MEMORANDUM OPINION
In connection with the issuance of subcontractor performance or payment bonds, sureties typically require subcontractors to agree, by contract, that in the event the bond is triggered by the subcontractor’s breach of its contract with the prime contractor, the subcontractor will (1) indemnify the surety and (2) assign to the surety the authority to settle any claims brought by the prime contractor against the subcontractor. Also typical is a provision in the indemnity agreement between the subcontractor and the surety that, in the event of a breach of that agreement, all rights in and to the bonded obligation are assigned to the surety and the surety becomes the subcontractor’s attorney-in-fact in that regard.
This case presents the question, not yet specifically resolved in Virginia, whether
I. 1
Plaintiff Bell BCI Company (“Bell”) is a Maryland corporation engaged in the construction contracting business and duly authorized to transact business in Virginia. On August 18, 1999, Bell entered into a contract (“Contract 4”) with the Alexandria Sanitation Authority (“the Authority”) for the general construction of the Alexandria Wastewater Treatment Facility, Nitrogen Compliance Facility, Contract #4. On March 20, 2002, Bell entered into a second contract (“Contract 6”) with the Authority for the general construction of the Advanced Wastewater Treatment Facility Upgrade — Package D, Contract # 6. Bell subsequently entered into two subcontracts with defendant Old Dominion Demolition Corporation (“ODDC”), a Virginia corporation, under which ODDC was to perform demolition, disposal, dewatering, excavation, backfill and site preparation work required under Bell’s corresponding general contracts with the Authority. Subcontract 6 was entered into on April 29, 2002, while Subcontract 4 was entered into on May 15, 2002.
Defendant Developers Surety and Indemnity Company (“the Surety”), an Iowa corporation, issued performance and payment bonds on behalf of ODDC, as principal, under which it guaranteed ODDC’s performance under Subcontracts 4 and 6, as well as payment by ODDC to its subcontractors and suppliers on the bonded projects. In addition, on May 15, 2002, defendant American Reinsurance Company (“AmRe”), a Delaware corporation, executed a Sitework Reinsurance Agreement under which it counter-secured the Surety’s obligations under the performance bond issued in connection with Subcontract 6.
In partial consideration for issuance of the bonds on ODDC’s behalf, ODDC executed an Indemnity Agreement in favor of the Surety.
2
Under the terms of the Indemnity Agreement, ODDC agreed,
inter alia,
to “indemnify and hold harmless Surety from and against all liability, loss, claims, demands, costs, damages, attorneys’ fees and expenses of whatever kind or nature” incurred by the Surety as a result of issuing bonds on behalf of ODDC. In addition, ODDC agreed to deposit with the Surety, upon demand, collateral in the amount equal to any reserve set by the Surety. Importantly, under paragraph 2.1 of the Indemnity Agreement, ODDC assigned the Surety “the right in its sole and absolute discretion to determine whether any claims under a Bond shall be paid, compromised, defended, prosecuted or appealed.” Additionally, in the event of a breach of the Indemnity Agreement by ODDC, paragraph 7 of that Agreement operates to assign to the Surety all of ODDC’s rights in and to the Subcontracts between ODDC and Bell. Under paragraph 12, ODDC also designates the Surety “as its attorney-in-fact with the right and power, but not the obligation, to exer
ODDC did not ultimately complete performance of its work under Subcontracts 4 and 6. According to ODDC, Bell was more than six months late in releasing some areas of the work site to ODDC and then required that ODDC complete the work on an unreasonably expedited schedule. When ODDC declined to adhere to this schedule, Bell declared a breach and terminated ODDC’s subcontracts. While Bell and ODDC dispute which of them was the first to breach, the undisputed record reflects that ODDC, contrary to its obligations under the Indemnity Agreement, had failed to pay some of its subcontractors and suppliers.
Indeed, it is undisputed that the Surety received payment bond claims from ODDC’s subcontractors and suppliers on the bonded projects in excess of $485,000. The Surety also received payment claims on two other projects bonded for ODDC. Currently, the record reflects that the Surety has paid $411,498.75 in resolving some of those claims and anticipates that it may be obligated to pay some or all of the remaining payment claims. Pursuant to paragraph 5.3 of the Indemnity Agreement, a failure on the part of ODDC “to pay for labor and materials ordered for or used in connection with” a bonded Obligation — here the Subcontracts — relating to development of real property or construction of improvements upon real property constitutes a default under the Indemnity Agreement. There is no dispute that the Subcontracts between Bell and ODDC relate to development of real property or construction of improvements upon real property.
On April 16, 2003, Bell filed suit against ODDC, the Surety, and AmRe, alleging that ODDC breached its Subcontracts by failing to perform the work required under the Subcontracts. Specifically, Bell alleged that ODDC failed to perform its work under the Subcontracts in a proper and timely manner and that ODDC had failed to give timely written notice of alleged claims against Bell in breach of its obligations under the Subcontracts. In addition to seeking contract damages from ODDC, Bell also sought recovery from the Surety and AmRe under the performance bonds and Sitework Reinsurance Agreement. In response, ODDC denied any breach of the Subcontracts and asserted a counterclaim against Bell, contending that Bell had breached its obligations under the Subcontracts to ODDC by unreasonably delaying the release of work areas under Subcontract 4 for more than six months and directing that work be completed on an unreasonably accelerated schedule, and by improperly terminating the Subcontracts. Additionally, ODDC alleged that Bell owed ODDC money for work performed under the Subcontracts, and that Bell’s retainage of ten percent of ODDC’s subcontract progress payments was a violation of certain Virginia statutes. See Va.Code § 2.2-4333 (limiting retainage to five percent of progress payments for public construction contracts); Va.Code § 2.2-4354 (listing payment clauses to be included in any contracts awarded by a state or local government agency).
As often occurs in these construction project disputes, the prime contractor has settled with the Surety, but not with the subcontractor. Specifically, the Surety and AmRe reached a settlement agreement with Bell under which the Surety agreed to pay Bell $275,000 in full settlement of this action, including a release of all claims against the Surety and AmRe and the claims and counterclaim between Bell and ODDC. Bell, the Surety, AmRe, and the Surety on behalf of ODDC, further agreed to endorse and submit to the court a Proposed Order pursuant to Rule 41(b),
In this action, Bell’s claims against the Surety total approximately $875,000, exclusive of attorneys’ fees and costs. ODDC contends that its counterclaim against Bell is worth, at a minimum, $576,808.51. Prior to settlement, ODDC informed the Surety that it was insolvent and, accordingly the Surety was anticipating additional liability on the bonds it issued for ODDC. Additionally, the Surety made demand under the Indemnity Agreement for ODDC to indemnify it from the various performance and payment claims against the Bonds and demanded deposit of the required collateral security in the amount of the Surety’s reserves pursuant to paragraph 3 of the Indemnity Agreement.' The Surety also requestéd an explanation of how ODDC intended to reimburse it for the losses it had already incurred on the bonds. It appears that ODDC did not respond to these demands. Further, it appears that the Surety’s settlement of the action was formally reached after ’these demands were made.
The Surety now moves to enforce the settlement reached between Bell, the Surety, AmRe, and the Surety on ODDC’s behalf apd to dismiss ODDO’s counterclaim. 4 . .
II.
There is no dispute that Virginia law governs the interpretation of the Indemnity Agreement. This result follows from the rule in
Klaxon Co. v. Stentor Elec. Mfg. Co.,
Notwithstanding the clarity of the contract language requiring this result, ODDC raises several objections to the settlement of its counterclaim against Bell. Specifically, ODDC contends that its counterclaim against Bell is meritorious because Bell, not ODDC, was the first to breach the Subcontracts and, as a result, ODDC suffered very substantial damages. ODDC further claims that the Surety’s agreement to give up this valuable counterclaim simply to limit its bond liability to Bell reflects the Surety’s bad faith, which should serve to bar the Surety’s settlement of the counterclaim. ODDC, moreover, contends that because the Subcontracts require Bell’s written approval for all assignments and because no such writing exists, no assignment of the Subcontracts occurred and hence the Surety had no authority to settle ODDC’s counterclaim. These arguments, separately addressed here, are unpersuasive.
ODDC first argues that since paragraph 8 of Subcontracts 4 and 6 does not allow ODDC to “assign the whole or any part of Work or this Agreement without [the] prior written approval of Bell,” the Surety could not settle the counterclaim with Bell because the assignment of the Subcontracts to the Surety was invalid, as Bell did not give any such prior approval. The obvious and fatal flaw in this argument is that only Bell, not ODDC, has standing to object to the absence of a writing reflecting Bell’s approval of the assignment. And, it is equally obvious that Bell does not wish to object to the assignment on this basis and indeed, to the contrary, supports the assignment and effectively waives the written consent requirement. In other words, the Subcontracts’ requirement of prior written approval by Bell to any assignment is of no avail to ODDC and is no bar to the assignment of the Subcontracts to the Surety pursuant to the Indemnity Agreement. This result is simply a reflection of the well-established contract principle that “[a] contract term prohibiting assignment of rights under the contract, unless a dif
ODDC’s reliance on
Burck v. Taylor,
Burck’s facts are quite different from those presented here. In contrast to the obligor in Burck, Bell was at all times aware of the Surety; indeed the Subcontracts themselves required ODDC to furnish Bell performance and payment bonds through an. acceptable surety. Moreover, through the settlement, Bell effectively waived its right to challenge the assignment of the Subcontracts to the Surety. 7 Indeed, the terms of the settlement make clear that Bell supports the Surety’s efforts to enforce and give effect to the settlement. It is clear, therefore, that Bell does not object in any way to the assigm ment, and that the anti-assignment provisions in the Subcontracts are for Bell’s benefit and protection. As a result, these anti-assignment provisions do not render the assignment of the Subcontracts to the Surety, by operation of the Indemnity Agreement, invalid.
Next, ODDC argues that notwithstanding the fact that, by its terms, the
Finally, ODDC argues that the settlement agreement should not be enforced because the Surety did not settle its counterclaim in good faith. In support of this argument, ODDC contends that it was owed a minimum of $576,808.51 for work performed at the time of Bell’s termination of the Subcontracts and that these unpaid monies were included in ODDC’s counterclaim against Bell. As a result, ODDC argues that the settlement, by allowing Bell to keep the monies owed to ODDC by dismissing the counterclaim and requiring a payment to Bell of $275,000, is the equivalent of paying Bell $851,808, a sum ODDC contends is slightly higher than Bell’s specified damages. Consequently, ODDC argues that the Surety paid Bell an “unquestionably unreasonable sum of money.”
This argument assumes, of course, that ODDC would unquestionably prevail on its counterclaim, an assumption that appears unwarranted.
8
More importantly,
III.
In summary, therefore, defendant Surety’s Motion to Enforce Settlement and to Dismiss Affirmative Claims of ODDC must be granted.
An appropriate order has issued.
Notes
. Facts relating to Bell's claims against ODDC and ODDC’s counterclaim against Bell are taken from Bell’s complaint and ODDC's counterclaim. Facts relating to the Indemnity Agreement and the settlement in this case are taken from the Surety’s Memorandum in Support of its Motion to Enforce Settlement and to Dismiss Affirmative Claims of ODDC and ODDC's Memorandum in Opposition to the Surety’s Motion.
. The Indemnity Agreement was also executed in favor of the Surety with respect to bonds issued for ODDC on contracts other than Subcontracts 4 and 6 and hence applies to those other contracts as well.
. Indeed, the settlement agreement provides that in the event the Surety's motion to enforce the settlement is denied and ODDC is permitted to pursue its counterclaim against Bell, the Surety will defend Bell and hold it harmless from this counterclaim. Should this occur, Bell is required to tender its defense of the counterclaim to the Surety and cooperate fully in the defense of Bell against ODDC’s counterclaim.
. Although the Surety’s motion to enforce the settlement effectively seeks a declaratory judgment concerning the parties' rights under the Indemnity Agreement and the Subcontracts, no party has suggested that this is not the appropriate procedural vehicle, and at least one other court has found that a motion to enforce settlement is the appropriate procedural vehicle.
See Hutton Constr. Co. v. County of Rockland,
.See also Fox-Greenwald Sheet Metal Co. v. Markowitz Bros., Inc.,
.
See Fox-Greenwald Sheet Metal Co.,
. To dispel any possible ambiguity on the subject of waiver, Bell, by counsel, expressly waived its right to challenge the assignment of the Subcontracts to the Surety at the hearing in this matter.
. Although, denied as moot in light of the resolution of the Surety's motion to enforce settlement and dismiss affirmative claims of ODDC, Bell had filed a motion for summary judgment, or alternatively partial summary judgment, in this case. In support of this motion, Bell persuasively argued, inter alia, that ODDC was the first to breach the Subcontracts and that any subsequent breach by Bell would trigger paragraph 14 of the Subcontracts, exclusively limiting Bell's liability to "reimbursement for reasonable direct expenditures and costs for materials and equipment incurred prior to termination.” Additionally, Bell's motion persuasively puts in doubt the likelihood of ODDC’s prevailing on its counterclaim.
. Moreover, although the matter is not decided, if there is any bad faith in the Surety's settlement of ODDC's counterclaim, it is certainly not obvious from the record in this case.
