239 F. 785 | 8th Cir. | 1917
A. B. Wills, W. V. Wills, and Emmett S. Wills, the plaintiffs below, brought an action against Bates county, Mo., to recover the amount which they alleged that that county owed them for excavating a part of the third section of a certain drainage ditch in that county under a contract between the county and Timothy Foo-hey & Sons, dated May 2, 1906, which, so far as it concerned the third section of the ditch, Foohey & Sons had assigned to the plaintiffs. In the course of the performance of the contract the plaintiffs encountered stone which they claimed that they were not required to remove under its terms, but the county denied this claim and on August 6, 1908, the plaintiffs and the county made an agreement that the plaintiffs should proceed to remove from the ditch all the material which they conceded they were required to take out under the contract without prejudice to the rights and claims of either party. Under this agreement the plaintiffs removed a large amount of material, but the county declined to pay them for its removal on the ground, among other things, that the original contract provided that the engineer should make estimates of the work done monthly and that 90 per cent, of his estimates should be paid when made respectively, but that no payment should be made until such estimates were made, and that the engineer had never made any estimates of the work done by the plaintiffs under the second agreement subsequent to August 6, 1908. Thereupon, on April 3, 1909, the plaintiffs commenced this action for $58,000, which they alleged that the county owed them for their work in excavating this ditch, and by an amendment to their complaint made before the last trial they alleged in substance that the engineer by a failure to exercise his honest judgment, or by fraud, or such gross mistake as implied bad faith, withheld the estimates of their work to which they were entitled. The county denied liability and the averments of the complaint charging it, upon various grounds, and also pleaded a counterclaim of $40,000 on account of excavation it alleged that it was compelled to make to complete the ditch and on account of expenses it incurred and damages it sustained by reason of the plaintiffs’ failure to complete it. At the close of the trial the jury found for the plaintiffs in the sum of $42,609.08, and for the county on its counterclaim in the sum of $11,610.70. A judgment was thereupon rendered against the county for $30,998.31. This case has been twice tried, and a more exhaustive account of its earlier course may be found in the opinion of this court on a review óf tire first trial in Bates County v. Wills et al., 190 Fed. 522, 111 C. C. A. 354.
But these statutes fail to convince of the soundness of this contention. The drainage district was originally organized under article 4 of chapter 41, which was repealed by the act of March 27, 1913, and since that act it has been reorganized under the act of March 24, 1913. The sections of the act of March 24, 1913, material to this question, provide that any drainage district in Missouri theretofore organized under any laws of that state may be reorganized under that act (section 52), that immediately after such reorganization the county clerk shall turn over to^ the secretary of the drainage district the papers and records belonging to the district and the county treasurer shall transfer the funds of the district to him (section 56), that no reorganization shall invalidate any indebtedness, liability, or contract of any nature incurred by a district under its former organization, but all such indebtedness, liability, or contract shall attach to and become the debt or liability of the new organization (section 57), and that when proceedings have been begun under the provisions of the sections repealed by the act of April 8, 1905 (Laws 1905, p. 190), they may be proceeded with and completed under the new act, that all liens, remedies, and processes for the collection of taxes provided for in the new act shall, so far as applicable, be available for the collection .of taxes levied and bonds issued under the sections repealed, and when drainage districts have been incorporated under sections repealed, and the work of drainage has been commenced or completed in whole or in part, no rights or obligations incurred by district or individual shall be nullified, invalidated, or for naught held (section 58). The act of March 27, 1913, which repeals certain sections of article 4 of chapter 41 of the Revised Statutes of Missouri 1909, under which this drainage district was originally organized, provides that the repeal of sections specified in section 1 of that act and the re-enacting of other sections in lieu of the sections repealed, and the enacting of new sections in addition thereto', shall not have the effect of invalidating, suspending,.or vitiating any drainage district heretofore organized, or any proceedings now pending in any of the courts of the state for the organization of any drainage district under article 4 of chapter 41, and that all contracts entered into, all liens established, and other obliga
When these acts were passed, the county of Bates was liable to the plaintiffs under the contract here in suit, the plaintiffs had a right of action upon this contract, and this action had been brought against the county to enforce that liability. Unless there was some constitutional enactment in these laws which deprived the plaintiffs thereof, that liability and. their right of action against the county thereon still exist. A careful reading of the entire acts has disclosed no such enactment. Thé portions of them which have been stated and the entire laws when read and considered in their entirety have convinced us that they did not take away or diminish that liability or the plaintiffs’ right of action to enforce it, but that the Legislature of Missouri intended to, and did thereby, preserve tire liability of the county to the plaintiffs upon this contract, the liability of the persons and property in the drainage district to pay the necessary taxes to discharge that liability, and the power and duty of the county to levy, collect, and pay over to the plaintiffs such necessary taxes for that purpose.
This brief review of the grant of authority to the county discloses the fact that plenary power was given to it to make the .contract for the construction of this ditch, to control, conduct, and determine every preliminary step which led up to the contract and which, if properly performed, made it valid and enabled the county to raise the funds to discharge all liability under it, to decide whether or not the improvement should be made, to decide what the true estimate of the cost of the location and construction of the ditch was, what the amounts of the damages to be paid and of the assessments to be.made and collected should be, and what amount of bonds should be issued. If the county had made its estimate of the cost of the work sufficiently large, its assessments sufficiently high, or if it had sold a sufficient amount of bonds and had applied the proceeds it could have lawfully obtained to the discharge of the contract here in suit, it would have had sufficient funds to pay its debt to the plaintiffs. The statute placed no limit upon the estimate of the cost of the improvement, and hence none upon the amount of bonds it could issue, none upon the amount of assessments it could levy and the duty and the responsibility to so estimate the cost, so fix the amount of the assessments, and so determine the amount of the bonds as to provide the funds to pay its contractors the amount lawfully due them under the contract it made with them, rested upon it alone, and as the contractors were charged with no notice, duty, or responsibility in these regards, but had the unquestioned right to rely upon the contract the county had tendered to and made with them, and the county has received and kept the benefits of plaintiffs’ performance of the contract, the county is estopped from defeating the plaintiffs’ claim and judgment against it on the ground that it failed to take the legal steps which it had the power and which it was its duty to take to provide the funds to pay it. On this ground the county is liable generally for this claim even if it now has no power to levy special assessments upon the property in the drainage district to pay it, and if a judgment is rendered against it at the next trial it should not be so limited as to be payable only from funds raised, or to be raised, by benefit assessments upon property in drainage district No. 1, Bates county, Mo.
“The burden of proving fraud on the part of Bell, the engineer, in refusing estimates to the plaintiffs, or that he in so doing did not exerase an honest judgment in so refusing, rests upon the plaintiff. To authorize a finding in plaintiffs’ favor upon this question plaintiffs are required to establish such fraud or failure to exercise an honest judgment by a preponderance or greater weight of credible evidence.”
The only reference to the burden of proof on the issue of the engineer’s fraudulent or arbitrary refusal to allow estimates found in the-charge of the court is this sentence:
“The burden of proof is upon the plaintiffs to establish their claim by a preponderance of the credible evidence in the case, and likewise the same-burden is upon the defendant to establish the damages prayed for in its counterclaim.”
The question whether the engineer withheld the monthly estimates of all work done and materials furnished by the plaintiffs after the second agreement, in the exercise of an honest judgment, or arbitrarily not through the exercise of an honest judgment, or fraudulently or through a mistake so gross as to imply fraud, was one of the most important issues, if it was not the most important, in the trial below. It is a general and salutary rule that where a charge states general rules of law governing the case, but fails to set forth a specific and crucial issue which the jury must determine, and to apply the law to that issue, either party, upon request, is entitled to additional instructions which tersely and clearly state such issue and the law applicable thereto. The refusal to submit the required instruction was in our opinion a violation of that rule and fatal to the trial of this case. Northern Central Coal Co. v. Hughes, 224 Fed. 57, 59, 139 C. C. A. 619, 621; Babbitt v. Bumpus, 73 Mich. 331, 41 N. W. 417, 419, 16 Am. St. Rep. 585; 11 Encycl. of Pl. & Pr. 298, 299; Cleveland, C., C. & St. L. Ry. Co. v. Baker, 91 Fed. 224, 227, 33 C. C. A. 468; Texas & Pac. Ry. Co. v. Short (Tex. Civ. App.) 58 S. W. 56, 58; Muldowney v. Illinois Central Ry. Co., 39 Iowa, 615, 619, 620; Parkhill v. Town of Brighton, 61 Iowa, 103, 108, 109, 15 N. W. 853; Lamar v. State, 64
The judgment below must therefore be reversed, and the case must be remanded to the District Court, with instructions to grant a new trial, and it is so ordered.
®^>For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes
(g^>For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes