The United States (government) appeals the judgment of the United States Court of Federal Claims holding the government liable and assessing just compensation for a permanent regulatory taking of plaintiffs’ (collectively Bass) rights under a lease to drill and remove gas and oil deposits, see Bass Enter. Prod. Co. v. United States,
BACKGROUND
In response to the growing public concern regarding the accumulating nuclear waste in the United States, the government pursued the creation of a permanent storage site for such waste. Selecting a location in Carlsbad, New Mexico, the government in 1977 condemned certain land and the subsurface to a depth of 6000 feet below the selected land in order to build, and to protect the integrity of, the Waste Isolation Pilot Plant (WIPP). In 1992, Congress passed the WIPP Land Withdrawal Act (LWA) to dedicate the condemned land for use in the project and to establish regulatory requirements that the Department of Energy must meet before waste can be deposited in the facility. See LWA, Pub.L. No. 102-579, 106 Stat. 4777 (1992).
The LWA, inter alia, prohibits all drilling through and underneath the site from outside of the condemned land. The Act exempts existing rights under two federal oil and gas leases
Bass holds one of the two exempted leases that underlie the property condemned in 1977. Bass submitted eight applications for permits to drill in April 1993. On August 22, 1994, the Bureau of Land Management (BLM), which is in charge of overseeing the lease, denied the permits “at this time.” The letter noted that BLM’s decision was based on EPA’s present inability to assess whether acquisition of the lease would be required. The decision was considered to be final, which permitted Bass to appeal to the Interi- or Board of Land Appeals.
Instead of appealing to the Interior Board of Land Appeals, however, Bass sued in the Court of Federal Claims alleging that the denial of the permits effected a permanent taking of portions of its lease. Ater Bass filed suit, BLM issued a supplemental decision on August 9,1995, noting that BLM was
At trial, the Court of Federal Claims held that the government had permanently taken Bass’ property interest in the lease and assessed $8,938,736 plus interest as just compensation. The court explicitly refused to consider a temporary taking theory because in its view such “analysis requires an end to the government regulation in order to measure the taking.” Bass,
DISCUSSION
On appeal from the Court of Federal Claims, we review questions of law de novo and questions of fact for clear error. See Columbia Gas Sys., Inc. v. United States,
Government regulation will effect a taking under the Fifth Amendment “where regulation denies all economically beneficial or productive use” of one’s property. See Lucas,
The government only contests the trial court’s determination that its actions constituted a permanent taking. The government argues that, instead, the government’s steps in evaluating Bass’ lease constitute at most a temporary taking because, at some definite point in the near future, the government will make a determination of whether to condemn Bass’ lease. Moreover, the government urges that any alleged taking is not permanent because Congress has established the procedures through which Bass’ lease will be condemned. It argues that a court decision at this time that the lease has been permanently taken would improperly remove that determination from the agency Congress selected to make this determination. Finally, the government argues that the Court of Federal Claims erred by using a bright-line test requiring the end of regulation and for this reason refusing to receive evidence regarding a temporary taking theory. Such a bright-line rule in the government’s view is not supported by precedent.
Bass responds that, under the terms of the LWA, the existing oil and gas drilling rights in the excepted leases “shall not be affected.” Thus Bass argues that BLM should have permitted Bass to drill and that the denial resulted in a taking of its rights. In Bass’ view, this taking is permanent because the date at which the regulation will end is unknown and at best speculative. Bass argues that the denial of the permits was just that— a denial — and not a “regulatory delay,” as characterized by BLM’s supplemental decision. Moreover, Bass contends that there is no guarantee that its drilling permits will ever be granted, even after the EPA renders its decision.
We conclude that any taking involved here is not a permanent taking. Congress has expressly established a mechanism for condemning the leases at issue if deemed necessary to ensure the integrity of the WIPP
As noted, the Court of Federal Claims declined to hear evidence on a temporary taking theory. Because such a theory was not litigated and decided by the trial court, we will not at this time decide whether the government’s activities can be held to be a temporary taking. Instead, we remand the case to the trial court for further proceedings.
In this connection, we note that the Court of Federal Claims erred in declining to consider the temporary taking issue. The court cited its prior decisions in Dufau v. United States, 22 Cl.Ch 156 (1990), and 1902 Atlantic Ltd. v. United States,
The fact that regulation has not ceased may complicate a determination of just compensation but does not justify a bright-line rule against liability. See Hendler v. United States,
CONCLUSION
We conclude that the government’s action in this case did not constitute a permanent taking of Bass’ property rights under its lease. Accordingly, the judgment of the Court of Federal Claims is reversed, and the case is remanded with instructions to the trial judge to allow the government and Bass to present additional evidence on the issue of whether the government has effected a tem
REVERSED AND REMANDED.
Notes
. The rights under these leases are limited to drilling below the 6000 feet of subsurface that had previously been condemned by the government.
. According to the government, there are two prerequisites to placing waste in the WIPP facility: EPA must both certify that the facility will comply with nuclear waste disposal regulations and also determine the fate of Bass’ lease. EPA has issued the compliance criteria for the Department of Energy, which submitted its application for certification on October 29, 1996. Under the LWA, EPA has one year to complete that evaluation. The government asserts that the decision regarding Bass’ lease should be determined around the same time as the EPA’s certification decision. The government concedes, however, that no definite date can be stated as to when the decision on Bass’ lease will be made. On October 30, 1997, the EPA issued proposed rules that conclude that acquisition of the lease at issue by the Department of Energy is not necessary. See 62 Fed.Reg. 58792, 58836 (to be codified at 40 C.F.R. pt. 194) (proposed October 30, 1997).
. Creppel v. United States,
