The parties to this lawsuit attended a settlement conference without knowing that the district court had handed down a summary judgment decision. This appeal addresses what effect, if any, should be given to the agreement they reached before discovering the court’s action. We hold that a contract was formed and was not based on mutual mistake.
I. BACKGROUND
Beihua Sheng sued her former employer, Starkey Laboratories, Inc. (Starkey) alleging violations of Title VII. Starkey moved for summary judgment and, after a hearing, the motion was submitted to the district court. While the request was pending, the district court ordered the parties’ attendance at a mediated settlement conference, scheduled for Monday, December 20, 1993. On Friday, December 17, the district court signed an order granting Starkey’s motion for summary judgment. Although copies of the order were mailed to both counsel, the court’s order was not immediately entered in the official docket and the clerk of court did not enter judgment. See Fed.R.Civ.P. 58 & 79. Monday morning, not yet aware of the district court’s decision, the parties met in the chambers of a United States magistrate judge. At that conference, the parties agreed that Sheng would dismiss all of her claims against Starkey in exchange for Starkey’s payment of $73,500. At the conclusion of the meeting the attorneys shook hands and began discussing the appropriate tax treatment for the payment.
After the conference, the magistrate judge informed the district court of the agreement. The district court then rescinded its summary judgment order
sua sponte,
directing the clerk of court to enter neither the order nor judgment in the case docket. That afternoon, counsel for both parties received copies
Starkey filed a Rule 60(b) motion seeking to vacate the court’s orders rescinding the summary judgment and dismissing the ease. Starkey argues that there was no settlement because the parties did not agree on all material terms of the contract. Alternatively, Starkey maintains that the agreement is unenforceable because it was based on mutual mistake. The district court denied Starkey’s motion.
Starkey appealed that determination to this court. In
Sheng v. Starkey Laboratories, Inc.,
Back in district court, the ease was assigned to another judge, and the required evidentiary hearing was held. The court found that the parties had reached agreement on all essential terms, but held the contract was unenforceable because it was based on both parties’ mistaken assumption that summary judgment had not been granted. Accordingly, the district court rescinded the dismissal order and reinstated the summary judgment order in Starkey’s favor. Sheng appeals.
II. DISCUSSION
This is essentially an appeal of a Rule 60(b) decision. Rule 60(b) allows a district court to rescind a final judgment for a variety of reasons, including mistake.
See
Fed.R.Civ.P. 60(b)(l)-(6). We review the grant or denial of Rule 60(b) relief for an abuse of discretion.
MIF Realty L.P. v. Rochester Assoc.,
A. Existence of Contract
An enforceable settlement requires the parties to reach agreement on the essential terms of the deal.
Ryan v. Ryan,
Here, the district court concluded that the parties had an agreement on all material issues. The court specifically found that the deal hinged neither on the tax treatment of the payment, nor on other particulars, such as the wording of clauses regarding confidentiality, disclaimers and the release of liability. We will not set aside a district court’s findings of fact unless they are clearly erroneous. Fed.R.Civ.P. 52(a). We perceive no such error, and therefore affirm the district court’s legal conclusion that a contract did exist between these parties.
Starkey argues that even if the parties formed a contract, the agreement was based on a mutual mistake. A mistake is a belief that is not in accord with the facts.
Restatement (Second) of Contracts
§ 151 (1981). “Mutual mistake” consists of a clear showing that both contracting parties misunderstood the fundamental subject matter or terms of the contract.
Dubbe v. Lano Equip., Inc.,
The district court first held that both parties assumed that Starkey’s summary judgment motion was still pending, and then concluded that this misconception rendered the contract voidable as mutual mistake. The intent of contracting parties is an issue of fact, reviewed only for clear error.
City of Savage v. Formanek,
As an initial matter, we are not convinced that the parties’ erroneous assumption regarding the disposition of the summary judgment motion would warrant recision. Before a misconception will render a contract voidable, it must be more then an error about the monetary value of the consideration; it must go to the very nature of the deal.
Gartner v. Eikill,
Even if misapprehension' about the pendency of Starkey’s motion was a fundamental mistake, however, we hold that Starkey assumed the risk of that error. A party may not avoid a contract on the grounds of mutual mistake when it assumed the risk of that mistake.
Winter v. Skoglund,
III. CONCLUSION
The decision of the district court is affirmed in part and reversed in part. The case is remanded to the district court for entry of judgment dismissing the action based on the settlement agreement.
Notes
. Courts disagree on the body of law governing Title VII settlements.
Compare Snider v. Circle K Corp.,
