BCCA APPEAL GROUP; NATIONAL RESOURCES DEFENSE COUNCIL; ENVIRONMENTAL DEFENSE; DAVID MARRACK; JANE W. ELIOSEFF; GALVESTON-HOUSTON ASSOCIATION FOR SMOG PREVENTION; GALVESTON BAY CONSERVATION AND PRESERVATION ASSOCIATION; SIERRA CLUB; AND BRAZORIA COUNTY, TEXAS v. UNITED STATES ENVIRONMENTAL PROTECTION AGENCY; CHRISTINE T. WHITMAN, ADMINISTRATOR; AND GREGG A. COOKE, ADMINISTRATOR, REGION 6
No. 02-60017
United States Court of Appeals, Fifth Circuit
January 8, 2004
ON PETITION FOR REHEARING EN BANC January 8, 2004
Charles R. Fulbruge III, Clerk
ON PETITION FOR REHEARING EN BANC (Opinion October 28, 2003, 5th Cir., 2003, 355 F.3d 817)
DAVIS, Circuit Judge and RESTANI, Judge:
Treating the Petition for Rehearing En Banc of Environmental Defense, David Marrack, Jane Elioseff, Galveston-Houston Association for Smog Prevention, and the Galveston Bay Conservation and Preservation Association as a Petition for Panel Rehearing, we delete footnote 28 from the original panel opinion and substitute the following in its place:
Footnote 28 - Environmental Defense claims that the CAA‘s specific mention of enforceable commitments in two provisions precludes the EPA from fully approving the Houston SIP under
§ 7410(a)(2)(A) . To the contrary, however, nothing in the CAA directly governs this issue. One provision,42 U.S.C. § 7410(k)(4) , gives EPA discretionary authority to conditionally approve a SIP “based on a commitment of the State to adopt specific enforceable measures by a date certain.” ED claims that this provision, which was enacted in 1990 amendments to the CAA, was meant to supplant EPA‘s practice of fully approving enforceable commitments under§ 7410(a)(2)(A) . There is nothing in the statute or in the legislative history, however, to support this theory. Furthermore, the cases Environmental Defense relies upon, which address conditional SIP approvals or construe statutory provisions before the 1990 amendments, are inapposite.ED also claims that the EPA‘s full approval of the Houston SIP‘s enforceable commitments was not authorized by
42 U.S.C. § 7511a(e)(5) , which provides that the EPA may “approve provisions of an implementation plan for an extreme area which anticipate[s] development of new control techniques or improvement of existing control technologies, and an attainment demonstration based on such provisions, if the state demonstrates . . . that . . . the State has submitted enforceable commitments to develop and adopt contingency measures to be implemented if the anticipated technologies do not achieve planned reductions” (emphasis added). The court agrees that EPA‘s action was not authorized by this particular provision, because it governs extreme nonattainment SIPs, not SIPs for severe nonattainment areas like Houston-Galveston. Contrary to ED‘s assertions, however, the fact that EPA‘s action was not authorized by this particular provision does not mean that EPA‘s action was not in accordance with law.The legislative history of the 1990 amendments of
§ 7410(a)(2)(A) acknowledged EPA‘s practice of fully approving SIPs that contained limited enforceable commitments, yet Congress made no changes to that sectionprecluding the practice. See H.R. Rep. No. 101-490, pt. 1 at 218 (1990). In fact, the 1990 amendments expanded EPA‘s authority under § 7410(a)(2)(A) by adding the “means” and “techniques” and “as . . . appropriate” language. This strengthens, rather than limits, the statutory basis for EPA‘s practice of fully approving SIPs that contain enforceable commitments as part of an overall control strategy. Finally, because§ 7410(a)(2)(A) is silent on the issue of whether an enforceable commitment is an “appropriate” “means” or “technique” to reach attainment, EPA‘s interpretation must be upheld if the court finds it a permissible construction of the statute.
In all other respects the Petition for Panel Rehearing is DENIED.
No member of the panel nor judge in regular active service of the court having requested that the court be polled on Rehearing En Banc (
