At the time of his injury in February 2013,
Bath arrived at the plant that morning without his tic tracer, which is a device used to detect "live" electrical current, and was given one by his supervisor Jerry Grubbs.
The IP employees then left the area, and the White Electrical employees tripped, tagged, and locked out Circuit 23 in Panel Box 8. They then went back to the dryer basement press area and tested the wires to the lights they would be working on to make sure they had been de-energized when they tripped the circuit. Bath was specifically observed using his tic tracer to make this check along with the other workers.
After working on repairing the lights for several hours, the White Electrical workers took a break and then came back and re-energized the lights to see if their repairs had been successful. However, "the last three lights" were still not working, and Grubbs testified that he told the other workers that probably meant there was a broken wire in a higher conduit that had not yet been checked. He instructed Bath and Baxter to trouble shoot the non-working lights, and they all went back to the panel box where Bath and Baxter again tagged and locked out Circuit 23 in Panel Box 8. Grubbs and the other White Electrical employee then went to another area of the plant to make repairs, and Bath and Baxter returned to trouble shoot the non-working lights.
Baxter and Bath had to use a scissors lift to reach the conduits they believed contained the wires to the inoperable lights. Baxter then exited the lift and climbed up on the condulet to reach the conduit containing the wires.
Based on these events, Bath alleged that defendants negligently provided them with an out-of-date, inaccurate, and misleading lighting plan and negligently represented to White Electrical which circuit and lighting panel provided the source of electric power to the lights on which they were performing repairs.
Prior to the trial court's ruling on defendants' summary judgment motions, Bath filed a motion for sanctions based on the alleged spoliation of evidence, including the tic tracer he had been using that day and the wires and lights that were replaced. Bath argued that, as to the tic tracer, the lost evidence prevented him from testing the tracer to determine if it was working properly at the time he was injured, which would negate defendants' defenses based on his failure to use the tic tracer to determine if the wire was energized before he started working on it. As to the light fixture, Bath argued that, by tracing the serial number, it would be possible to determine
Without specifying which grounds, the trial court agreed with defendants that Bath's motion for sanctions was unrelated to three of the grounds for summary judgment, and thus those grounds could be considered, and summary judgment granted if warranted, even if spoliation had occurred. The court then went on to rule against defendants on the issue of contractual surrender, deemed summary judgment improper on the assumption of the risk defense because of the spoliated tic tracer, but granted summary judgment to defendants on the grounds of lack of reasonable reliance on the trial court's sua sponte re-framed claim for "negligent misrepresentation," intervening cause or failure to prove proximate cause, and lack of superior knowledge. This appeal followed.
1. Bath contends that the trial court erred in granting summary judgment because IP spoliated key pieces of evidence.
Spoliation refers to the destruction or failure to preserve evidence that is necessary to contemplated or pending litigation. Such conduct creates the presumption that the evidence would have been harmful to the spoliator. Proof of spoliation raises a rebuttable presumption against the spoliator that the evidence favored the spoliator's opponent, a fact rendering summary judgment inappropriate.
(Citations and punctuation omitted.) Baxley v. Hakiel Indus., Inc.,
even if [the] evidence [is] wrongly destroyed, the injured party still must show prejudice, and the grant of summary judgment is appropriate if the injured party cannot establishany causal link between the failure of his underlying claims and the alleged misconduct by the defendant.
(Citation and punctuation omitted.) Wilson v. Mountain Valley Community Bank,
(a) Proximate Cause. The trial court concluded that summary judgment was appropriate based on a finding that "the final, proximate cause of Plaintiff's injury was White Electrical's failure to de-energize the 277-volt wire." Pretermitting the soundness of that ruling, see Miller v. Turner Broadcasting Sys. Inc.,
(b) Premises Liability and Superior Knowledge. As to the issue of superior knowledge and the light fixture, the trial court agreed that the light fixture was relevant to the issue of IP's knowledge of the 277-volt wires, but went on to find that even if it determined that there was spoliation of the light fixture, it would show only a possible date of manufacture and/or a timeframe within which the light was changed, which would be irrelevant because the undisputed testimony indicates that contractors have been replacing the machine for decades, a fact the trial court says no party disputes.
Although it is true that the evidence showed that electrical contractors took over the majority of electrical work and repairs in the mill in or around 2000, the evidence also showed that IP conducted its own electrical maintenance and repair from the time the Number 8 paper machine became operational around 1990 or 1991 until it began to use electrical contractors for the majority of the repairs about ten years later. Brown in particular testified that he worked on the lights in the Number 8 paper machine during the
2. Defendants argue, however, that they were also entitled to summary judgment because IP surrendered the premises to White Electrical and that we should reverse the trial court's adverse ruling on this issue and affirm on this alternative basis. Although we agree that the issue of whether relevant evidence was spoliated is unrelated to the issue of contractual surrender, defendants' failure to file a cross-appeal from this adverse ruling means we cannot reach this issue. See OCGA § 5-6-38 ; Truelove v. Buckley,
Judgment vacated and case remanded with direction.
Barnes, P. J., and Mercier, J., concur.
Notes
International Paper and Brown were the only defendants originally named in the complaint. Other plaintiffs and defendants were subsequently added to this lawsuit, but at the time this appeal was filed, IP and Brown were the only remaining defendants.
We construe the facts and disputed testimony, and any inferences therefrom in favor of Bath as the nonmovant on summary judgment. Cowart v. Widener,
The plant is composed of numerous such "paper machines" which are actually large, football field sized buildings standing multiple stories high where the paper products are produced. These buildings contain numerous hanging lights to provide illumination. Generally speaking, it is impossible to replace or repair the hanging lights inside the machines while the machines are operational.
Due to his injuries, Bath has no memory of the day he was injured.
A condulet is a fitting resembling a pipe or box with a removable cover for access to electric conduits. An electrical conduit is the tube used to route electrical wiring in a building or structure. Merriam Webster's Online Dictionary, http://www.merriam-webster.com/dictionary/condulet, http://www.merriam-webster.com/dictionary/conduit.
Bath also contended that the wires were improperly color coded, which also misled him into thinking the wires were 110 volts. However, the record is replete with evidence that no such color coding is required in an industrial setting, so we will not dwell on this claim.
Defendants' response, as well as other filings in this case, were placed under seal pursuant to stipulation and protective order of confidential material.
In Miller , we held that it was for a jury to decide whether defendants' negligence in mislabeling a panel box was the proximate cause of plaintiff's injuries even where there was no evidence plaintiff or the other electrical workers were using their tic tracers and circumstances indicated plaintiff must have known that something was wrong because his co-worker had been shocked just minutes before on the same wire.
Bath has also presented some evidence that high humidity and the presence of pulp wood may have an effect on whether a tic tracer will work properly. We express no opinion about whether the evidence demonstrates these conditions were present at the time of the accident.
We note that in addition to undertaking a proximate cause analysis and granting summary judgment to defendants on that basis, the trial court also "re-framed" Bath's claims to state a cause of action for the tort of negligent misrepresentation and then went on to determine that defendants were also entitled to summary judgment on these re-framed claims because Bath could not establish the essential element of reasonable reliance. On appeal, Bath asserts this sua sponte re-framing of his claims was error. See OCGA § 9-11-15 (b) ; Investment Properties Co. v. Watson,
To remedy the prejudice resulting from evidence spoliation, a trial court is authorized to craft a solution that fits the facts; the court may (1) charge the jury that spoliation of evidence creates the rebuttable presumption that the evidence would have been harmful to the spoliator; (2) dismiss the case; or (3) exclude testimony about the evidence. This is not an exhaustive list of sanctions a trial court may impose; rather, the trial court has wide latitude to fashion sanctions on a case-by-case basis, considering what is appropriate and fair under the circumstances.
(Citations and punctuation omitted.) Kitchens v. Brusman,
