206 N.W. 49 | Minn. | 1925
The contractor was the Mountain Iron General Contracting Company, a copartnership. Its contracts with the county of St. Louis for the two jobs in question and the statutory bond of the surety took effect in January, 1922. The contracts were in the form then in use by the State Highway Department. Although they did not expressly require the contractor to pay for all of the labor and materials used in the work, they did obligate him "to furnish" all such materials and "perform all the work and labor" required to complete the jobs according to plans and specifications which, by reference, were made a part of the agreements. The particular specifications for the two jobs were in evidence below and are before us. The general specifications are not in evidence and we do not consider them except insofar as it is conceded that they called for the payment to the contractor, on progress estimates, of not to exceed 85 per cent of the moneys earned by him, and the retention of the remaining 15 per cent pending completion of the work to the satisfaction of the county. We assume that the contract in that respect availed itself of the unnecessary permission of section 22, chapter 323, L. 1921, under which "the county board may agree * * * to pay the contractor, on account of the contract price, an amount not exceeding eighty-five per cent of the value of the work from time to time actually completed, as shown by monthly estimates thereof, based on the contract price." Neither the contracts, so far as they are before us, nor the statute, says that this reserved percentage is for the benefit of laborers, materialmen or the contractor's surety, an omission which, so far as the latter is concerned, we consider immaterial. *160
Plaintiff, a wholesale grocer, furnished the contractor a large quantity of provisions for use not only on the jobs in question, but on others as well. It has no rights under the contractor's bond. Its only claim is under the assignment (bearing date of April 21, 1922), from the contractor of all of his earnings under the two contracts. That assignment is absolute in form, and, when this action was commenced to enforce it, there was due from the county to the contractor $5,782.24, which happened to be $2,190.64 more than the retained percentage of $3,591.60. Plaintiff's demand is for only $828.21.
Plaintiff makes no claim upon the reserved percentage, but argues that its assignment puts its title to the earnings of the assignor, over and above the reserved percentage, beyond attack by the surety. That position is based upon Dowling v. City of Seattle,
We have examined those cases with deferential care and must disagree so far as they deny the surety's equity of subrogation any application to the earnings of his principal in excess of the reserved percentage. The Washington rule seems not to have been followed to any great extent elsewhere. See annotation of Labbe v. Bernard [
To sustain that rule, a distinction must be made between two parts of the same fund, the earnings of the contractor being the *161 fund and the two otherwise indistinguishable parts consisting of the reserved percentage on the one hand and the excess on the other. In this case, the former is 15 per cent and the latter 85 per cent of the total. The distinction, if allowed, makes the surety's equity of subrogation, which in principle is applicable to all rights of the contractor, effective in practice on only 15 per cent of those rights. At least it would enable the contractor, by assignment, to deprive the surety of 85 per cent of the fund, all of which he is otherwise entitled to claim as subrogee.
That result disregards the fact that the surety's equity of subrogation attaches to the contract and the prospective earnings of the contractor thereunder at the very moment he becomes surety. The right of subrogation and its automatic equitable assignment "relate to the date of the suretyship, as against the principal and those claiming under him." McArthur v. Martin,
In this case the contracts and bonds took effect at the same time. In consequence and from that moment, the rights of the contracting parties, the builder and the county, were qualified insofar as they became subject to the surety's equity of subrogation. It follows that there was no part of the prospective earnings, whether reserved or unreserved, which the contractor could assign to a mere stranger, such as plaintiff, having no independent equity, and thereby given to the assignee a right superior to that of the surety. That is the precise holding, as we understand the decision, in Henningsen v. U.S. F. G. Co.
We attach no importance to the absence of lien rights or the fact that the county was not legally liable to laborers and materialmen or that the contract did not expressly require the contractor to pay them. There is merit in the argument that the contractor's obligation to "furnish" materials and "perform" the labor could not be fulfilled without payment for such material and labor by him. But all else aside, the bond of the surety was required by statute, G. S. 1923, § 9700, under which, without the bond, the contract itself would not have been "valid for any purpose." Complying with the conditions of its bond, the surety has performed the obligation of the principal to pay laborers and materialmen. It is thereby subrogated to the rights of its principal to collect the entire balance due from the county so far as required for its protection. Plaintiff's assignment can have no effect as against that right because, as we have seen, it relates back to the date of the suretyship and was merely matured by the surety's performance of the principal's obligation.
There is nothing in our recent decision of Standard Oil Co. v. Day,
This case is equally unaffected by Nat. Surety Co. v. Berggren,
Order affirmed.