The defendant appeals 1 from a judgment by the trial court for the plaintiffs in a suit for breach of a contract for the construction of a new house. The plaintiffs alleged that they had a written contract 2 for construction of a house to be built for them according to certain specifications on land owned by *653 the defendant. They claim numerous construction defects and seek damages for the cost of repair of these defects.
The closing took place on July 29, 1975. The plaintiffs brought suit on July 4, 1976, claiming eleven defects in the house. The trial began on May 16,1979, and on May 17, 1979, the court allowed the plaintiffs to file an amended complaint claiming a very different set of defects based upon a pretrial memorandum filed by the plaintiffs on March 29, 1979.
The trial court concluded that the plaintiffs’ suit was for a breach of contract and that the six-year statute of limitations contained in General Statutes § 52-576 applied. The court found sixteen defects proven and after itemizing the costs to correct or repair each item, awarded the plaintiffs $6470.86 in damages.
The defendant raises two principal issues on appeal: (1) that the amended complaint was barred either by the three-year statute of limitations for torts; General Statutes § 52-577; by the two-year statute of limitations for negligent damage to real property; General Statutes § 52-584; or by the three-year statute of limitations for failure to comply with the building code in the construction of a new single-family house; General Statutes § 52-563a; and (2) that the court erred in basing damages on the cost to repair the defects rather than on the diminution in value of the plaintiffs’ property. 3
The plaintiffs’ amended list of defects contained in the amended complaint of May 17, 1979, did not con
*654
stitute a new cause of action. Both the original list of defects and the amended list grew out of claimed defects in the construction of a new house. “ ‘A cause of action is that single group of facts which is claimed to have brought about an unlawful injury to the plaintiff and which entitles the plaintiff to relief.’
Bridgeport Hydraulic Co.
v.
Pearson,
“As a general rule, in awarding damages upon a breach of contract, the prevailing party is entitled to compensation which will place him in the same position he would have been in had the contract been properly performed.
Bertozzi
v.
McCarthy,
In this case, the $6470.86 cost of repair was a reasonably small amount compared to the purchase price *656 of the house and lot in the amount of $52,260. The award of such damages does not involve an unreasonable economic waste.
The judgment of the court was not clearly erroneous. Practice Book § 3060D;
Pandolphe’s Auto Parts, Inc.
v.
Manchester,
There is no error.
Notes
This appeal, originally filed it the Supreme Court, was transferred to this court. Public Acts, Spec. Sess., June, 1983, No. 83-29, § 2 (c).
Although the trial court found that there was an unwritten agreement, the plaintiff alleged that there was a written agreement. In paragraph one of the complaint, the plaintiff stated in part: “Copies of the Agreement and Specifications will be filed as Plaintiff’s Exhibit A.” No exhibits, how *653 ever, were filed with this appeal. At trial, a written purchase agreement was admitted into evidence and a “material specification” sheet was introduced also. There is testimony regarding the fact that these written documents existed. Whether or not the agreement was in writing, in any event, does not affect our decision in this matter.
The defendant also claims error in the trial court’s admission into evidence, over the defendant’s objection, of uncertified copies of portions of
*654
tive state building code. This was harmless error in the trial to the court. “Nothing in the memorandum of decision suggests that the court used the purported code to establish the standard of care owed by the defendant to the plaintiffs.”
Coburn
v.
Lenox Homes, Inc.,
