76 N.Y.S. 438 | N.Y. App. Div. | 1902
Lead Opinion
In this action the plaintiff seeks to recover from the defendants for the. damages sustained by breach of a contract. The complaint alleged that defendants entered into a written contract on -the 18th day of August, 1898, whereby they employed the plaintiff to manu
The question as to whether there was a breach of the contract by the defendants was the material question to be determined upon the trial, and that depended upon the obligation of the defendants to accept and use in the construction of the building of the Albany Savings Bank the materials furnished by the plaintiff. The plairn tiff testified that he met a Mr. Wesehler,, the superintendent of the, defendants ; that Wesehler called a Mr. Barmyer, who,, he said, was a general draftsman employed by the defendants and was the man to look over the job and superintend it; that the defendants had a contract .with the Albany Savings Bank to furnish some bronze material, and that there resulted from this interview the original contract in writing between, the plaintiff and the defendants, which was introduced in evidence. By this contract the plaintiff agreed-to provide “ all the materials ■ for and perform in a good and workmanlike manner, under the direction of Henry Ives Cobb, architect, and according to the plans and. specifications of the said architect, all the work set forth and explained in said plans and specifications, which plans and specifications, being identified by the signatures of the parties hereto, are to be considered as forming a part of this agreement; and in case any particulars shall be deficient or not clearly expressed in said plans and specifications, the said party of the second part (plaintiff) will apply to the said architect for additional -drawings and explanations, and will carry out the general design as directed by the said architect in a thorough manner as part of the contract. And in case of any said work done dr materials provided by the said party of the. second part shall be unsatisfactory to the said architect, then the said party of the second part will, on being notified thereof by the said architect, immediately remove such unsatisfactory work or materials and supply, the place thereof with other work and materials satisfactory to the said architect.” It was also provided that “If any question should arise during the progress of the work, or in the settlement of accounts touching the same, it is to be referred to the said architect, whose decision shall be binding upon both parties; ” that “ The work under this contract is to be begun forthwith and carried on promptly^
We must keep in mind that the question to be determined is, whether the plaintiff complied with his contract, for it is a compliance with that contract that he alleges, and the refusal of the defendants to allow him to complete his contract in the way that he had undertaken to complete it is the breach alleged. As before stated, the plaintiff went on to complete his contract; manufactured the articles that he had contracted to supply, and on the fourth of November a portion of them was delivered at the building in Albany. As soon as they were delivered a Mr. Remington, who was an assistant of the architect in immediate supervision of the work, stated to the plaintiff that the bank people did not like the work because Hess & Co. had promised the bank people all cast work, and probably there -would be trouble in having the work accepted, saying to the plaintiff, “ I should advise you to stop with this work and not go on and put up anything in the building.” The following Saturday the plaintiff received a message from the defendants to come to New York to meet Weschler. At the interview that followed, Weschler said to the plaintiff that he had seen Mr. Cobb, the architect, and he wanted some changes made on the work, and asked the plaintiff whether he would do it, to which the plaintiff replied, “ I will if you get leave to pay me an additional sum for that part, whatever I do, and then you must enter into a new contract.” On the subsequent day Weschler went to the plaintiff’s shop and told him he had better stop all “ drawn work ” and simply work on the “ cast work.” He said that they would not be accepted if they were wrought; that he (Weschler) did not know what the bank people wanted, whether they wanted it wrought or cast and what portions they wanted cast. At this interview Weschler said, “ Becker, I am very sorry; you made a first class job of its kind, but it is not the kind the architect wants, and I am sorry it is not what he -wants. He is not satisfied with it.” At the
The architect was called on behalf of the defendants and testified as to the character of the work done and materials furnished by the plaintiff; that Remington, who was his representative in charge of the building, informed him of the character of the bronze work furnished by the plaintiff; that he went to Albany and saw the bronze work and that it was éntirely different from what was called for by the drawings; and he explained in detail the particulars in which the materials that he rejected failed to comply with the contract and drawings. The defendants then offered in evidence the contract between the defendants and the Albany Savings Bank, which was objected to by the plaintiff and excluded by the court.
The plaintiff was informed before he made this contract with the defendants that the defendants were erecting this building for the Albany Savings Bank, and that it was to comply with their contract with the bank that this sub-contract between the plaintiff and the defendants was made. The contract between the plaintiff and the defendants was, therefore, made in express reference to the contract between the defendants and the bank; and I think this contract was competent evidence to show that under their contract with the bank the defendants were prevented from using a portion of the materials furnished by the plaintiff in the performance of their work under their contract with the bank and that the determination of the architect was made in good faith under that contract. When the plaintiff refused to comply with the directions of the architect and furnish the bronze work according to his construction of the requirements of the contract and plans and specifications between the plaintiff and the defendants, the defendants were placed in the situation which this provision in the contract (requiring the work and materials furnished by the plaintiff to be approved by the architect, and providing that, in case any of said work done or materials furnished should be unsatisfactory to him, the plaintiff would remove such unsatisfactory work or materials and supply the place thereof with
■ The case narrows itself down to the one question, was it the defendants who were guilty of a breach of the contract because they refused to allow the plaintiff to continue to supply work and materials which the architect had determined were not in accordance with the contract and not satisfactory to him, or was it the plaintiff who, when he was informed of the determination of the architect that the materials that he had furnished were not satisfactory and were not in accordance with the contract, refused to comply with the direction of the architect and furnish the materials as directed by him ? It seems to me that it was the plaintiff who was guilty of a breach of the contract and not the defendants* and that the plaintiff had, therefore, failed to prove the crucial fact upon which his cause of action depended.
. Both at the end of the plaintiff’s'case and at the close of the testimony the defendants moved to dismiss the complaint upon the ground that there was no evidence that the defendants had been guilty of a breach of the contract. This motion was denied and the defendants excepted. The learned trial judge then submitted the question to the jury as to whether the plaintiff had complied with his contract, and they were directed that the determination of
The court also charged, the jury: “ The defendants deny that the plaintiff has done any work in accordance with the plans and specifications, and they say that for that reason they should not be compelled to pay him anything* so that you will see the question for you to determine is, has the plaintiff done the work that he contracted to do, in accordance with the plans and specifications furnished by the defendants. If he has, he is entitled to recover the sum that he has sued for. If he has not, he is not entitled uo recover that sum.” In relation to the provision of the contract as to the determination of the architect, the court charged: “ The contract contains a certain statement or a statement in various forms that it is to be to the satisfaction of the architect. I charge you that that means the reasonable satisfaction of the architect. If the architect as a reasonable man ought to have been satisfied with it, then the law says that he was satisfied with it, although as a matter of fact he refused to accept it. Was the work in compliance with the plans and specifications or not ? It may be as between the defendants and the owners of the building the architect would have the right to reject the work, because it may be that the work did not comply with the contract between the' defendants and the owners of the building, but that is immaterial so far as you are concerned, for the question for you is, did the work comply with the contract made by the plaintiff and the defendants.” Counsel for the defendants excepted to-this portion of the charge. The defendants then requested the court to charge that “ Before the plaintiff can successfully assert that there has been any" breach of contract on the part of the defendants and recover a verdict in his favor, you must be satisfied that there has been no breach of the contract on his part, for if there has been
In my view of this contract, and considering the theory upon which the action was brought, I think these requests to charge were correct and that it was error to refuse them.
The main principle to be applied in this case was considered in Sweet v. Morrison (116 N. Y. 19). There the defendants had-entered into a contract with the Northern Pacific Railroad . Company to furnish materials and build a part of its road, the contract providing that the work should conform to the specifications annexed, and to the construction and direction of the-chief engineer of the railroad company. The defendants entered into a contract with the plaintiffs to construct the bridges, trfestles and other timber work required by the contract between the defendants and the railroad company. They agreed to perform their contract to the satisfaction of the chief engineer of the railroad company, and he was made an umpire to decide all matters arising or growing out of the contract between the plaintiffs and the defendants, and his decision was to be final' and conclusive between the parties. The chief engineer made a determination as to the work and materials furnished by the plaintiffs which was not satisfactory to the plaintiffs, whereupon the plaintiffs sued to recover for the work and materials furnished in excess of that allowed by the certificate of the engineer. The court commented upon the fact that the person selected by the parties to make the estimate was in the employ of neither, and the case, therefore, was unlike those so frequently arising in which the certificate or estimate is required from the architect or engineer in the employment of one of the parties, and said : “ The intention of the parties to make it (the estimate) final is evident from the language used in their own agreement, and it is emphasized by the reference to the agreement between the railroad company and the defendants, which contains a' provision making the estimate' of the same person conclusive upon the parties to ■ that instrument also. The defendants evidently intended that the work which they had agreed to do for the railroad company and which they sub-let at a profit to the plaintiffs should be - estimated
Assuming, however, that the defendant was not entitled to the direction of a verdict, there was certainly a question of fact for the jury as to whether the architect acted in good faith in rejecting the plaintiff’s work as not in compliance with the plans and specifications and determining that the materials were not in accordance with the contract, and that, if he did, the refusal of the plaintiff to supply other materials in accordance with his decision was a breach of the contract by the plaintiff which precluded a recovery in this action, and the defendants were entitled to have the jury instructed upon
There is one other request to charge to which, I think, the defendants were entitled. The court had stated that in determining what weight there should be given to the evidence of a witness they might consider his interest in the result of the litigation; that the plaintiff “ of course is interested in the result of the litigation, and the defendant Lesser is interested in the result of the litigation, because he is one of the persons that is sued, just the same as the plaintiff is the person that sues, and in determining how much weight you shall give to the testimony of these witnesses you will consider that fact.” The defendants requested the court to charge that “ Becker is an. interested witness who if successful will recover the fruits of this litigation, and-you are not bound to believe him even though he were uncontradicted or uni impeached.” This the court refused to charge* and the defendants excepted'. I think the defendants were entitled to have this request charged. An examination of this testimony will show that Becker again and again testified to facts which were contradicted by every other witness who testified upon the subject. He testified to promises made to him by JBarmeyer and Weschler jvhich these witnesses contradicted. He also testified to occurrences which were contradicted by other witnesses. The court instructed the jury that in weighing his testimony they could consider his interest: but the defendants were also entitled to have the jury told that, he being an interested party, although they were to consider his testimony in the light of his interest in the controversy, they were not bound to accept his testimony as true, although uncontradicted or nnimpeached.
There was evidence tending to show that some of the materials furnished by the plaintiff, which were delivered at the savings bank and which the plaintiff refused to remove when rejected by the architect, were subsequently used in the construction of the building.
The judgment and order should be reversed and a new trial granted, with costs to the appellant to abide the event.
"Van Brunt, P. J., concurred; Patterson and Hatch, JJ.,■dissented.
Dissenting Opinion
I am unable to concur in the opinion of the majority of the court in this case. If there were nothing else involved in it than what is referred to in that opinion, I might coincide in some of the views therein expressed, but the real question at issue, as the case came before ns, is totally ignored in the prevailing opinion and it seems to me that the. rights of the parties are to be determined Upon facts which are not even casually adverted to in that opinion.
The action was brought to recover damages for the breach of contracts by which the defendants bound themselves to pay for certain work to be done and materials to be furnished by the plaintiff in fitting up part of a savings bank building in Albany. The materials and workmanship were to be to the satisfaction of an architect employed by the savings bank, and were to be paid for upon the presentation of the final certificate of that architect. The plaintiff’s
Bearing in mind that we are considering these contracts only as between the parties to them, and that for all the purposes of this litigation the Albany Savings Bank is an absolute stranger to the contest, the situation of the parties on the record before us is the following: The plaintiff alleges substantial performance up to the time he was prevented by the defendants from further performance. The defendants justify their act- of prevention by saying that the material furnished up to the time they intervened to prevent did not accord with the plans and specifications, and that the architect, who was the arbiter, so decided. To which the plaintiff rejoined that the defendants, through their agents, gave a construction to the plans and specifications, in strict accordance with which construction the plaintiff went on and manufactured the material. By the contracts between the plaintiff and the defendants, the architect was to determine whether the work accorded with the plans and specifications, but that architect was a resident of Washington in the District of Columbia, and was not accessible when questions arose as to the manner in which the material to be furnished by the plaintiff under the contracts should be manufactured. The plans and specifications of the contracts had been drawn by the head of one of the departments of the defendants’ business, and the work to be done by the plaintiff was superintended by another skilled employee of the defendants. Questions arising during the progress of the work as to the proper method of manufacture of the material under the specifications, and doubt arising as to that method, the plaintiff, according to his testimony, called upon Mr. Lesser, one of the defendant copartnership, and was told by Mr. Lesser to follow the instructions or the interpretation of the plans and specifications that should be given to him by those two persons, namely, the head of the drafting department and the superintendent of the defendants’ business.
Therefore, there was in the case evidence, which the jury believed,
I think that the right of the plaintiff to recover is plain, and that the. judgment ought to be affirmed, with costs, .
Judgment and order reversed and new trial granted, with costs to appellants to abide event.
Concurrence Opinion
I concur in the reversal of this judgment on the ground that it was error for the court to refuse to instruct the jury that in view of the plaintiff’s interest in the recovery the jury were not obliged to believe him. The right to recover rested upon, the uncorroborated testimony of the plaintiff, which was not altogether probable. In these circumstances, the jury should have been clearly instructed that if they deemed his evidence improbable they were not obliged to accept it, even though it was uncontradicted and he was not impeached.