71 N.C. App. 700 | N.C. Ct. App. | 1984
We address first the DOT’s cross assignment of error that service of process was not timely and that the court erred in denying its motion to dismiss. The state has consented to suit on highway contract claims. N.C. Gen. Stat. § 136-29 (1981 and Cum. Supp. 1983). Such a suit is timely filed if instituted by filing of complaint and issuance of summons within six months after the final decision of the State Highway Administrator denying the claim. Id. Plaintiff filed its complaint, and summons issued, within the time set by statute. However, the summons was not properly served on the DOT’s registered process agent or the Attorney General as required by N.C. Gen. Stat. § 1A-1, Rule 4(j)(4) of the Rules of Civil Procedure (1983). After the six-month period had expired, but only 30 days after issuance of the original summons, the DOT moved to dismiss. Five days later, and 35 days after issuance of the original summons, plaintiff obtained an alias or pluries summons which was properly served in due time on the DOT. The trial court ruled that the alias summons continued the action and denied the DOT’s motion. We affirm that ruling.
G.S. § 136-29 only requires institution of the civil action, not service of process, within six months. N.C. Gen. Stat. § 1A-1, Rule 4(d) of the Rules of Civil Procedure (1983) provides that a civil action may be continued in existence against “any defendant” (emphasis added) by suing out alias summons within 90 days of the last preceding summons. No special attention to this rule appears for suits against the state, nor does this civil action appear to be any different from other civil actions. The state, once it has con
Turning now to the merits, we note that summary judgment may be granted to the non-moving party in appropriate cases. A-S-P Associates v. City of Raleigh, 38 N.C. App. 271, 247 S.E. 2d 800 (1978), rev’d on other grounds, 298 N.C. 207, 258 S.E. 2d 444 (1979). Where dispute arises only as to questions of law, summary judgment is appropriate. Kessing v. Mortgage Corp., 278 N.C. 523, 180 S.E. 2d 823 (1971). Both parties concede in their briefs that there is no dispute concerning any material fact. “When a contract is in writing and free from any ambiguity which would require resort to extrinsic evidence, or the consideration of disputed fact, the intention of the parties is a question of law. The court determines the effect* of their agreement by declaring its legal meaning.” Lane v. Scarborough, 284 N.C. 407, 200 S.E. 2d 622 (1973); see also Salvation Army v. Welfare, 63 N.C. App. 156, 303 S.E. 2d 658 (1983), disc. rev. denied, 311 N.C. 306, 317 S.E. 2d 682 (1984); 4 S. Williston, Law of Contracts § 616 (3d ed. 1961); Restatement (Second) of Contracts § 200, Comment c. (1981). Since this contract is in writing, and the facts are undisputed, its legal effect was for the court and summary judgment was appropriate.
Plaintiffs position is simple: since the contract expressly provides that there will be a 180-day inspection period after the intermediate completion date, the DOT, in adjusting the intermediate date, was required to correspondingly adjust the final contract completion date to reflect the 180-day interval. Therefore, plaintiff and not the DOT was entitled to judgment. We disagree.
The undisputed facts show that even before its request for an extension, plaintiff had accepted unequal extensions of the intermediate and final dates. In fact, the original dates agreed upon were 166 days apart, although the DOT later adjusted the final contract date to reflect the proper interval as part of its response to plaintiffs original verified claim. Plaintiff then stipulated to separate groups of “authorized time extensions” for the two contract dates. Only one of the items appears as an extension to both dates. The major item of difference, a 90-day winter weather extension, was added only to the intermediate date in adherence to the terms of the contract, which provides that upon authorized extension beyond 15 December the 90 days is added automatically to the contract time. The final contract date, however, was not extended beyond 15 December and thus did not receive the 90-day extension. Plaintiff does not object to this discrepancy, insisting instead on the inflexibility of the 180-day interval.
It is apparent however from both the plaintiffs claim and the DOT’s answers to interrogatories that adjustments to contract time reflect in large part contract, and not actual, time. By the time plaintiff submitted its claim, it had already completed the work, subject only to possible correction of pavement markings. Plaintiff was already in breach under the terms of the contract; allowing extensions served only to reduce the amount of damages assessed, not to extend time to complete the work. Even accepting plaintiffs requested extensions in toto, substantial damages would still be due. The distinction between contract time and ac
The 90-day adjustment mentioned above is one example; plaintiff received it even though it is clear from the record that work continued during the period 15 December-16 March. Plaintiff arrived at several components of its request for extension not by computing actual delays, but by calculations such as multiplying the ratio (cost overruns/contract price) times contract time to arrive at an estimated extension, or by estimating production percentage shortfalls and requesting extensions by multiplying that percentage times the days of production slowdown. Of special note in light of plaintiffs present position is its request, thus arrived at, for a 192-day interval between the intermediate and final contract dates.
The DOT’s explanations for the extensions allowed similarly reflect contract adjustments. The DOT adopted the same methodology as plaintiff in computing overrun and underrun extensions. It used a “theoretical pro rata basis" in these calculations. In addition it adjusted the final date based on percentage modifications of the arbitrary winter extension period. It is clear from all this evidence that the adjustments in contract time after breach were to properly adjust damages, not to change actual time of performance.
Plaintiff does not contend that any of the extensions granted by the DOT are unjustifiably small. Nor does it contend that any specific adjustment should have been made which was not made. Nor does it contend that by assessing liquidated damages for overruns of both the intermediate and final contract dates, the DOT unfairly doubled the damages. It admits that the erroneous interval in the original contract has been corrected. Its only contention, simply put, is that, having received a more favorable extension of the intermediate date than the final date, it is entitled to an equal adjustment to the final date. In light of the distinction between contract time and actual time discussed above, the DOT could have simply used its “theoretical pro rata” extensions and the like to add extension days equally to both dates, leaving the
Affirmed.