Bryan BAUMEISTER, Robin Baumeister, Jeffrey Brown and Stacy Brown, Plaintiffs-Appellants-Petitioners, HERITAGE MUTUAL INSURANCE COMPANY, Subrogated-Plaintiff, v. AUTOMATED PRODUCTS, INC., Defendant, Edward A. SOLNER AIA d/b/a Solner and Associates, Defendant-Respondent-Petitioner.
No. 02-1003
Supreme Court of Wisconsin
Oral argument September 10, 2004.— Decided December 15, 2004.
2004 WI 148 | 690 N.W.2d 1
For the defendant-respondent-petitioner there were briefs by Anthony R. Varda and DeWitt Ross & Stevens, S.C., Madison, and oral argument by Anthony R. Varda.
An amicus curiae brief was filed by Lynn R. Laufenberg and Laufenberg & Hoefle, S.C., Milwaukee, on behalf of the Wisconsin Academy of Trial Laywers, and oral argument by Lynn R. Laufenberg.
¶ 1. N. PATRICK CROOKS, J. This case is before the court on two petitions seeking review of an unpublished decision of the court of appeals, Baumeister v. Automated Products, Inc., No. 02-1003, unpublished slip. op. (Wis. Ct. App. Nov. 20, 2003). The first petition,
¶ 2. We affirm the court of appeals and hold that summary judgment was appropriately granted in favor of Solner. We find that there were no genuine issues of material fact presented by Baumeister and Brown to rebut the affidavits presented, and, thus, the prima facie case established, by Solner. We further hold that the court of appeals was correct when it denied Solner‘s motion for costs, fees, and reasonable attorney fees, pursuant to
I
¶ 3. On November 12, 1994, Holy Trinity Lutheran Church (Holy Trinity) retained Edward Solner, an architect licensed in Wisconsin, to design its new church. Solner entered into a contract with Holy Trinity pursuant to the Standard Form of Agreement Between Owner and Architect, AIA Document B141 (1987 ed.), which contained the language from Sections 2.6.52 and 2.6.6.3 Holy Trinity had the option to extend
¶ 4. Holy Trinity hired Roberts Construction Associates, Inc. (Roberts), as the general contractor, pursuant to a Standard Form of Agreement Between Owner and Contractor, AIA Document A101 and 201 (1987 ed.). This contract specified, among other things, that both Roberts and its subcontractors must follow certain requirements related to truss installation: (1) comply with recommendations of TPI (Truss Plate Institute) design specifications for metal plate connected wood trusses and the State of Wisconsin Code requirements; and (2) install materials and systems in accordance with manufacturers’ instructions and approved submittals.
¶ 5. Solner completed his plans of the new church and then designed “contract specifications” for the wood trusses to be placed above the main assembly area. Meanwhile, Roberts hired Automated Products, Inc. (Automated) to provide the fabricated wood trusses. An engineer from Automated, Gary Korpela, designed the trusses and their layout to meet the “contract specifications.” Automated then shipped the trusses to the construction site and attached instructions: “The Builder shall be responsible for proper truss handling and bracing. A guide for the qualified Builder may be but is not limited to: ‘Handling and Erecting Wood Trusses’ by TPI, Inc.”
¶ 7. The insurance company for Holy Trinity, General Casualty Company, subsequently brought a subrogation claim against Diamond Builders in September, 1999. General Casualty sought to recover the cost of the collapsed trusses and the cost for the cleanup, which it had paid to Holy Trinity after the accident. The complaint alleged negligent installation of temporary bracing of the wood trusses.
¶ 8. Baumeister and Brown moved to intervene pursuant to
¶ 9. The court of appeals unanimously affirmed the circuit court‘s grant of summary judgment. Judge Lundsten, writing for the majority on that matter, held that Baumeister and Brown were unable to show that Solner‘s duty of care included supervising personally the construction site, assuring safe construction, or providing safe temporary truss bracing instructions. Moreover, the court of appeals found that Baumeister and Brown would not have been able to satisfy the causation requirement for a claim of negligence, since they, themselves, did not follow the TPI guidelines and, thus, could not show that Solner was negligent in directing that those guidelines be followed. Such alleged negligence could not, therefore, have been a substantial factor in producing their injuries. Baumeister, No. 02-1003, unpublished slip. op., ¶ 32.
¶ 10. The issue of the frivolous appeal resulted in a split decision. Judge Deininger wrote a concurrence joined by Judge Vergeront. The majority of the court of appeals concluded that Solner was not entitled to costs, fees, and reasonable attorney fees under
II
¶ 11. We first address whether summary judgment was appropriately granted. Although benefiting by the review of the circuit court and the court of appeals, we review an order for summary judgment de novo, applying the same standards as used by those courts. Conley Publ‘g Group v. Journal Communications, 2003 WI 119, ¶ 13, 265 Wis. 2d 128, 665 N.W.2d 879. We will affirm a grant of summary judgment when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law.
¶ 12. The first step of the methodology is to determine whether the pleadings set forth a claim for relief. Trinity Evangelical v. Tower Ins. Co., 2003 WI 46, ¶ 32, 261 Wis. 2d 333, 661 N.W.2d 789. If a claim for relief is stated, then examination is made of the moving party‘s affidavits and other proof to determine whether a prima facie case for summary judgment has been established. Peninsular Carpets, Inc. v. Bradley Homes, Inc., 58 Wis. 2d 405, 410-11, 206 N.W.2d 408 (1973). If a moving party has established a prima facie case, the opposing party must then establish that there are disputed material facts, or undisputed material facts from which reasonable alternative inferences could be
¶ 13. Baumeister and Brown‘s principal summary judgment argument in opposition to the motion is that there exist genuine issues of material fact concerning Solner‘s duty. They claim that the circuit court failed to address properly evidence that created a common-law duty based on foreseeability. In making the argument, Baumeister and Brown rely almost exclusively on this court‘s recent decision in Alvarado v. Sersch, 2003 WI 55, 262 Wis. 2d 74, 662 N.W.2d 350. That case held: “a duty to use ordinary care is established whenever it is foreseeable that a person‘s act or failure to act might cause harm to some other person.” Id., ¶ 14 (citation omitted).5 Baumeister and Brown argue that this principle, applied to the facts of this case, results in a duty that was breached by Solner, because he should have foreseen that the trusses would not have been installed properly. They allege that because Solner gave instructions to the general contractor, Roberts, that workers should follow the guidelines of TPI, but did not give more adequate instructions to the workers, themselves, he should have known that the workers would be in danger. As a result, they contend that the architect breached his duty to provide some form of warning.
¶ 15. Baumeister and Brown‘s next argument is that the court incorrectly ruled on Solner‘s contractual responsibility to prepare specific bracing instructions. They allege that Automated‘s instructions clearly stated that the temporary bracing instructions were
¶ 16. Baumeister and Brown also contend, in their briefs, that Solner, personally, had a duty, which was breached, to supervise truss installation. Although their attorney did not rely on this claim during oral arguments,9 they maintain that Solner was in breach of the Wisconsin Administrative Code. Specifically, Baumeister and Brown attack Solner for ignoring
¶ 17. Baumeister and Brown also assert that the issue of causation should also be left for a jury. They buttress this argument with a claimed presumption that in cases where there are inadequate warnings, causation is presumed, relying on Tanner v. Shoupe, 228 Wis. 2d 357, 380, 596 N.W.2d 805 (Ct. App. 1999). It should be noted that their argument is not really about inadequate warnings, but about no warnings, and either wrong or inadequate instructions.
¶ 18. We agree with the conclusion of the court of appeals that Solner, in that regard, did not breach his duty to use the standard of care ordinarily exercised by an architect. Baumeister and Brown‘s reliance on Alvarado is misplaced.10 They assert that Solner‘s “superior
¶ 19. Although Baumeister and Brown alleged that an architect who designs or specifies a building component has a professional duty, which was breached, to ensure that safe installation instructions for that particular component are provided, the court of appeals noted that they presented no expert testimony in support of that allegation. Id. In his affidavit, Buttry did not assert directly, or through a recitation of his qualifications, that he was qualified to give an opinion as an expert on the professional responsibility of an architect.
¶ 20. Solner asserted in his affidavit that, in the usual situation, the contractor would hire a truss manufacturer to provide necessary trusses and its engineer would assure that the trusses met the design specifications.11 In his professional opinion as an architect, Solner stated that he “had a right to reasonably rely upon the professional certification of Mr. Korpela as to the structural accuracy of the trusses he had designed and [he] had no obligation to redesign those trusses or inspect and verify the trusses, as built, to determine if they complied with his design.” Based on
¶ 21. Solner also had no contractual duty, which was breached, in regard to the installation of the truss bracing. An inspection of the contract and review of the truss manufacturer‘s instructions demonstrate that Baumeister and Brown‘s argument is flawed. Under the terms of the AIA contract, Solner is relieved of liability with regards to “construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work.” AIA Section 2.6.6. Architect Lee Madden confirmed this in his affidavit. He stated: “Under AIA contracts, the architect is not responsible for, nor does he control, the methodology and techniques chosen by the contractor to construction [sic] a building, including the use of temporary bracing while erecting trusses.”
¶ 22. As for the argument that Automated‘s instructions bind Solner, since the instructions read, “both temporary and permanent bracing are required and their design is the responsibility of the project architect or engineer,” the court of appeals disposed of it convincingly:
Baumeister, No. 02-1003, unpublished slip op., ¶¶ 15-18. The holding of the court of appeals is consistent with our decision in Vonasek v. Hirsch and Stevens, Inc., 65 Wis. 2d 1, 221 N.W.2d 815 (1974). In that case, a general contractor brought a claim against an architect to recover for damages from a building that collapsed. The contractor alleged that the architect had supplied defective plans and specifications, and that his supervision of the project was inadequate. We concluded that the architect‘s contract with the owner did not require the architect to specify procedures or to supervise the work of the contractor.12 “To hold otherwise would make the architect a general safety super-First, nothing in the truss manufacturer‘s instructions “explicitly” states that “Solner” is responsible.
Second, Baumeister and Brown do not even attempt to explain why a directive from the truss manufacturer could impose a contractual duty on the building architect.
Third, the manufacturer‘s instructions do not say that the architect of the building is responsible for
providing temporary truss bracing instructions. Rather, the manufacturer‘s instructions read: “both temporary and permanent bracing are required and their design is the responsibility of the project architect or engineer.” Baumeister and Brown do not provide any basis on which to conclude that Solner was the “project architect” within the meaning of the manufacturer‘s instructions. Certainly Solner was the architect who designed the church, but does that make him the “project architect” within the meaning of the instructions? Baumeister and Brown provide no answer. Fourth, the manufacturer‘s instructions put responsibility on the “project architect or engineer.” Baumeister and Brown do not explain why, with respect to this particular project, it is the project architect and not the project engineer who was responsible.
¶ 23. Baumeister and Brown also failed to demonstrate that there was a breach of a duty by Solner, personally, to supervise the construction site. The duty listed in the Wisconsin Administrative Code ensures that the construction complies with the approved plans and specifications.
¶ 24. The court of appeals also acknowledged that Baumeister and Brown “have a causation problem” in regard to the assertion that Solner was negligent when he required that the TPI instructions be followed. Baumeister, No. 02-1003, unpublished slip. op., ¶ 32. In Wisconsin, the test for causation is whether the conduct at issue was a “substantial factor” in producing plaintiff‘s injury. Estate of Cavanaugh v. Andrade, 202 Wis. 2d 290, 306, 550 N.W.2d 103 (1996). Here,
III
¶ 25. We next address Solner‘s motion to declare the appeal frivolous, in accordance with
¶ 26. Frivolous action claims and frivolous appeals present a serious cause for concern. We have found this to be “an especially delicate area since it is here that ingenuity, foresightedness and competency of the bar must be encouraged and not stifled.” Radlein v. Indus. Fire & Cas. Ins. Co., 117 Wis. 2d 605, 613, 345 N.W.2d 874 (1984). Thus, in Wisconsin, the court of appeals has not assessed costs, fees, and reasonable attorney fees under
¶ 27. Solner argues that this interpretation of the frivolous appeals statute will lead to illogical results. He contends that because causation is a determinative factor in a negligence analysis, if causation cannot be established, that the entire appeal should be found to be frivolous. This argument is flawed. We need to find each of their arguments frivolous, under
¶ 28. The court of appeals’ majority was correct in determining that not all of the arguments made by Baumeister and Brown were lacking in arguable merit. Legitimate issues were raised concerning whether Solner breached his duty of care as an architect. Although
¶ 29. Judge Lundsten concluded in his dissent that Baumeister and Brown should have been sanctioned for filing a frivolous appeal. He agreed that under
¶ 30. We conclude, as did the court of appeals’ majority, that it was not frivolous for Baumeister and Brown‘s attorney to rely on Buttry‘s affidavit concerning Solner‘s duty of care related to truss bracing. As stated above, the Buttry affidavit raises an issue as to
¶ 31. Lastly, we decline, as urged by Solner, to overrule the court of appeals’ holding in Leske v. Leske, 185 Wis. 2d 628, 517 N.W.2d 538 (Ct. App. 1994). In Leske, the defendant counterclaimed for costs and attorney fees under
¶ 32. We encourage a party alleging a frivolous claim to move the appellate court to stay the appeal, and retain jurisdiction while the case is remanded for a circuit court ruling on the frivolousness issue. If a party chooses to appeal the circuit court‘s frivolousness rul-
IV
¶ 33. In sum, we conclude that the summary judgment motion of Solner was properly granted. There were no genuine issues of material fact presented by Baumeister and Brown to rebut the affidavits and attachments filed, and, thus, the prima facie case established, on behalf of Solner, that supported Solner‘s position that Solner breached no duty of care.
¶ 34. We also conclude that Baumeister and Brown‘s appeal was not frivolous under
By the Court.—The decision of the court of appeals is affirmed.
¶ 35. JON P. WILCOX, J., did not participate.
Notes
(a) If an appeal or cross-appeal is found to be frivolous by the court, the court shall award to the successful party costs, fees, and reasonable attorney fees under this section. . . .
(c) In order to find an appeal or cross-appeal to be frivolous under par. (a), the court must find one or more of the following:
(1) The appeal or cross-appeal was filed, used or continued in bad faith, solely for purposes of harassing or maliciously injuring another.
(2) The party or the party‘s attorney knew, or should have known, that the appeal or cross-appeal was without any reasonable basis in law or equity and could not be supported by a good faith argument for an extension, modification or reversal of existing law.
The Architect shall visit the site at intervals appropriate to the stage of construction or as otherwise agreed by the Owner and . Architect in writing to become generally familiar with the progress and quality of the Work completed and to determine in general if the Work is being performed in a manner indicating that the Work when completed will be in accordance with the Contract Documents. However, the Architect shall not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. On the basis of on-site observations as an architect, the Architect shall keep the Owner informed of the progress and quality of the Work, and shall endeavor to guard the Owner against defects and deficiencies in the Work. (More extensive site representation may be agreed to as an Additional Service, as described in Paragraph 3.2.)
The Architect shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, since these are solely the Contractor‘s responsibility under the Contract for Construction. The Architect shall not be responsible for the Contractor‘s . . . failure to carry out the Work in accordance with the Contract Documents. The Architect shall not have control over or charge of acts or omissions of the Contractor, Subcontractors, or their agents or employees, or of any other persons performing portions of the Work.
Vonasek v. Hirsch and Stevens, Inc., 65 Wis. 2d 1, 11, 221 N.W.2d 815 (1974) (emphasis omitted).“3.4.3 [The Architect] will make periodic visits to the site to familiarize himself generally with the progress and quality of the work and to determine in general if the work is proceeding in accordance with the Contract Documents. He will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the work and he will not be responsible for the Contractors’ failure to carry out the construction work in accordance with Contract Documents.”
