On the other
B. Was the proceeding below an “original” proceeding?
I. Are all 47 U.S.C. § 252(e)(6) proceedings, in which LECs seek review of PSC orders in federal district court, undertaken pursuant to the original jurisdiction of district courts under 28 U.S.C. § 1331?
At first blush, it may appear strange to call the district court’s posture in the 47 U.S.C. § 252(e)(6) context to be that of a court asserting “original” jurisdiction. After all, the district court is reviewing the ruling of a lower body, and the district court’s role therefore seems to be “appellate” in nature. However, there is a color-able argument that all such proceedings are, in fact, “original.” If this argument prevails, then the proceeding in the district court below was an “original” proceeding, and the district court might have had jurisdiction over the state law claim depending upon how an analysis of the case under Merrell Dow would be resolved.
a. “Yes”: A potential argument
In Verizon, the Court asserted that section 252(e)(6) may not be a jurisdictional provision; rather, it might be a provision that confers a private right of action. See Verizon,
One must ask, then, what is the jurisdictional basis for district court review of accept-or-reject determinations that PSCs must make pursuant to § 252(e)(1)? Since there must be a jurisdictional basis outside of § 252(e)(6), then it is tempting to look at 28 U.S.C. § 1331. That provision states: “The district courts shall have original jurisdiction of all civil actions arising under the Constitution, laws, or treaties of the United States.” The italicized term is striking: section 1331 is about “original” rather than “appellate” jurisdiction. Suppose, for example, that a PSC arbitrates an interconnection agreement. Suppose further that a CLEC feels that the PSC has not required the ILEC to meet all of the obligations that is required of it under 47 U.S.C. § 251, and it seeks review of the PSC’s determination in federal district court. Is the proceeding before the district court an “original” proceeding? If it is not, then § 252(e)(6) is without effect; Congress drafted a private cause of action, but district courts have no jurisdiction to review PSCs because Congress did not amend 28 U.S.C. § 1331 to provide for appellate jurisdiction in the district courts.
One option is contend that jurisdiction under section 1331, in the context of an
After Verizon, we are thus left with four possible conclusions: (1) appellate jurisdiction and 28 U.S.C. § 1331 can coincide with respect to the same claim;
b. “No”: The Better Argument
A reading of Verizon that would tag the nature of district court review of PSC orders with the “original” label poses several problems that ultimately force me to take option four rather than option three. First, anyone familiar with Anglo-American jurisprudence would believe that the district court’s posture in the accept-or-reject setting is that of an appellate court. Compare Black’s Law Dictionary 98 (6th ed. 1990) (defining “appellate jurisdiction” as “jurisdiction to revise or correct the proceedings in a cause already instituted and acted upon by an inferior court, or by a tribunal having the attributes of a court”), with id. at 1099 (defining “original jurisdiction” as “jurisdiction to consider the case in the first instance”). In the example of the CLEC challenge described above, the PSC considers the case “in the first instance,” while the district court is being asked to “correct the proceedings in
More importantly, 47 U.S.C. § 252(e)(5) provides that the FCC is to make the accept-or-reject determination if the PSC does not act. As Justice Souter points out in his opinion, see Verizon,
Two other considerations inform my conclusion that the proceedings before district courts on review of PSC orders are appellate proceedings. First, three Justices of the Supreme Court agreed with an opinion that explicitly called the district court’s posture to be that of an “appellate” court.
Since district court review of PSC accept-or-reject determinations is an “appellate” rather than “original” proceeding, this leaves me with option four: I decline to read the Court’s suggestion that 47 U.S.C. § 252(e)(6) is a “private right of action” as a holding. Since this conclusion is, in fact, the best reading of the Court’s language, I read the Court’s discussion as dieta and distinguish the present case from Verizon.
The Verizon Court never analyzed whether the 47 U.S.C. § 252(e)(6) is a private right of action. It never invoked the factors employed in Cort v. Ash,
My reading is consistent with the facts in Verizon. In that case, the plaintiff claimed that federal law precluded the Maryland PSC from ordering the payment of reciprocal compensation, notwithstanding the PSC’s conclusion that, under principles of state contract law, the parties agreed to pay each other for the termination of ISP-bound calls. As the Court put it: “Verizon [sought] relief from the Commission’s order on the ground that such regulation is pre-empted by a federal statute which, by virtue of the Supremacy Clause of the Constitution, must prevail.” Verizon,
2. Was the proceeding below, in which BellSouth sought review of the PSC Order in federal district court, undertaken pursuant to the original jurisdiction of the district court under 28 U.S.C. § 1331?
The answer to this question is a resounding “no.” As stated in part II.A.1, BellSouth abandoned its Verizon-like claim that the GPSC was preempted by federal law and therefore could not order the payment of reciprocal compensation fees for ISP-bound traffic. The district court had original jurisdiction over this claim, because the crux of the claim is that the PSC did something illegal. A private right of action — whether under the Constitution directly (pursuant to Shaw) or 42 U.S.C. § 1983 — provides the vehicle for such a claim. The only potential claim left is the state law claim with a federal element. See supra part II.A.3. In short, BellSouth argues that (a) the GPSC agreed that the parties intended to track federal law
Indeed, BellSouth itself must have believed that the proceeding below was an “appellate” proceeding. If it were an original proceeding, BellSouth would have asked the district court to ignore the PSC’s Order entirely. Instead, it argued before the district court that (a) the GPSC believed that the parties intended to track federal law and (b) that this conclusion was correct, but that the GPSC got the law part wrong. It asked the court, in short, to give vitality to part of the GPSC’s analysis rather than ignoring it entirely. Moreover, paragraph 57 of BellSouth’s “petition for judicial review” asks the district court to “reverse” the PSC Order because it was “erroneous as a matter of law.” That language is typical of appellate proceedings, not original proceedings.
III. Section 252(e)(6) Jurisdiction A. The source of PSC authority to interpret and enforce interconnection agreements is not section 252(e)(1), but residual authority reserved to states under the 1996 Act
Proponents of federal jurisdiction are eager to find that the source of PSC authority to interpret and enforce voluntary agreements resides in section 252(e)(1) rather than residual authority under the 1996 Act,
I am convinced that PSC authority does not reside in section 252(e)(1). My primary reason is that the plain language of the 1996 Act says nothing of the sort. I have looked long and hard at the provision, and I find only this language: “A State commission to which an agreement is submitted shall approve or reject the agreement, with written findings as to any deficiencies.” 47 U.S.C. § 252(e)(1) (emphasis added). BellSouth asks this court to in-serf by judicial fiat the following additional language: “State commissions shall also enforce and interpret interconnection agreements if any post-agreement dispute arises.” It is up to Congress, not judges, to make this proposed statutory amendment, and I decline to read into the statute language that does not exist. To the majority, it would not make sense to grant PSCs authority to ensure that interconnection agreements comply with the requirements of the 1996 Act on the front end without also instructing PSCs to engage in post-agreement adjudication on the back end. I will show in due time why Congress’s choice made perfect sense. For now, it is enough to say that the authority is not found within the text of 47 U.S.C. § 252(e)(1). “[O]ur problem is to construe what Congress has written. After all, Congress expresses its purpose by words. It is for us to ascertain — neither to add nor to subtract, neither to delete nor to distort.” 62 Cases, More or Less, Each Containing Six Jars of Jam v. U.S.,
Aside from the obvious separation-of-powers concern, there are two additional problems with judicially manipulating section 252(e)(1) so as to insert language about post-agreement adjudication. First, since this interpretation would give federal courts jurisdiction to review all interconnection disputes under section 252(e)(6), such as price and performance disputes, all of the problems discussed in part III.B, infra, apply. Second, this reading would foreclose states from allocating adjudicative authority to enforce and interpret interconnection agreements to state trial courts rather than state PSCs, and Con-
It is not section 252(e)(1), but rather residual authority left to states under the 1996 Act that gives states (and potentially PSCs, if the state so chooses) authority to interpret and enforce interconnection agreements.
Suppose that prior to 1996, a Bell Operating Company in State X desired to let a CLEC interconnect with its system (for a fee, of course). The state, invoking its exclusive authority over the intrastate arena, would (a) decide whether to permit the new entry; (b) possibly require (i) certain contractual provisions and/or (ii) state approval of the final ILEC/CLEC agreement; and (c) adjudicate any post-agreement dispute. Moreover, the state would have authority to designate the entity charged with each particular task. The chosen entity might well be a court, regulatory agency, or even the legislature itself. The 1996 Act altered the scope of state authority, but this alteration was only partial. For example, states no longer have the choice to deny new entry altogether, and so state authority to undertake task (a) has been completely abrogated. See 47 U.S.C. § 25S (“Removal of barriers to entry”).
B. Why there is no jurisdiction under section 252(e)(6)
1. Plain language
Having determined that the GPSC’s authority to enforce and interpret interconnection agreements does not arise from section 252(e)(1), I know that federal jurisdiction does not exist under section
2. Cooperative federalism and the presumption against federal jurisdiction
Clearly, state commission decisions that are not expressly designated for review in federal court are left for. review by state courts, as provided by the existing law of the state that created the state commission. The reverse-preemption provision of the 1996 Act stands for the proposition that state jurisdiction should be retained (to the exclusion of federal jurisdiction) unless there is a clear statement to the contrary. Another clear statement rule is at play in this case: because federal courts are courts of limited jurisdiction, when their jurisdiction is created by statute, the statute is strictly construed. See Turner v. Bank of N. Am.,
3. Special problems of deference; protective jurisdiction reconsidered
If the proponents of section 252(e)(6) jurisdiction are correct, what rule of decision must state PSCs utilize in adjudicating generic contract disputes, such as whether the parties have performed under the terms of an interconnection agreement? And what level of deference, if any, must federal courts give to the PSC’s conclusion? Under my interpretation of the 1996 Act, the answer is easy: state entities (whether a PSC or trial court) review contracts under state law, and appeals are taken as provided by state rules of appellate review. Under the opposing view, these questions become intractable problems which lead to absurd results, lending further credence to the proposition that federal jurisdiction was never intended by Congress.
Perhaps anticipating these devastating arguments, BellSouth concedes that the rule of decision might well be state law.
I also note that if the statutory scheme were interpreted so as to prescribe federal review of state entities on questions of state law, the scheme would push the boundaries of Congress’s authority under Article III to define the scope of federal jurisdiction.
4. Other circuits
Against this array of arguments consisting of (1) venerable principles of federal jurisdiction (i.e., the presumption against federal jurisdiction and the presumption against federal common law); (2) the reverse-preemption provision and the 1996 Act’s scheme of cooperative federalism; (3) the constitutional avoidance canon; and (4) a host of intractable problems that federal jurisdiction would yield, one would think that proponents of jurisdiction would be able to point to an ultra-clear statement that Congress intended federal jurisdiction to exist over all run-of-the-mill disputes regarding compliance with existing interconnection agreements. As part III.B.l demonstrates, however, the plain language of the 1996 Act leads to the opposite conclusion, further buttressing the argument against jurisdiction under section 252(e)(6). Instead, proponents of federal jurisdiction (both litigants and courts) point to amorphous concepts of “inherent” jurisdiction
The Seventh circuit stated simply, “Decisions of state agencies implementing the 1996 Act are renewable in federal district courts,” without providing analysis to support this broad statement in the context of a suit challenging a commission’s interpretation or enforcement actions. Illinois Bell,179 F.3d at 570 (quoting an earlier order in the same case that was similarly devoid of jurisdictional analysis, see Illinois Bell Tel. Co. v. WorldCom Techs., Inc.,157 F.3d 500 , 501 (7th Cir.1998)). And the Eight Circuit, in dictum and without analysis, first stated its “belie[f] that the enforcement decisions of state commissions would ... be subject to federal district court review under subsection 252(e)(6).” Iowa Utils. Bd. v. FCC,120 F.3d at 804 n. 24. This statement appeared in a footnote in a section of analysis that the Supreme Court held the Eight Circuit should not have reached because the issue was not ripe for review. See Iowa Utils.,525 U.S. at 386 ,119 S.Ct. 721 . Then later, it simply deferred to the FCC in finding jurisdiction. See Southwestern Bell Tel. Co. v. Connect Communications Corp.,225 F.3d 942 , 946 (8th Cir.2000).
The Fifth Circuit held that “federal court jurisdiction extends to review of state commission rulings on complaints pertaining to interconnection agreements and that such jurisdiction is not restricted to mere approval or rejection of such agreements.” Southwestern Bell Tel. Co. v. Public Util. Comm’n,208 F.3d 475 , 481 (5th Cir.2000). In reaching this conclusion, the court recognized that § 252(e)(6) could be read literally to limit federal review of State commissions to decisions “approving, or disapproving, or arbitrating, an interconnection agreement.” Id. at 479. But the court rejected that reading because it concluded, “We do not think such a narrow construction was intended.” Id. The court then reasoned that assignment to State commissions “of plenary authority to approve or disapprove these interconnection agreements necessarily carries with it the authority to interpret and enforce the provisions of [such] agreements.” Id.
Bell Atl. Md., Inc.,
5. Chevron Deference
Sensing that conclusory assertions about “inherent” jurisdiction will not carry the day, proponents of federal jurisdiction mount one last ditch effort by invoking Chevron deference. See Chevron, U.S.A., Inc. v. Natural Res. Def. Counsel,
I do not think Chevron deference is appropriate in this case. First, section 252(e)(1) lists only two possible PSC “determinations” (i.e., to approve or reject an agreement); section 252(e)(6) cabins federal jurisdiction to section 252(e)(1) determinations by its very terms. The statute is clear as a bell, and no deference is owed when the statute is unambiguous. Second, the clear statement rules and absurdities discussed above reinforce my conclusion that Congress did not intend section
6. Summary of section 252(e)(6) argument
The jurisdictional question before this court — whether U.S. district courts have jurisdiction to review all PSC orders interpreting and enforcing voluntary interconnection agreements under 47 U.S.C. § 252(e)(6) — could be decided in one of several ways. First, we might conclude, as the panel did, that the silence of 47 U.S.C. § 252(e)(1). on the subject of PSC adjudication of post-agreement disputes is tantamount to a congressional conclusion that PSCs are precluded from adjudicating interconnection disputes. Second, we might conclude that 47 U.S.C. § 252(e)(1) grants PSCs “inherent” authority to interpret and enforce interconnection agree
The Fourth Circuit recognized that interconnection disputes “may amount to tens of thousands of cases.” See Bell Atl. Md., Inc. v. MCI WorldCom, Inc.,
IV. Section 1367 Jurisdiction
The supplemental jurisdiction statute provides that “in any civil action of which
V. Unclear GPSC Order
After examining the GPSC’s Order in this case, I am unable to conclude, as did the district court, that the GPSC in fact determined that the parties agreed to pay reciprocal compensation fees for ISP-bound traffic even though they were not required to do so under federal law. Much like BellSouth’s cryptic “petition for judicial review,” I am unable to make sense of the GPSC’s Order. On one hand, it claims that the parties “agreed” to deem ISP-bound traffic “local,” in addition to pointing to factors such as usage of trade and course of dealing. The latter are state law interpretative tools used to shed light on the parties’ intent at the time of contracting. See Restatement (Second) of Contracts §§ 219-22 (1981); U.C.C. § 1-205 (1977). Therefore, BellSouth’s position that the GPSC’s holding was driven solely by the fact that it determined, as a matter of law, that such traffic is “local” is incorrect. On the other hand, there is no question that the GPSC’s erroneous assessment of federal law was a significant factor in its conclusion, occupying most of the pages in the GPSC Order. The fact issue in this case — whether the parties’ objective intent called for the payment of reciprocal compensation fees for ISP-bound traffic — was never clearly answered by the GPSC. Did the parties intend to track federal law? Or did they intend to pay each other for the termination of ISP-bound calls notwithstanding federal law? These are fact questions that must be clearly answered in the first instance by the GPSC or a court exercising original
VI. Conclusion
The crux of BellSouth’s position is that the GPSC made an error of law in its analysis of BellSouth’s “federal element” state law claim, and that the district court should have corrected the alleged error. BellSouth cites only two possible grounds for jurisdiction in this case — section 1331 and section 252(e)(6). Each of these positions suffers from a fatal flaw. The district court lacked section 1331 jurisdiction because the proceeding before the court on the “federal element” claim was an “appellate” rather than an “original” proceeding. Section 252(e)(6) is equally unavailing because that statute cabins district court appellate jurisdiction to accept-or-reject determinations that PSCs make pursuant to 47 U.S.C. § 252(e)(1).
The district qourt did, however, have supplemental jurisdiction over BellSouth’s “federal element” claim. This is because BellSouth initially brought another claim in addition to its claim for administrative review — namely, that the GPSC was federally preempted from ordering the payment of reciprocal compensation fees for ISP-bound calls. Thus, although the district court did not have jurisdiction under section 1331 to hear BellSouth’s claim for administrative review, it had supplemental jurisdiction over that claim (notwithstanding its appellate nature) because the court had original jurisdiction over the preemption claim.
Even though the district court had supplemental jurisdiction over the “federal element” claim, it is unclear what, precisely, the GPSC held with regard to that claim. I would therefore vacate the decision by the district court and remand the case to the district court with instructions to remand to the GPSC.
. These include: the duty to negotiate interconnection agreements in good faith; the obligation to interconnect with competitors; the obligation to provide competitors with unbundled access to its network elements (“UNEs”) at reasonable rates; the duty to offer for resale at wholesale rates any telecommunications service that the ILEC provides at retail; and the duty to allow collocation of the CLECs' equipment on the ILEC’s premises. See 47 U.S.C. § 251(c).
. Section 252(a)(1) states:
Upon receiving a request for interconnection, services, or network elements pursuant to section 251 of this title, an ... [ILEC] may negotiate and enter into a binding agreement with the requesting ... [CLEC] without regard to the standards set forth in subsections (b) and (c) of section 251 of this title. The agreement shall include a detailed schedule of itemized charges for interconnection and each service or network element included in the agreement. The agreement, including any interconnection agreement negotiated before February 8, 1996, shall be submitted to the State commission under subsection (e) of this section.
. Section 252(e)(1) states:
Any interconnection agreement adopted by negotiation or arbitration shall be submitted for approval to the State commission. A State commission to which an agreement is submitted shall approve or reject the agreement, with written findings as to any deficiencies.
. The 1996 Act refers only to “state commissions.” “PSC” and "state commission” are used interchangeably throughout this opinion.
. Section 252(e)(6) states in pertinent part:
In any case in which a State commission makes a determination under this section, any party aggrieved by such determination may bring an action in an appropriate Federal district court to determine whether the agreement or statement meets the requirements of section 251 of this title and this section.
. The FCC’s initial decision was vacated by the D.C. Circuit. See Implementation of the Local Competition Provisions in the Tele-comm. Act of 1996; Intercarrier Compensation for ISP-Bound. Traffic, 14 F.C.C.R. 3689,
. As will be discussed in part V infra, it is unclear whether the GPSC took one of two positions. Did it hold that the parties intended to compensate each other for the termination of ISP-bound calls because it believed la) the parties intended to track federal law and (b) federal law defines ISP-bound calls as "local” rather than "interstate” (which would have been an erroneous understanding of federal law)? Or did it believe that the parties contracted to compensate each other for the termination of ISP-bound calls notwithstanding how federal regulations might define ISP-bound traffic?
.As the district court framed the issues: "The heart of the present disputes involve two questions: First, did the PSC orders violate federal law, as reflected in the 1996 Act and in the FCC’s rules and regulations? Second, did the PSC correctly interpret the interconnection agreement under Georgia law?” BellSouth Telecomms., Inc. v. MCI Metro Access Transmission Servs., Inc.,
. The Supreme Court did not hold that federal jurisdiction exists to review all PSC interpretation/enforcement decisions pursuant to 28 U.S.C. § 1331. The only place section 1331 was implicated in Verizon was with regard to the federal question — namely, whether a PSC conclusion that the CLECs and the ILEC had agreed to deem ISP-bound calls "local” is preempted by federal law. The Court never said that a PSC adjudication of an interconnection agreement inherently entails a federal question. In his concurrence, Justice Souter made clear that the Court was not deciding what the majority of this court claims it decided: "Whether the interpretation of a reciprocal compensation provision in a privately negotiated interconnection agreement presents a federal issue is a different question which neither the Court nor I address at the present.” Verizon,
. In asserting jurisdiction over the supplemental claim, the the district court should have sat as if it were a Georgia superior court, reviewing the GPSC’s decision under the standard of review provided by Georgia law.
. I ultimately conclude that there is jurisdiction over this state law cause of action under the supplemental jurisdiction statute, 28 U.S.C. § 1367, in part IV, infra.
. The majority of this court, like the Verizon concurrence, evidently believes that 28 U.S.C. § 1331 encompasses appellate jurisdiction. This is the only conclusion one can reach from the majority’s holding that "[T]he federal district court had jurisdiction under 28 U.S.C. § 1331 to review that decision on appeal." As the Verizon majority noted, however, “28 U.S.C. § 1331 is a grant of original jurisdiction, and does not authorize district courts to exercise appellate jurisdiction over state-court judgments.” Verizon,
. This is an unattractive option not only because it violates the plain language of 28 U.S.C. § 1331, but also because the Verizon majority expressly asserted that "28 U.S.C. § 1331 is a grant of original jurisdiction, and does not authorize district courts to exercise appellate jurisdiction over state-court judgments.” Verizon,
. As will be discussed, Justice Souter could easily have endorsed the notion that the claim in Verizon entailed a claim of original jurisdiction, whereas judicial review by district courts of accept-or-reject determinations are appellate in nature. Since he believed that Verizon entailed an appellate proceeding, he must certainly believe that district court review of an accept-or-reject determination is an appellate proceeding.
. See, e.g., Southwestern Bell Tel. Co. v. Apple,
. This is a debatable proposition — both in terms of what the parties intended and what the GPSC actually held.
. Both parties in this case are, for various reasons, eager to assert federal jurisdiction. I note that it is incumbent upon the federal courts to assess their own jurisdiction, even if it does so without the benefit of an adversarial presentation. If the parties do not raise the question of lack of jurisdiction, it is the duty of the federal court to determine the matter sua sponte. See Atlas Life Ins. Co. v. W.I. Southern Inc.,
. For example, the 2001 GPSC Chairman, Lauren "Bubba” McDonald, Jr., does not have a law degree and was in the hardware business prior to his appointment to the Commission. In addition to his commission duties, McDonald is currently involved in the funeral home business. See Commissioner Biographies, at http://www.psc.state.ga.us/pscinfo/bios/htm (last visited Nov. 6, 2002).
. The provision states: "This Act and the amendments made by this Act shall not be construed to modify, impair, or supersede Federal, State, or local law unless expressly so provided in such Act or amendments.”
. See 47 U.S.C. § 252(e)(5) ("Commission to act if State will not act").
. See infra part III.B.3.
. I agree with the Fourth Circuit on this point. See Bell Atl. Md. Inc. v. MCI World-Com, Inc.,
. Professors Benjamin, Lichtman, and She-lanski write:
From its creation in 1934, the FCC has always shared jurisdiction over telephony*1299 with state regulators. The 1934 Act's limitation of federal authority is clearly stated, if not so easily implemented in practice: the Act is not to be construed "to give the Commission jurisdiction with respect to ... practices, services, facilities, or regulations for or in connection with intrastate communication service by wire or radio of any carrier.” 47 U.S.C. § 152(b) (emphasis added). Indeed, the 1934 Act on its face restricts FCC jurisdiction to “interstate and foreign communication by wire or radio.” 47 U.S.C. § 152(a) (emphasis added). The Act thus appears to keep the Commission out of the business of regulating what, in 1934, accounted for the vast bulk of telephone usage: local telephony.
Benjamin et al., supra, at 610-11.
. Section 253 states that "[n]o State or local statute or regulation, or other State or local legal requirement, may prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate telecommunications service.” This provision put an end to state-sanctioned monopolies, demonstrating Congress's new confidence that local competition would not lead to wasteful duplication of resources, but rather to more consumer choice and lower rates.
. Section 252(e)(6) reads: "[A]ny party aggrieved by such determination may bring an action in an appropriate Federal district court to determine whether the agreement or statement meets the requirements of section 251 of this title and this section.” The two italicized portions have been removed in the quote found in the text for the sake of clarity. The "statement” referred to concerns a Bell Operating Company’s option to file a "Statement of Generally Available Terms” pursuant to section 252(f). This is not relevant to the voluntary interconnection agreement setting. Similarly, "section 251 of [title 47]” is irrelevant to the voluntary agreement context, except for the section 251(a) discussion of the "general duties” of LECs.
. Such findings are important for judicial review of the PSC's decision to approve or reject an interconnection agreement.
. The provision provides in part: "No State court shall have jurisdiction to review the action of a State commission in approving or rejecting an agreement under this section.” 47 U.S.C. § 252(e)(4) (emphasis added). This is the flip side of section 252(e)(6), which gives federal courts the power of judicial review over the PSC’s approve-or-reject determination. Together, the provisions make that power exclusive. The italicized language confirms what should be obvious from the statute: the only affirmative duty of a state PSC under section 252(e)(1) is to approve or reject an agreement and nothing more. Indeed, there is no operative clause prescribing any duty under "this section” besides the duty prescribed in section 252(e)(1) to approve or reject an agreement. The PSC's determination to approve or reject, then, is the key triggering event, and the rest of the statutory provisions relate back to that determination, filling in procedural details such as what reasons the PSC must give for its decision, what happens if the PSC chooses not to make the approve-or-reject determination at all, and how the approve-or-reject determination is appealed. Section 252(e)(6) is therefore inap-posite when it comes to defining the PSC's substantive duty, which is found only in section 252(e)(1). Indeed, section 252(e)(6) by its terms covers only "Review of State commission actions” — a procedural rather than substantive matter. One can hardly conclude, then, that because the "approve or reject” language is found in sections 252(e)(1) and 252(e)(4) but not section 252(e)(6), this somehow means that state commissions must undertake additional responsibilities besides that which is expressly enumerated in section 252(e)(1). The fact that this argument is even made shows the hollow logic of the pro-jurisdiction camp. They realize that section 252(e)(6) ties judicial review to section 252(e)(1), so they must somehow conclude that post-agreement adjudication is an affirmative duty under the latter section. Yet they also realize that section 252(e)(1) says nothing of the sort, so they strain to find an affirmative duty to engage in post-agreement adjudication outside of section 252(e)(1). They cannot have it both ways. One need not strain so mightily under a natural reading of the statute, however.
. The district court, for example, concluded that the “literal" interpretation of the statute would not confer jurisdiction. It went on to adopt the "inherent" argument (discussed below) without analysis.
. The habeas corpus setting is the only area I am aware of. The Antiterrorism and Effective Death Penalty Act of 1996 provides that relief is available only when the state court determination is "contrary to, or involved an unreasonable application of, clearly established Federal law as determined by the Supreme Court of the United States.” 28 U.S.C. § 2254(d)(1) (emphasis added).
. See supra note 18 and accompanying text.
. The now-FCC Chairman has also implied that state law typically provides the rule of decision: "[SJtate commissions have a duty to resolve interconnection disputes by relying on any legitimate bases (including state law bases), so long as those bases do not conflict with federal law.” Starpower Communications, LLC, Petition for Preemption of Jurisdiction of the Va. State Corp. Comm’n, 15 F.C.C.R. 11277, 11286,
.The district court, for example, reviewed the GPSC’s state law conclusion under an arbitrary-and-capricious standard rather than de novo. As a testament to how odd it would be for federal courts to review state entities for compliance with state law, the district court was grasping at straws to give any kind of deference that it could. After incorrectly asserting jurisdiction, I can hardly fault the district court for pulling the arbitrary-and-capricious standard out of thin air, giving only a "Cf.” citation to a Supreme Court case, United States v. Carlo Bianchi & Co.,
. In Georgia, for example, petitions for review may be filed "in the Superior Court of Fulton County or in the superior court of the county of residence of the petitioner.” Ga. Code. Ann. § 50-13 — 19(b) (2002).
. "The judicial Power shall extend to all Cases, in Law and Equity, arising under this Constitution, the Laws of the United States, and Treaties made, or which shall be made, under their Authority....” U.S. Const, art. Ill, § 2.
.Since a conclusion that federal jurisdiction exists demands a clear statement, use of the word "inherent” should be sufficient evidence that a clear statement does not exist.
. As has been discussed at length, a conclusion that PSC authority to adjudicate post-agreement disputes comes from section 252(e)(1) (rather than residual authority) would, of course, make such adjudications "determinations” under "this section” and would therefore give district courts jurisdiction to review such determinations.
. The analysis the FCC undertook — if one wishes to call it "analysis”' — comes in the form of the following statement: "These court opinions implicitly recognize that, due to its role in the approval process, a state commission is well-suited to address disputes arising from interconnection agreements.” Starpower, 15 F.C.C.R. at 11277, 116, at 11279-80. Hardly a model of legal reasoning, the FCC's observation is inapposite because it has nothing to say about the source of PSC authority; a state commission is equally "well-suited” whether or not its authority arises from residual authority or from authority that resides in section 252(e)(1). Moreover, a state legislature might think that due to its role in traditional contract adjudication and legal expertise, the state trial court is "well-suited” to address interconnection disputes. Why section 252 prevents states from making this judgment is left unexplained by the FCC decision.
.This analogy comes from commercial paper law, which prevents a forger from "laundering” a forged note through a holder in due course ("HDC”) in order to attain HDC status. For example, a forger cannot sell a note to a party without notice of the forgery and then proceed to buy the note back from the HDC so as to attain HDC status under the shelter rule.
. One of the many problems with this interpretation is that since all PSC adjudications would be made pursuant to section 252(e)(1) rather than residual authority, there is no logical basis for systematically excluding from federal review those adjudications based solely upon state law. All PSC orders would be “determinations” under "this section” and thus subject to federal review.
. This is also the conclusion the Fourth Circuit may reach on remand from the Supreme Court's Verizon decision.
.Various interpretations of 47 U.S.C. § 251 would, for example, (1) make the statutory scheme wasteful by allowing for de novo review in federal district court (if federal common law is the rule of decision) or (2) entail federal court review of state agencies on matters of state law (if state law is the rule of decision). I have also noted many other problems that section 252 jurisdiction would yield.
. The district court evidently did not understand BellSouth to be claiming that (a) the parties intended to track federal law and (b) federal law provided that ISP-bound calls are not subject to the 1996 Act's reciprocal compensation requirement. This conclusion is understandable given the cryptic “petition for judicial review” described in part II.A.3, supra.
Concurrence Opinion
concurring in part:
I concur in the judgment of the Court and in the opinion by Judge Barkett, except that I decide nothing about jurisdiction under 47 U.S.C. § 252(e)(6).
