26 Mo. 102 | Mo. | 1857
delivered the opinion of the court.
Justice requires that the plaintiff should be paid the full value of his work. As he agreed to build a road in a complete and workmanlike manner for $2,300 a mile, if he failed to make the road as required by his agreement, he can only expect to receive as much as the road built by him is worth, considering that if it had been built in all respects in pursuance to the contract it would have been worth $2,300 per mile. To escape from this equitable mode of determining the controversy, the plaintiff has endeavored to set up an estimate or estimates by the engineer of the defects in the construction of the work, which he maintains are conclusive between the parties to this suit. It was certainly competent for the defendant to contract that the estimates of the deficiencies in the execution of the work should be made by an engineer, and that his estimates should be binding on the parties interested. As the plaintiff sets up this defence in order to avoid the rule dictated by natural justice for the adjustment of this dispute, he should show, by evidence that would satisfy a jury, that there was such an understanding between the parties. There is no hardship in holding the plaintiff to this proof, as in the event of his failure to make it he is still entitled to the value of the work performed by him estimated according to the terms of the contract, inasmuch as the defendant has taken and used the road.
By the contract it was agreed that the work should be completed by the first of November, 1853. In December following the contractor called on the engineer to examine and receive the work. Upon an examination of it the engineer in
Tbe parties to tbe contract might have agreed that the engineer’s report should determine the amount of deductions to be made from tbe contract price of tbe work, but in tbe absence of any such agreement we do not see bow tbe engineer could bind tbe company, as there was no power for any such purpose in the contract. Nor do we conceive that there is any thing in the record which shows that tbe company ever consented to tbe proposition made by the contractor. We do not see bow tbe presence of tbe directors in their unofficial capacity on tbe day tbe proposition was made can be considered as any evidence of their assent or the assent of tbe company to tbe proposition. They were not so organized as to do any act binding on tbe corporation; nor did they attempt so to do. Nor do we see bow the subsequent action of tbe board on tbe estimates could bind tbe company, as that action ultimately resulted in a determination not to abide by them. The proposition of tbe contractor, as stated by tbe engineer, did not specify that the estimate should be made by the engineer. Tbe fact that tbe board did, by a resolution on tbe 30th of December, 1853, call upon tbe engineer for a final estimate of tbe work done by the contractor, is scarcely
We have said that the contract did not authorize the engineer to make any arrangement with the contractor by which any deficiency in the work might be made good to the company. The instruction given by the court on this subject seems to base the binding effect of the engineer’s estimate on a supposed agreement made between him and the contractor in December, 1853, and its subsequent ratification by the board. The contract provides that the road shall be built according to the engineer’s specifications and plans, and to be governed by the engineer in all things relating to the work. A subsequent clause, after providing for monthly estimates of the work done with a view to making payment for it, stipulates that within thirty days after the road is completed an estimate of all the work done shall be made and the amount due the contractor shall be paid. These are all the provisions in the contract relative to the manner of its performance ; and it will be seen that they confer no authority on the engineer in relation to the making of estimates in the event of a misunderstanding between the parties arising out of a failure on the part of the contractor to perform his work according to the specifications annexed to the contract.
We do not well see how the instruction relative to the estimates, even admitting that the company is bound by them, can be sustained. It seems to be inconsistent with itself. The phrase “ and that the company afterwards adopted those
What has been previously stated applies to the last portion of the work. Those portions of the work which were received under resolutions of the board, and the deficiencies of which were agreed upon and estimated by the parties, can not be re-examined unless fraud in its execution is alleged and proved. If the work was fraudulently executed or its defects in any manner disguised or concealed, the plaintiff is liable for the consequences of such fraud or concealment, although he had no knowledge of it. He is responsible for ■ the good conduct of those employed by him to do the work, and, however he may stand in the -forum of conscience, he can not avoid a responsibility incurred by his servants or agents; as the injury is the same to the company as if it had been done by the principal himself. As by his employment of unworthy agents he has been the cause of the injury, it is nothing but justice that he should be responsible for it.
We do not consider that, under the circumstances, much if
The other judges concurring, the judgment will be reversed and the cause remanded.