271 F. 144 | 6th Cir. | 1921
(after stating the facts as above). The record is full of informalities. No effective notice of the proceedings was ever given to the contractor. We might well dispose of the appeal for this or similar reasons; but the underlying merits of the matter have been so fully presented and argued by counsel for the parties
Mechanic’s lien statutes evidence a general recognition of the thought that those who contribute the labor and material going into a structure should have a claim against it for what they have furnished in preference to other creditors of the builder, though the equitable distinction, between those materialmen who are unpaid to-day and the banker who furnished the money which was used to pay those who furnished material yesterday, seems rather arbitrary. It is commonly held that this lien or priority is wholly statutory, and we are not aware of any case (unless those hereafter discussed) where, without the aid of any contract or statute, this vague equity of materialmen and laborers has been thought sufficient to put the owner of the property under obligation to see that they were paid before he settled with the contractor.
It seems, however, that the desire to see this class of claims given some preference was sufficient, so that the United States had some-works that it should have the right to withhold payments in case the times thought proper to provide expressly in a contract for public
It is not necessary to consider which of these views would seem the better one, if the question were open. We think it has been foreclosed by the decision of the Supreme Court in Henningsen v. U. S., 208 U. S. 404, 28 Sup. Ct. 389, 52 L. Ed. 547. In that case, the surety upon a bond of this kind, given pursuant to the 1894 statute, and who had been compelled to pay its surety obligation, was held entitled to'priority in the retained fund as against a general creditor of the contractor. The case was essentially different from the Prairie State Bank Case, because there the surety had taken over and completed the contract and the performance of the contractor’s obligation to the United States as the other party to the contract, and so had become entitled to the security which the United States held against the contractor; in the Henningsen Case, the contractor himself had completely performed the contract and had finished the work. • It would seem, therefore, that subrogation in the Henningsen Case could not be to any security which the United States held against the contractor; there was no such element in the case. The surety’s claim of priority in the fund was sustained, and this was done on the stated theory of subrogation. Since there cannot be the transfer of a right by subrogation, unless there is
If this is the true principle of the decision, it may not be clear what the rights of the parties would be in the various situations that might arise, e. g., as between a surety who had performed the contract and claimants of this class unpaid when the surety took it over, or as between a surety who had paid claims of this class to the limit of his bond and the unpaid remainder of the same class; but those questions can be met when they arise. The same result was reached in Re McGarry (C. C. A. 7) 240 Fed. 400, 153 C. C. A. 326, and in Cox v. New England Co. (C. C. A. 8) 247 Fed. 955, 160 C. C. A. 655. The opinions in these cases do not decide the controlling question—what the right of the laborers and materialmen in the fund is—but they assume that it is decided in the Henningsen Case. In Re Schofield (C. C. A. 2) 215 Fed. 45, 48-50, 131 C. C. A. 353, the precise question is discussed, but seems to be left undecided. The" Court follows the Henningsen Case, but assumes that it was the same in principle as in the Prairie State Bank Case, not observing what, with all deference, we think the essential distinction already pointed out. When the surety in the latter case stepped in, the United States was the obligee in an unperformed contract, holding security for its performance, and the surety was subrogated. When Henningsen’s surety paid up, the United States, the secured creditor, had been satisfied, and had no further claim on the fund, unless it bore the duty to devote the fund to the labor and material claimants; hence the latter proposition must be considered as affirmed. Obviously, the retained fund is devoted to the payment for such labor and material as may be necessary to finish the work after the contractor defaults. Whether it is devoted to pay the contractor’s debts of that class is a distinct question, and the cited cases suggest to us some confusion of thought on this subject.
In reaching the conclusion to which the Henningsen Case leads us —that the statute leaves unimpaired an existing obligation by the United States to protect such claimants—we get no help from the fact that the bond which is executed runs to the United States as the nominal obligee. The provisions of the act of 1894 as to bringing suits
“9. The contractor shall be responsible for and pay all liabilities incurred in the prosecution of the work for labor and materialand
“12. Payments shall be made to the contractor as prescribed in paragraph 20 of the specifications hereto attached and forming part of this agreement.”
The introductory part of the contract says that it is “in conformity with the advertisement and specifications hereto attached which form a part of this contract.” In the copies filed as exhibits with the bill, the advertisement and specifications were not included. Appellant produced at the hearing a copy of such advertisement and specifications, certified by the War Department, and asked that it also be in-' eluded in the record. We do not clearly see how we can thus bring in a paper which was never presented to the court below, but, as its authenticity does not seem to be questioned, and in order that we might not overlook something inconsistent with the result which we have reached, we have examined this additional paper. We find nothing in it which, as it seems to us, could be thought to bear on the question, save the part which is copied in the margin.
The Hermingsen Case was decided under the statute of 1894, and substantial changes were made in 1905, but they <lo not affect the principle of that case. The chief change is to give, the United States priority in the full satisfaction of all its claims under the bond, for completion of the contract or for delay, before the labor and material claimants get their protection. This indicates a less tender care for the interests of such claimants, but we do not see that it affects the question of the underlying obligation of the government to give this protection, in so far as it can be given consistently with the government’s priority.
We therefore conclude that the labor and material claimants are entitled to priority in the distribution of the fund in the receiver’s bands, as against other creditors. Our order will be that the decree be reversed, with costs, and that the case he remanded, in order that the claimants may recast their pleadings, so as to he in form either an intervention in the receivership case, or an independent bill expressly ancillary to that case, as they may be advised, and that thereafter further proceedings be had in accordance with this opinion.
“20. Payments. When funds are available, payments will be made monthly on estimates of work accepted. Ten per cent, will be reserved from each payment until the amount so reserved shall equal $75,000. Upon completion and acceptance of the entire work, all reserved payments will be paid to the contractor. Should payments be discontinued for a period of one year, owing to a lack of funds, one-half of the reserved percentage will be paid to the contractor, it being understood that such payment shall in no manner release the contractor from his obligations under this contract, and that the contract and the accompanying bond shall remain in full force and effect the same as if such reserved percentage had not been paid. When work is resumed, 10 per cent, will be deducted from each monthly payment as before until the total amount reserved again equals $75,000.”