235 Mass. 263 | Mass. | 1920
This is a bill in equity brought by the plaintiff in behalf of itself and of all other creditors of the defendant W. H. Ellis and Son Company who may be permitted to join as parties plaintiff against W. H. Ellis and Son Company, the Commonwealth of Massachusetts and the National Surety Company, under R. L. c. 6, § 77, to recover for labor performed or furnished and for materials used in the construction or repair of a pier and steel shed in the city of New Bedford under a contract dated January 5, 1915, between the Commonwealth of Massachusetts, acting by its Board of Harbor and Land Commissioners, and W. H. Ellis and Son Company, and is before this court on a reservation from the Superior Court. No question is raised as to the validity of the contract. ■
On January 6, 1915, W. H. Ellis and Son Company, as principal, and the National Surety Company, as surety, in pursuance of the contract and of. the statutes of the Commonwealth, executed and delivered to the Commonwealth of Massachusetts a bond conditional upon the payment by it for labor performed or furnished and for materials used in the construction or repair of said public work. Thereafter the Ellis company began work under said contract, and from time to time entered into subcontracts with the remaining intervening plaintiffs to furnish materials and perform labor of various kinds in connection therewith. While" the work was progressing under the contract, on April 11, 1917, the Commonwealth of Massachusetts, acting by the Commission on Waterways and Public Lands, which commission had succeeded to the powers and duties of the Harbor and Land Commission, entered into a written modification of the original contract with the Ellis company, which modification released the Ellis company from its obligation under the contract to construct a driveway through the centre of the pier and through the shed, of vitrified paving brick, wood blocks or granite blocks.
When the contract was thus modified, the driveway had been filled with dirt, but had not been surfaced in any way. Regard
At the hearing before the master there was evidence and the master-found that the various plaintiffs filed with the Harbor and Land Commission or their successors, the Commission on Waterways and Public Lands, claims against the Ellis company in the proper form and in compliance with the statute, except as to the question whether some of them were seasonably filed; and the issues now presented are whether certain of the plaintiffs seasonably filed proofs of claim, and, as to certain of them, (Joseph Langlois and Charles S. Ashley and Sons Company,) whether the labor performed and materials furnished are of such a character as to permit them to recover in this proceeding.
The claim of Langlois is for the use of a staging and falls which were reasonably used by a subcontractor of the Ellis company in the necessary work of painting and plastering upon the pier and steel shed. They remained upon the premises after the completion of the work of painting and plastering, were damaged and ren
The claim of Charles S. Ashley and Sons Company is for a premium on an insurance liability policy issued to the" Ellis company; it is not for labor or material performed or furnished, and is not within the statute. Kennedy v. Commonwealth, supra. Sampson v. Commonwealth, 202 Mass. 326. Friedman v. County of Hampden, 204 Mass. 494.
The remaining claims which are contested fall into one or the other of two classes: (1) those wherein the sworn statements of claims were filed before September 4, 1917, and (2) those wherein the sworn statements of claims were filed more than sixty days after September 4, 1917. The defendant National Surety Company contends that the statute is in derogation of common right, should be strictly construed, and that so construed the sworn statement of every claimant under the statute must be filed within the period of sixty days which begins September 4, 1917, and ends November 3, 1917. Assuming, without deciding, that the statute in question in analogy to the construction of mechanic lien statutes is to be construed strictly, as to which see Gale v. Blaikie, 129 Mass. 206, 209; Whalen v. Collins, 164 Mass. 146; Angier v. Bay State, Distilling Co. 178 Mass. 163; Pratt & Forest Co. v. Strand Realty Co. of Lowell, 233 Mass. 314; Nash v. Commonwealth, 174 Mass. 335, 182 Mass. 12; Burr v. Massachusetts School for Feeble-Minded, 197 Mass. 357; Friedman v. County of Hampden, 204 Mass. 494; E. I. Dupont De Nemours Powder Co. v. CulginPace Contracting Co. 206 Mass. 585; Philadelphia v. Fidelity & Deposit Co. of Maryland, 231 Penn. St. 208; Ann. Cas. 1912 B 1085 note, no one could be injured in the legal sense if a claim within the terms of the statute was filed with the designated officer or agent of the Commonwealth at any time within sixty
The filing of the sworn statements was seasonable and within the statute. The work to be completed as a condition to the right to have the benefit of the security, upen the filing of a sworn statement within sixty days after the completion of the work, plainly refers to the public work embraced within the terms of the contract as it existed when the contractor or subcontractor was required to furnish sufficient security for the labor and material to be performed or furnished; and the right "to have the benefit of that security enured to any laborer and materialman who should furnish labor or material which was used or employed in the construction or repair of the public work if he should file a sworn statement of his claim within sixty days after the completion of the work contemplated by the original contract, even if it be not completed by the original contractor.
The interlocutory decree confirming the master’s report as modified is affirmed. The cause is remanded to the Superior Court to establish the debts of the several plaintiffs, and to establish the form of the decree in accordance with this opinion.
Decree accordingly.