116 Mo. 179 | Mo. | 1893
The plaintiff entered into a contract with the defendants, whereby they agreed to furnish all the labor and materials, and build and complete an addition to a hotel, according to the plans, elevations and specifications furnished by the superintending architect; for which the plaintiff agreed to pay them the sum of $31,070, in installments as the work progressed. The defendants, Strimple & Son, proceeded with the work until nearly completed and then abandoned it, leaving unpaid bills. The plaintiff was obliged to employ others to complete the work and to lay out money in the discharge of mechanic’s liens created by the Strimples, and hence this suit. The Strimples made no defense. Wolf, Hayden and Reitz defend on the ground that they were sureties for the Strimples and that the plaintiff and the Strimples altered and changed the terms of the contract without theirdmowledge or consent..
The contract describes the defendants as “Joab Strimples & Son, principals, and A. Wolf, T. E. Hayden and John Reitz, sureties, parties of the second part.” The agreements throughout the contract are expressed to be by and between the parties of the first
By agreement the cause was heard by a referee, who found for the plaintiff as against the Strimples.in the sum of $5,203.54; and, ás to the affirmative defense, he found that the plaintiff and the Strimples made, without the knowledge or consent of the other defendants, changes and ¿Iterations in the plans and specifications forming a part of the contract as follows :
“First. The large sliding doors provided by the plans for the dining room were omitted, and a pair of smaller sliding doors inserted in the room on the second floor used for a parlor, the smaller doors being less costly than the doors omitted.
Second. The closets in the rooms on the second floor were differently arranged, and the doors, as you enter from the old building on the third, fourth and fifth floors were changed, so as to face the opening from the old building instead of being around on the north side coming from the hall.
Third. That by reason of the bottom of the basement being lower than the sewer for the new building, a bulk-head was put in the basement to enable the plumber to connect with the sewer for said addition.^
Fourth. That flitch-plates provided for the fifth story were omitted from that story, and used in the. openings of the first story to form girders instead of lintels.
Fifth. The closets in said addition were made six inches deeper than provided for by said plans.
Sixth. The basement of said addition was made six inches deeper than provided for by said plans.
As a matter of law the referee found that the sureties were discharged because of these changes and alterations. To this conclusion of law the plaintiff excepted and the exception was sustained, and the court gave judgment against all of the defendants for $4,431.
1. The first question is, did the appellants contract as principals, so as to waive' their rights ás sureties. One who is in reality a surety may contract as a principal. He may waive the rights which the law throws around a surety, for such a waiver has nothing in it offensive to the law; and the surety does waive such rights when he in terms contracts and agrees to be bound as principal. Picot v. Signiago, 22 Mo. 587; McMillan v. Parkell, 64 Mo. 286; Brandt on Surety-ship, sec. 28. But in this case the appellants did not waive their rights as sureties. They are in the beginning of the contract described as sureties, and when we come to the agreements concerning the last two payments the distinction between principal and sureties is
2. It is contended on behalf of the plaintiff that the superintendent had the right to make changes in the plans and specifications without consulting the sureties. Whether he had such right or not must depend upon a proper construction of the contact. As there is a dispute as to the meaning of the contract, it may be stated here, that ,the contract of a surety must be construed like any other contract, that is to say, according to the intent of the parties. There should be no strained construction in order to release or hold the surety. The contract of the, surety is “to be construed according to what is fairly to be presumed to have been the understanding of the parties, without any strict technical nicety.” Lee v. Lick, 10 Pet. 482; Lionberger v. Krieger, 88 Mo. 160; Locke v. McVean, 33 Mich. 473. “The rules for construing the contract of a surety or a guarantor, should by no means be confounded with the rule that sureties and guarantors are favorites of the law, and have a right to stand upon the strict terms of their obligations. * * * In the construction of the contract of a surety or guarantor, as well as of every other contract, the true question is: What was the intention of the parties, as disclosed by the instrument read in the light" of the surrounding circumstances? * * * The meaning of the words is not affected by the fact that the party sought to be
Guided by these principles we come to the contract, which contains the following stipulations: “The superintendent shall be at liberty to make any deviation from, or alteration in, the plan, form, construction, detail and execution, described by the drawings and specifications without invalidating or rendering void this contract, and in case of any difference in the expense, an addition to or abatement from the contract price shall be made, and the same shall be determined by the architect. And in case any such alteration or change shall be made or directed by the said superintendent as aforesaid, in the plans, drawings and construction of the aforesaid building, and in case of any omission or addition to said building being required by said superintendent, the cost and expense thereof is to be agreed upon in writing, and such agreement is to be signed by said parties of the second part and superintendent before the same is done or before any allowance therefor can be claimed; and in case of any failure so to agree, the same shall be completed upon the original plan.”
The first sentence provides in clear terms that the superintendent may make deviations from, and alterations in, the drawings and specifications without invalidating the contract; and in case of any difference in the expense, an addition to or abatement from the contract price shall be made, the same to be determined by the architect, meaning the superintendent, he being the architect. Nothing more appearing, the meaning would be that the superintendent had the right to make changes and alterations, and fix the amount to be added to, or deducted from the contract price by reason thereof. Had the parties stopped here, it is manifest that changes and alterations made in the work by
The finding of the referee shows that a number of changes and alterations were made, and that, too, without the knowledge or consent of the sureties. The
The circuit court gave judgment against all of the defendants on the theory that the changes were so slight that they were immaterial, applying the maxim, de minimis non curat lex. There was certainly a change of six inches in the depth of the basement and in the depth of the closets, and these changes made an additional cost in the plastering alone of $221.61. The change in the depth of the basement also added the cost of a bulk-head in order to secure sewer connections. The closets on second floor were differently arranged. How many closets there were, the record does not disclose, but it may be fairly presumed that there were many of them, as the structure was an addition to a hotel. Can it be said these changes, taken as a whole, were so small that the law will take no notice of them? We think not. No case to which we are cited will justify any such conclusion. To a suit to recover the expense brought about by these alterations, it would be no answer to say that they were immaterial. These changes destroyed the identity of
The judgment is reversed and the cause remanded with directions to enter judgment on the report of the referee in favor of the sureties, but in favor of the plaintiff as against the Strimples.