157 N.Y. 322 | NY | 1898
These actions were brought for the foreclosure of mechanics' liens and were consolidated by order of the court. The question presented is whether the appellant, the Salt Springs National Bank of Syracuse, as the assignee of the contractors, is entitled to a fund, which has been paid into court to abide the event of the action, as against the various parties who have filed liens for work done and materials furnished in the execution of the contract. It appears that in December, 1890, the firm of Dickison and Allen entered into a contract with the trustees of the Masonic Hall and Asylum Fund for the erection of a Masonic home near Utica. The contract price of $139,500, was to be paid in twelve installments; the last of which, being stated at the sum of $28,500, was payable when the buildings were completely finished and accepted. After the making of said contract, and in February, *326 1891, before any work had been performed under the contract, the contractors assigned, in writing, to the defendant, the Salt Springs Bank, the last payment to be made on said contract as collateral security for their existing and future indebtedness to the bank. Notice of this assignment was given to the trustees on April 28th, 1892. On May 31st, and on June 4th following, mechanics' liens were filed by the defendants Cahill and Utica Planing Mills. On the latter date the contractors made a further assignment to the Salt Springs Bank, as collateral security, of all payments then, or which might thereafter become, due and payable on said contract, including extra work. Notice of this assignment was received by the trustees on June 6th. Thereupon, the contractors, being insolvent, abandoned the work and requested the trustees to finish the buildings under the contract. Between June 5th and July 17th, 1892, other liens, aggregating over $18,000, were filed by the creditors of the contractors. At the time of the abandonment of the work, there was unpaid upon the contract, including extra work, the sum of $33,067.31. The trustees in completing the work on the buildings under the contract expended the sum of $8,478.32. Deducting from that amount certain damages for delay and the expenses of completing the buildings, the sum which would have been payable to the contractors, if they had completed their contract, and which is now to be disposed of in this action, is $23,788.49. The Salt Springs Bank, on the 6th and on the 9th of June, 1892, recovered judgments against the contractors aggregating in amount the sum of upwards of $38,000, and, in proceedings supplementary to execution, the defendant Ross was appointed receiver of the joint and several property of the contractors. It was found that the indebtedness unpaid to the bank, inclusive of interest, exceeded the sum of $25,000.
The General Term of the Supreme Court has affirmed a judgment of the trial court, under which the parties who had filed mechanics' liens were adjudged to be entitled to be paid the amount of their respective liens in preference to the Salt *327
Springs Bank. The theory upon which this conclusion has been reached is that, under the proper construction of a certain clause in the contract, it was intended by the parties thereto that persons who labored for, or furnished, materials to the contractors should be protected. The clause which received this construction reads as follows: "It is also agreed that no payment shall be made hereunder until the said parties of the second part, (meaning the contractors), shall have obtained a certificate from the clerk of Oneida county, showing that at the date of such payment, no liens or claims have been recorded or filed against said premises or building, which are then unsatisfied of record." Upon the interpretation to be given to this provision must depend the decision of the question involved in this case, whether the amount unpaid upon the contract belonged to the bank by virtue of its assignment, or whether it belongs to the lienholders to the extent of their liens. In considering that question the learned General Term discarded the suggestion of the respondents, that the amount unpaid upon the contract was not due by reason of the provision that no payment should be made until the contractors produced the county clerk's certificate that no liens were unsatisfied; and, very properly, held that if the assignment to the bank carried the right to the amount unpaid on the contract, it was the duty of the court to set aside the liens, so that the bank could procure the proper certificate and thus obtain the fund to which it was in fact entitled. The opinion held that under the Mechanics' Lien Law, (Chap. 342, Laws of 1885), the laborer, or materialman, has no preferential right to be paid out of the sum due the contractor, until he files his notice of lien. In the absence of anything to the contrary in the contract and before any notice is filed, the contractor may assign to his creditor, in payment of his debt, the whole, or any portion, of the moneys due, or to become due, under the contract and the assignee acquires a preference over a subsequent lienor. This view was based on abundant authority and is indisputable. (Brill v. Tuttle,
The reasoning in the New York city cases is not applicable to create a distinction as against the authority of Lauer v.Dunn in the decision of this case. It is not quite consistent with reason, or with the motives which usually influence parties in the making of contracts, that we should regard the clause in the present contract as inserted otherwise than for the protection of the trustees who had contracted for the construction of the buildings. The owner, in such a case, is only desirous to be protected, in his payments due under the contract, against the liens of laborers and materialmen and that purpose is accomplished by requiring the contractor, as a condition precedent to payment, to produce a certificate as to no liens being filed. Of course, the contractor is not interested in the insertion of such a provision. To infer from the presence of the clause a design to protect third parties, requires something more definite to that effect in writing, in order to make the inference reasonable and natural. To attribute to an ordinary business agreement between parties an altruistic purpose requires some support in the language. In its absence, the inference to be drawn, in the interpretation of its clauses, is subject to the usual rules which govern in the construction of legal instruments, which define the respective undertakings and obligations of the parties.
Nor does the fact that the trustees completed the buildings affect the right of the plaintiff. They elected to do so and, therefore, such part of the last payment as remained in their hands, after deducting the cost of completion, became applicable *331
to the payment of the claim of the assignee of the contractor. (Beardsley v. Cook,
Concluding, therefore, as I think we are bound to do under the authority of Lauer v. Dunn, that this clause in the contract was for the benefit of the trustees only, it follows that the assignment by the contractor to the Salt Springs Bank of the last payment upon the contract, executed upon the making of the contract, operated as an equitable assignment of the moneys remaining unpaid upon the contract, when notice of it was given to the trustees, and gave to the assignee a preference over liens subsequently filed. There is no question as to there being an indebtedness from the contractors to the bank and upon notice of the assignment to the trustees, the effect was to bind the moneys remaining unpaid upon the last installment in favor of the bank's claim. There had been an equitable assignment of the moneys, which only required for its enforcement a fund to fasten upon and a notice to the holder of the fund. The bank acquired the right of the contractors; who lost their interest in, and dominion over, the fund and its assignment was subject to no other equities than such as the trustees may have had against the contractors at the time they had notice of the assignment.
It follows from the views expressed that the judgment appealed from should be reversed and a new trial ordered, with costs to abide the event.
All concur, except O'BRIEN, J., dissenting, and MARTIN, J., not sitting.
Judgment reversed, etc. *332