26 F. 899 | U.S. Cir. Ct. | 1886
The case comes up qn a rule to show cause why a new trial should not be granted. Several grounds are stated why the rule should be made absolute, but only one has suggested any serious question. The pleadings and evidence reveal the following state of facts: A contract was entered into between the plaintiff and the defendant for the construction of a hotel at Key East, on the New Jersey coast. By the terms of the agreement the builder was to be paid, during the progress of the work, the sum of $4-0,000, as follows: On November 15, 1883, $5,000; on December 15, 1883, $10,-000; on January 15, 1884, $5,000; on February 15, 1884, $5,000; on March 15, 1884, $5,000; on May 15, 1884, $5,900; on June 15,
Under the charge of the learned circuit justice this verdict must be held to have established (1) that the work has sufficiently progressed in the months of February and March to entitle the plaintiff to the certificates; (2) that the architects fraudulently refused to give them; and (3) that the defendant failed to make the payments when the contractor demanded them, and was entitled to them under the contract, and wrongfully took the building out of his hands. Tbe jury was advised by the court, on the trial, that unless these questions of fact were found for the plaintiff he could not recover in this action.
The counsel for the defendant, on the argument, insisted that a new trial should be granted, because there was no evidence of collusion between the owner and the architects; that no proof was offered that he induced them to withhold the certificates; and, even admitting that the architects acted fraudulently, the owner was not to be prejudiced by such action unless he was in some way a party to tbe fraud. The counsel for the plaintiff, on the other hand, contended that a fraudulent refusal of the architects to furnish a certificate, when the work was sufficiently progressed to call for one, whether in collusion vith the owner or for any other cause not traceable to the influence and action of the contracto!’, justified the latter in not
We have thus presented for consideration an interesting, and, judging from the conflicting views in various cases which I have examined, I may add, unsettled, question, contracts of this character for the erection of buildings or the construction of other kinds of work arc not common. As a rule, the owner has the means to pay, but wishes to guard against loss by paying no faster than the progress of the work warranted, and the contractor is dependent upon the moneys received during the progress of the building fgr the means of carrying the undertaking on to completion. A. third party is therefore selected to determine when the payments ought to be made. In the present case the third party were the architects of the builder, and the contractor agreed to be bound by their judgment, not their uleiit but honest judgment, in regard to the payment of the several installments provided for in the contract.
Evidence was offered tending or, at least, designed to show that during the progress of the work these architects complained to the contractor that they were not receiving enough money from the owner to pay them for superintending the buildings in their construction; that they had the opportunity, under the terms of the contract, to determine whether the work should cost Mm $40,000 or $80,000; and that it was to his interest, therefore, to pursue a liberal policy towards them if he wished them to decide any matters depending on their judgment in his favor. He naturally concluded, when the architects refused their certificates in the months of 'February and March, that they wore not expressing their honest convictions, but wore pursuing a course which they imagined would bring them compensation fm. changing their judgment. There is no pretense that the builder was in collusion with them. They were not acting to benefit him, but themselves. On the other hand, the testimony indicates that he was ready and willing to pay when the architects signed the certificates that the work was sufficiently advanced to render it safe for him to do so.
Whether the work had so far progressed as to entitle the contractor to have the certificates, and whether they were withheld for a fraudulent purpose, were questions of fact which the jury has determined in favor of the plaintiff, and I quite agree with the circuit justice in his charge that fraud by the arbiters, although not in collusion with the defendant, entitles the plaintiff to recover.
The only authority in direct conflict with this view is tho statement of Addison in his valuable work on Contracts, p. *896. In discussing the subject of actions for wrongfully withholding certificates, he says, (section 861:) “But the employer is not responsible for any
“If the plaintiff had intended to rely on withholding the certificate as a wrongful act on the part of the defendant, he should have stated how it was wrongful. This is an attempt on the part of the plaintiff to take from the defendant the protection of his surveyor, and to substitute for it the opinion of a jury.”
And Milles, J., in assenting to the opinion of the chief justice, said: “Consistently with the allegations in this declaration, the only wrong the surveyor has been guilty of may be an error of judgment.”
The motion for a new trial is overruled.