35 Neb. 240 | Neb. | 1892
This is an action by George P. Paul against Norling & Reynolds, aspríncipals, and John T. Bell and Ed. L. Howe, as sureties, on a certain building contract bond. The trial resulted in a verdict in favor of the plaintiff below in the sum of $1,418.86. A motion for a new trial having been filed by the defendants the plaintiff filed a remittitur for $122.36, whereupon the court overruled the motion for a new trial, and rendered judgment in plaintiff’s favor for the sum assessed by the jury, less the amount of said remittitur.' The sureties bring the cause into this court for review by petition in error.
A brief statement of the facts will assist in a proper Understanding of the questions presented. On the 30th day of April, 1887, Norling & Reynolds, contractors and builders, entered into a written contract with George P. Paul, by which they agreed to furnish all materials and perform all the labor necessary to build, finish, and complete in good,'first-class and workmanlike manner, for said Paul, in the city of Omaha, to his compílete satisfaction, a frame dwelling, pilumbing and heating excepted. The material was to be furnished and the labor pierformed 'under
On the 3d day of May, 1887, the bond in suit was executed, which contained the following condition: “Now if said Norling & Reynolds furnish all material and perform all labor in connection with said building as per said plans and specifications and contract, and turn over said building free from liens for labor or materials furnished through said Norling & Reynolds, then these presents to be void,, otherwise to be of full force and effect.”
It is insisted that the contractors were prevented from completing the building by the owner taking possession thereof and excluding them therefrom; therefore the sureties were discharged from all liability on the bond. The question was fairly submitted to the jury, whether Norling & Reynolds voluntarily abandoned the work and refused to proceed with the same, or whether they were prevented from so doing without their consent, by Mr. Paul assuming the control of the building and the completion of the same, and they found that the contractors voluntarily abandoned the work. We think the testimony justified the finding. The reason they did not finish the job was because the architect declined to give an estimate on September 3,1887. The fact that one was refused furnished no valid excuse to the contractors to abandon the contract and refuse to complete the building, even had they been entitled to an estimate. Until one was furnished the owner was not obliged to pay; that is clear; nor was his failing so to do any justification for their abandonment of the job.
Counsel urge that the sureties are not liable because payments were made the contractors in violation of the terms
It is insisted that the stipulation of the contract relating to payments on estimates has reference only to payments made to the contractors. Granted; but how does that affect the defendant in error? Numerous payments were made without estimates, on orders given by the contractors on Mr. Paul. The payment of these orders by the drawee was, in effect, a payment to the contractors. Nor is it material that the orders were given and paid after it is claimed'the work was abandoned by Norling & Reynolds; that they had violated the contract did not justify the other party to disregard the provisions written therein on his part to be performed. A party who seeks to enforce a contract must not, himself, have been guilty of a breach thereof.
Objections are made to several paragraphs of the charge of the court, but one of which we will notice, and that relates to the tenth instruction, which reads as follows:
“If, under the testimony adduced upon the trial and the instructions above given you, you shall find for the plaintiff, you will assess as his damages such amount as the testimony shows he was obliged to and did expend in the
This instruction is clearly erroneous, in that it fails to state the true rule of damages. By it the jury were told to allow the plaintiff the amounts paid in liquidation of claims for labor performed and materials furnished under the contract for the construction of the building, instead of limiting the recovery to the amount paid in settlement of liens against the property. The extent of .the obligation of the sureties was that the contractors should complete the building and turn over the same to the owners “free from liens for labor or materials furnished through Norling & Reynolds.” Further than this, they did not undertake or promise.
It is admitted that only one lien was filed against the building, which was on a claim for $358.80, for brick furnished by one Thomas Murry, yet the judgment was for $1,296.50, the full penalty of the bond, with interest. It is quite immaterial that the amount paid by Mr. Paul was justly due for labor performed and materials supplied in the construction of the building. As liens therefor had not been filed, the payment was entirely voluntary. Plaintiffs in error did not obligate themselves that the contractors should pay for all labor and materials, only that the building should be delivered to the owner free from all liens. Sureties are not bound beyond the terms of their engagements.
Reversed and remanded.