167 F. 486 | 6th Cir. | 1909
The Brackett Bridge Company, an Ohio corporation doing business at Glendale, Ohio, was adjudged bankrupt July 3, 1906. The AVestern German Bank claimed and was allowed preferential liens, under alleged equitable assignments from the bridge company, of payments to be made under construction contracts made by the bridge company with various parties, as well as upon a quantity of structural iron pledged by the bridge company to the bank. The case is brought to this court under both the appellate and revisory authority conferred by the bankrupt act. The fact that both remedies are invoked makes it unnecessary to consider which is, under the circumstances, the proper remedy, a subject which will be found discussed in various decisions of this court, from Cunningham v. German Ins. Bank, 103 Fed. 932, 935, 43 C. C. A. 377, to In re Doran, 154 Fed. 467, 468, 83 C. C. A. 265. No attack is here made upon the validity of the indebtedness claimed to be secured by the liens in question. The assault is made upon the validity of the assignments of the payments made under construction contracts, as well as of the pledge of the structural iron. The grounds of this assault will appear as the opinion progresses.
1. The first asserted ground of invalidity of the assignments and pledge is that they' were not authorized by the board of directors. It is not alleged that the giving of these securities was beyond the authority of the corporation. On the other hand, it is expressly conceded in the briefs of counsel for the trustee that the corporation had the power to give the security. The notes containing the collateral assignments were signed on behalf of the bridge company by F. J. P. Brackett, president, and George A. Brackett, secretary, at least two of the notes being signed also by the members of the advisory committee hereafter referred to. The first of the assignments was made April 6, 1904. Others, either originals or renewals, were given from time to time until shortly before the bankruptcy. The president owned a very large majority of the common stock of the corporation, and was the practical bridge manufacturer and the general manager of the corporation. For several years before the bankruptcy, including the entire period covered by the securities in question, the president had been allowed practical charge of all the financial business of the company, including the borrowing of money, except that in 1903 the board of directors, by resolution, created a so-called advisory board “for the purpose of considering and passing on all contracts aggregating $5,000.00 or more and such other business of the company as might come before it.” This board consisted of the president and two other members. There was but one director in addition to these three and the secretary.
The method of raising money upon the securities was this: When the bridge company had a contract for the carrying out of which money was needed, it presented to the hank with its application for loan an assignment of the payments to be made under the contract. The money was loaned upon the strength of the assignment, passed to the credit of the bridge company, and by it checked out in the regirlar and lawful transaction of its business and for its direct benefit. The testimony is express and uncontradicted that the members of the
2. The validity of the assignments of the payments under the construction contracts is assailed as being void as to creditors represented by the trustee: first, as being secret and unknown to other creditors of the bankrupt; ' second,. for the reason that the assignor (the bridge company) retained.(as alleged) full dominion and control over the assigned claims; third, that the alleged assignments are mere promises to pay out of the moneys obtained under the construction contracts; fourth, that-no notice of the fact of the assignment was given to the debtors under the assigned contracts; and, fifth, that, if the assignments are valid at all, they are so valid only to the extent of the particular payments specified, and that such specified and assigned payments had been before the bankruptcy collected by the bridge company, leaving nothing for the assignment to operate upon.
The facts necessary to an understanding of these objections are these: As'security for the payment of each loan, the bridge company gave a note reciting the assignment as security, together with a. separate instrument of assignment. The forms used in each case were
"Having deposited or pledged as collateral security for tlie payment of tills note. No. 1709. Hamilton county, Ohio, for $119,500.00 for the construction of Elizabethtown bridge”
—this clause being followed by a power of sale; the assignment being in this language:
“In consideration of $15,000.00 loan made to us this day by the Western Gorman Bank, Cincinnati, Ohio, for four months, we hereby transfer to them our claim as follows — in course of construction at our factory or in the course of erection, contract No. 1769, Hamilton county, Ohio, $118,500.00; said loan to be paid out of the first money received on said claim and as recen ed, except the first estimate.”
The exception above noted is that in each of the other assignments the words “except the first estimate” are omitted. In the case of each loan the assignment was entered in full upon the hooks of the bridge company, and, in advance of the payment over of the money, was given to the bank with a notarial certificate attached that “the above is a true and correct copy of the entry as made this day on the books of the Brackett Bridge Company, Cincinnati, Ohio.” This assignment was not filed or recorded in any public office. The bank did not keep the assignments “secret,” except in the sense that they were not made public. The bridge company retained possession of the contract, and payments were made directly to it, the debtors under the construction contracts not being notified of the assignment. The bank had obviously the power to make the collections itself, had it desired to do so. The bridge company was under obligation to turn over to the bank all payments made as fast as collected. The bank expected that such course would be taken. In fact, the greater part of the payments made up to the time of the bankruptcy had been retained by the bridge company, and used in the regular transaction of its business. _ Targe amounts, however, still remained unpaid upon the contracts in question, and it is upon these unpaid amounts that the lien of the bank was claimed and allowed. The trustee represents only general creditors, none claiming preferential liens, and none having fastened or attempted to fasten upon the property in question by attachment or other special proceeding. The actior of the bank in making the loans, and in its treatment of the security, is shown to have been in good faith and with the design only of protecting its own interests in connection with the loans.
It should be noted that no question of preference under the bankrupt act is involved, it being conceded that all the preferences claimed were made more than four months before bankruptcy intervened. The subject of the validity of ati assignment of the nature of those in question here is not in Ohio regulated by statute, and we are cited to no decisions of the courts of that state declaring an assignment of this nature invalid as between the original parties thereto. The validity of the assignments must therefore depend upon equitable principles applicable to the general law. It may be said, in passing, that
The assignments in question are not mere promises to pay money. They are assignments of “our claim,” and relate to the moneys to be earned by the assignor through the performance of the contract. An assignment of future earnings from personal employment is valid (Rodijkeit v. Andrews, 74 Ohio St. 104, 77 N. E. 747), and, notwithstanding the assignment was of a part only of the moneys to he earned. In Union Trust Co. v. Bulkeley, supra, the assignment which was held valid was of accounts and bills receivable to be thereafter acquired. There is no reason for asserting a different rule as against the assignments of moneys to be earned under a construction contract.
It is not necessary to the validity of the assignments as against the assignor that those liable to pay the claims assigned be notified of the assignment. Thayer v. Daniels, 113 Mass. 139 ; Marsh v. Carney, 69 N. H. 236, 45 Atl. 745; Copeland v. Manton, 22 Ohio St. 404. No question of lack of notice is raised by the debtors, nor have they been prejudiced by the assertion of rights of other claimants to the fund. The contest is entirely between the assignee and the one standing in the shoes of the assignor.
The proposition that the rights of the bank have been lost by the failure to enforce payment out of the first money received applicable to the payment cannot be sustained. The assignment was not merely of the first money received on the claim: it was of the entire claim, so far as necessary to meet the debt secured. The provision for payment out of the first moneys received was manifestly for the benefit of the bank. If, without surrendering its right to later payments, it failed to receive the earlier payments, the bridge company had no right to object to the enforcement of the lien out of the later payments. There is a lack of satisfactory evidence that the bank ever intentionally relinquished its claim upon the funds assigned. The testimony indicates that the bank supposed it was actually getting the moneys as fast as received. If this is so, the bridge company would
The objection that the lien is lost is thus not only without legal sanction, but is without equity, in view of the fact that the bankrupt estate has been benefited by the payments retained by the debtor. In' our opinion, the assignments of the moneys arising under construction contracts must be held valid and enforceable.
3. As to the pledge of the structural iron: On February 17, 190(1. the bridge company arranged for a loan at the bank of $15,000, to be secured by a pledge of 520 tons of structural iron, viz., 350 tons of T-beams and 170 tons of channels. The bridge company had this material on hand at the time. It accordingly executed a written transfer of the iron in these words:
“In consideration of $15,000.00 advanced to us this day by the Western German Bank, Cincinnati, Ohio, we hereby transfer to them as follows: 350 tons of I-beams as designed and marked lot No. 10, 170 tons of channels as designed and marked lot No. 12, 520 tons at $30.(50 per ton, $10,032.00. The above material to be the property of the Western German Bank and to be used only on the payment of the above loan or such portion as paid from time to time.”
It then set aside the 350 tons of I-beams in different piles in the yard, and had them marked as lot No. 10. At the same lime it set apart '! 70 tons of channels in different piles, marking them lot No. .12. These lots 10 and 12 were given into the custody of one Greer, a shipping clerk of the bridge company, with instructions to retain the custody on behalf of the bank and to keep the pledged iron intact. He accordingly checked over the piles, found them to aggregate the amounts stated, and gave a receipt reading:
“As warehouse custodian for the Western German Bank, I have (his day received from the Brackett Bridge Company 350 tons of I-beams designated as lot No. 10 and 170 lens of channels designated as lot No. .12. Said material is stored on the premises of the Brackett Bridge Company, is to be held intact, and to be subject to the order of the Wosiorn German Bank.”
The assignment was entered upon the stock book oí the bridge company, and (accompanied by a notarial certificate of sucli entry) was delivered to the bank, together with the custodian’s receipt, before tin money was loaned.
d'he objections to the validity of this pledge are: First, that it was not made in good faith, but in actual fraud; second, that then-was ho delivery of the iron, but that the pledgor retained possession and control of the iron and had the right to use it, no notice being given creditors; and, third, that the pledgor actually used the iron and that thus nothing remained for the pledge to attach to.
The evidence satisfies us of the good faith of the transaction. There is testimony tending to show that a portion at least of the pledged iron had been used; also that it had not been kept apart from the other property of the bridge company. There was also testimony of statements to third persons by the president of the bridge company inconsistent with the existence of a pledge of this stock. We arc satis
In our opinion, the validity of this pledge is sustained upon well-settled principles, recognized in the authorities above cited. The case presented differs radically from that of Security Warehousing Company v. Hand, 206 U. S. 415, 27 Sup. Ct. 720, 51 L. Ed. 1117, in which case the alleged change of possession was characterized as “a mere pretense, a sham.”
The District Court correctly held that the claimant is entitled to the preferential liens claimed, and its order will be affirmed.