Bayliss v. Hennessey

54 Iowa 11 | Iowa | 1880

Servers, J.

struotion°of contract. Tbe contract of purchase and warranty was in writing. Tbe defendant contracted to pay two hundred dollars for tbe machine, as follows: “ Cash $22, an reaPer;note $95, due November 1,1877, with interest at teu per cent per annum, provided tbe machine was as warranted,” but if it proved not to be, “ after notice and trial as stipulated in tbe warranty,” then tbe defendant was to return it to tbe place of delivery. Tbe warranty was as follows:

“When tbe machine is put in operation, if it should fail to perform as warranted, it shall be tbe duty of tbe purchaser to notify us immediately of tbe fact, and allow us sufficient time to send a man and put it in order; then, if it does not work, and tbe fault is in tbe machine, it will be taken back and tbe money refunded, or that part which proved defective will be replaced, or a perfect machine given in its place. Tbe use of tbe machine in cutting five acres shall be conclusive evidence that tbe warranty is fulfilled.” *

Both parties claimed to have performed tbe contract on their part, and that tbe other failed to do so.

It is assigned as error, 1. That tbe judgment is not in accordance with, but is contrary to, tbe facts found. Tbe court found tbe machine was not as good as it was warranted, and also tbe following facts in tbe form of questions and answers:

“ Q. 4. Did defendant cut five acres with tbe machine, before be notified tbe agent of plaintiff that tbe machine would not work? A. No.
Q. 7. Did tbe defendant, between tbe first and second time of notifying plaintiff’s agent, cut more than five acres? A. Don’t know. .
*13“ Q. 11. Did the defendant, between the first time plaintiff’s agent left the machine at work and the next Sunday thereafter, cut five acres or more of grain with the machine? A. Tes.”

The contract in term§ stipulated that the cutting of five acres with the machine should be regarded as conclusive evidence the warranty had been fulfilled. Now, as the fact is that more than five acres were cut with the machine, the terms and conditions of the warranty have been complied with on the part of the plaintiff, because the parties have so expressly contracted. The plaintiff, therefore, is entitled to recover, and the District Court correctly so held.

Counsel for the appellant insists that the five acre clause only refers to the first trial. There is no such exception in the contract, and it would require certain essential words inserted therein before such construction could be adopted. It seems to us there is no room for construction, but that the evident meaning of the words used must prevail and be adopted.

2. The machine was to be shipped to the defendant on or before the 15th day of July, 1876. When it was received does not distinctly appear, but conceding it to be at the time just stated, the defendant agreed to then pay therefor in accordance with the contract. Among other payments he was to execute a note for $95, bearing ten per cent interest. On this amount the plaintiff was entitled to the stipulated interest, because there was a written agreement to pay ten per cent interest. He also agreed to pay in cash $22, and the value of the old reaper must have been fixed at $83. On neither of these amounts did the defendant in writing agree to pay ten per cent interest.

The District Court rendered a judgment for $212, with ten per cent interest thereon from July 15, 1876. This judgment is excessive. The plaintiff is only entitled to recover' $200, ninety-five dollars of which should draw interest at ten per cent from the time above stated, and the residue at *14the rate of six per cent. As there was a finding of facts such a judgment as the District Court should have rendered may "be entered here, if the plaintiff so desires, or the cause will be remanded to the court below for this purpose.

The next question is at whose costs should the correction be made. No motion for a new trial was made in the District Court, nor is there any evidence in the abstract tending to show the attention of that court was called to the error. Under the express provision of Code, § 3168, this cause cannot be reversed for the error alluded to, because no motion to correct it was made in the District Court. It follows, therefore, that the correction should be made at the costs of appellant. The appellee must recover his costs in this court.

Modified and affirmed.

midpage