Lead Opinion
Plаintiff and respondent brought an action against defendants'and appellants to recover the unpaid balance for materials furnished to one Kirkland to be used in the construction of the “Somerville sewer.” Kirkland contracted to construct the sewer, and, as principal, signed an instrument in which the appellants joined as sureties, which purported to be a bond to the city of St. Paul conditioned for the performance of the contract, and for the payment for the labor and materials furnished in its execution. The total amount of the account was $6,286.30. The balanсe unpaid was $2,967.55. The amount of the bond was $59,200. The present is a test case. The court found for the plaintiff. It found as facts, inter alia, that the course of the sewer carried it under property hereinafter more fully set forth as to which the city had acquired no right by condemnation or grant. This appeal was taken from an order denying defendants’ motion for a new trial.
Defendants’ essential argument is that, if the contract was ultra vires and void, so also was the bond, aqd that the agreement was shown to have been ultra vires and void.
In the first place, the agreement required the construction of a sewer through property not owned by the city. The sewer provided for in the contract was a main sewer of about forty two hundred feet in length. It is cut into two almost equal parts by a railroad right of way and adjoining private property for two hundred five feet. It is proposed to construct it to the Mississippi river as an outlet. In connection with the latter proposition, it is argued that a sewer is of no value unless continuous, or unless it has an outlet. It cannot reach the river because the last eighty five feet is owned by the United States government. The result was two disjointed piеces of sewer without an outlet. The significant fact is that the ultra vires part of the contract leaves the sewer valueless. A contract to construct a useless sewer in private property is beyond the power of the city. The invalidity appears upon the face of the contract.
In 9 Harv. Law Rev. 255, Mr. George Wharton Pepper combats—and we think successfully—the existence of any clear distinction between the principles of the earlier and of the present decisions or of inextricable confusion on the subject in the American reports. He
With respect to contracts by municipal corporations, one current opinion is that: The “contracts of corporations, whether public or private, stand on the same footing with contracts of natural persons, and depend on the same circumstances for their validity and effect. The doctrine of ratification and estoppel is as applicable to corporations as to individuals.” Argenti v. City of San Francisco,
The first of these describes a contract which is not within the scope of the powers of a corporation to make under any circumstánces, or for any purposes; for example: “Where a corporation authorized only to build a railroad engages in banking.” Mitchell, J., in Minnesota Thresher Mnfg. Co. v. Langdon,
The former class is ultra vires in the primar}', and really only proper use of the term, while in the second it is merely secondary. Mitchell, J., in Minnesota Thresher Mnfg. Co. v. Langdon, supra. That is to say, an ultra vires municipal contract, in its true sense, is a contract relating to matters wholly outside the charter powers of a corporation. 2 Dillon, Mun. Corp. §§ 935, 936. In Miners v. Zellerbach,
in considering a question arising out of dealings with a corporation. When an act is ultra vires in the first sense mentioned, it is generally, if not always, void in toto, and the corporation may avail itself of the plea. But, when it is ultra vires in the second sense, the right of the corporation to avail itself of the plea will depend upon the circumstances of the case.” And see City of Valparaiso v. Valpаraiso,
In the second place, the present contract is ultra vires, if at all, as to a small part only. It is convenient to postpone the consideration of irregularities in the letting of the contract, and to here refer only to the failure of the city to condemn. So far as that failure is addressed to private property, which the city could have condemned, the controversy is disposed of by the ruling in Keough v. City of St. Paul,
In the third place, the features of this contract objected to remain
In the leading case of Hitchcock v. Galveston, 96 U. S. 341,
We have referred to these considerations to make plain the restricted sense and extent of the ultra vires aspect of this contract and its executed character, as well as the trend of judicial position concerning the legal position of plaintiff’s contract. The facts that as to a small portion of a contract with a municipality only it was ultra vires in any sense, and that it has been substantially executed by the parties basing rights of ,action upon it, are strong, if not conclusive, considerations for refusing to hold it absolutely void. It is, however, unnecessaiy, and because of the course the argument has taken in this court, undesirable, to determine whether the contract was valid in the sense that the contractor could have recovered on it from the city.
In a suit against the bondsmen of the contractor, it is difficult to discover what considerations of public policy would tend to favor the forfeiture of this plaintiff’s right. Without controversy, “all persons contracting with a municipal corporation must, at their peril, inquire into the power of the corporation or its officers to make the contract.” State v. Minn. Transfer Ry. Co.,
There is good authority to the effect that where the act of a corporation is done with power to do it, but without the formality presсribed for the execution of the power, persons dealing with the company are not bound to do more than to ascertain that the power to do the proposed act exists. 5 Thompson, Corp. 5978; 2 Morawetz, Priv. Corp. §§ 678, 686. Allen, J., in Moore v. Mayor,
The policy of the law — and apparently the law itself — oppose the adoption of defendants’ views. Nor does the admitted principle that the defendants, as sureties, are entitled to the strict construction of the facts giving rise to an action against them, and are generally favored in the law, affect the doctrine of ultra vires. As a matter of abstract justice, the sureties to whom a consideration of legal sufficiency has moved, although it does not appear that substantial benefits have accrued to them, have held themselves out as responsible for the validity of the contract to persons having the right to rely upon the security that bond is expressly designed to afford. Moreover, “Volente non fit injuria.” Red Wing Sewer Pipe Co. v. Donnelly, supra, page 192,
The most nearly specific authority which has been called to our attention, or which we have been able to find, is City v. American,
Our attention has, however, been directed to Conant v. Newton,
7. In view of the clear tendency of the courts to avoid injustice from the application of the,doctrine of ultra vires, of the restricted sense in which in any aspect this contract may be regarded as of that character, of the absence of reason for destroying the contract because only part was not direсtly within the power of the city, of the extent to which it has been executed, and of the peculiar position of the bondsmen defending against a materialman who in good faith sold material for the benefit of the contractor, in reliance on a bond on which he had a right to rely, and which recited the contract as valid and subsisting, we are clearly of the opinion that the conclusion of the trial court on this point was correct.
Incidentally defendants have argued that, when plaintiff furnished the material for the construction of the sewer, it is not shown where
Order affirmed.
Concurrence Opinion
(concurring).
The sureties cannot be heard to assert that this contract is ultra vires. A municipal corporation with charter power to construct sewers irregularly entered into a contract for the construction of a particular sewer which was to extend in part through land over which the corporation had acquired no right by grant or condemnation. The contractor executed a bond with the required sureties, conditioned upon the faithful performance of the contract with the city and the payment of the lawful claims for labor and materal used in the work. This bond recited that the principal had entered into a contract with the city, and that the contract had been duly executed by each of the contracting parties. By executing this bond the sureties acknowledged that the contract was valid and the bond authorized. I think it is settled that a guaranty of payment of an obligation or the performance of an undertaking imports an agreement that the instrument is valid and the undertaking legal.
If the sureties on the bond can defeat the claims of laborers and materialmen, because of irregularities in the making of the contract referred to in the bond, it follows that every man who contemplates selling a foot of pipe to a contractor, and every laborer, before commencing work with his shovel, must employ counsel learned in the .law to ascertain whether the corporation counsel has properly performed his duties and verify the formal statement of the sureties that a contract exists between the city and the contractor.
This burden rests upon the sureties, and they are bound by the recitals in the bond. I would place the decision upon this ground.
