133 N.Y.S. 202 | N.Y. App. Div. | 1912
The plaintiff was a contractor with the city of New York for the improvement of the East Branch reservoirs, constituting a part of the city’s water system. The work included the raising of the spillway of the dam, raising and building the side walls of the spillway, some excavation and paving, and the building of stone fences. The work was completed to the satisfaction of the department having it in charge on January 2, 1906, and a final certificate given, upon which the final payment (excepting the retained repaving security) was made on February 28, 1906.
This action is for damages for the breach of a contract by the city in that, as is alleged, plaintiff was required and compelled to perform certain portions of the work in a more expensive manner than was required by the contract and specifications upon which he bid. It is now established that such an action will lie in a proper case and subject to the limitations hereinafter to be referred to. (Gearty v. Mayor, etc.,
The circumstances giving rise to this action are briefly as follows: On July 8, 1903, the city of New York by its department of water supply, gas and electricity, invited proposals for bids for doing the work referred to. The advertisement stated in general terms the character, nature and extent of the work to be performed and informed intending bidders that forms of bids together with a copy of the contract and specifications could be obtained on application at the office of the chief engineer “where plans' and drawings which aré made a part of the specifications may be seen.”
The plaintiff, through his engineer and superintendent of construction, obtained a copy of the contract and specifications, examined the ground upon which the work was to be performed, and applied at the office of the chief engineer to be allowed to examine the contract drawings, At this point there arises a conflict in the testimony. The plaintiff’s engineer and superintendent allege that they were shown only a single plan, of which a copy was put in evidence, and marked Exhibit G-, by which name for convenience it will hereafter be mentioned.This plan contains an outline of the work to be done, with an indication of the character of work at different places, but exhibits no detail of the manner in which the several classes of work are to be performed. Other plans were prepared by the department and used by the engineers in charge of the work, which in addition to the general plan and outlines exhibited on Exhibit G-, also contained graphic illustrations of the details of different classes of work. These plans came to be known in the case as Exhibits 3-0 and 3-D and will be so described hereinafter. The question whether or not plaintiff was shown Exhibits 3-0 and 3-D before he bid was sharply contested and made the subject of a specific question put to the jury, which answered that he had not. The evidence in our opinion justified this answer. It must, therefore, be accepted as a settled fact in the case that when plaintiff bid he had before him only the contract, specifications and a plan of which Exhibit 0 is a copy. While this plan did not show all -the details of the work
The present, as it seems to us, is a proper case for the application of this rule. The discrepancy between the plans, Exhibits 3-0 and 3-D, and the specifications certainly raised a debatable question as to which the contractor was bound to follow. These discrepancies related to the manner in which work called for by the contract should be performed, and did not include items of work entirely outside of the contract. We are, therefore, of the opinion that the plaintiff was entitled to recover upon the items of - his claim as to which, the jury awarded damages, and the amount of those damages as found by the • jury is supported by the evidence. ;
It follows that the judgment' and order: must be affirmed, with costs.'
Ingraham, P. J., Laughlin, Clarke and Miller, JJ.v concurred.
Judgment and- order affirmed, with costs.