121 Tenn. 381 | Tenn. | 1908
delivered the opinion of the Court.
The late W. H. Jackson and Howell E. Jackson, the owners of a life estate in a lot in Nashville, contracted Avith various parties for the erection on it of a large business house. The complainants, P. & M. J. Bannon, under the name and style of the Louisville Fireproof Construction Company, on the 22d of September, 1893, entered into articles of agreement with the owner to furnish and place in the building the fireproofing required.
By the first article of this agreement, the complainants undertook that they would “welt and satisfactorily erect, finish, and deliver in a true and workmanlike manner the fireproofing materials required in the erection and completion of the new stores, offices, and apartments, . . . agreeably to the plans, detailed drawings, and specifications, prepared for the said work, . . . to the satisfaction and under the direction and personal supervision of the architects. . . .”
The second article stipulated for the payment of the sum of $13,850 for this work by the owners, but with the proviso “that in each case of said payment a certificate shall be obtained from and signed by H. J. Dudley & Son, architects, to the effect the work is done in strict accordance with the drawings and specifications and that they consider the payment properly due.”
The third article provided that the owners at any time during the progress of the work might require
Article 6 is in these words:
“No new work of any description done on the premises, or any work of any kind whatsoever, shall be considered extra, unless a written order for the same shall have been given to the contractors by the architects, and their signatures obtained thereto.”
• The seventh article in substance and effect provided that the owner should not in any manner be held responsible for any loss or damage which the complainants might sustain in material or in work.at the hand of any other contractor upon this building.
The work covered by this contract was begun by the complainants soon after the date, and was finished by them in June or July, 1895, and immediately thereafter they presented an account of the amount that they claimed to be due them to W. H. Jackson, who, by the death ■ of H. E. Jackson, which occurred during the progress of the work, was the surviving owner. This account was not accompanied with a certificate from the architects, as required by the second article of the contract. It embraced items of extra
In their bill the complainants admit that the extra work embraced in their account was done without written orders from the architects of the owners; but they allege that they did it by their direction, and that they, and their representative, who was looking after the filling of their contract on this building, were assured, by H. J. Dudley, the senior of this firm of architects, that written orders ' in strict compliance with the requirement of article 6 of the contract had been or would be prepared by him and delivered to the complainants, but that the demands for these written orders were constantly evaded by him and his firm. While it is alleged in the bill that during the progress of the work H. J. Dudley uniformly recognized the obligation of the owners to pay for this work as outside the contract, and by his promise to give them orders in writing covering this extra work lulled complainants into security, yet after the completion of all the work the architects and the defendants denied the liability of' the latter for the same.
To this bill an answer was filed by W. H. Jackson, as well as the other- defendants, in which it was denied
As a reason for this long lull in the ligation, involving as it did the large amount of money claimed by these complainants to be due them, it is suggested by defendants that it is to be found in the fact that upon the cross-examination of M. J. Bannon in 1897 there was produced and submitted to him by their counsel a paper writing, which is in words and figures as follows:
*389 “Nashville, Tennessee, September 9, 1896.
“For services 'rendered we hereby acknowledge indebtedness to H. J. Dudley in the sum of $500, to be paid upon the settlement of the suit now pending, between ourselves and General Jackson and others, for fireproof construction in building corner Church and Sumner streets, Nashville, Tennessee.
“[Signed] Louisville Fireproof Construction
Company, ■
“M. J. Bannon, General Manager.”
When interrogated with regard to it, the witness denied that the instrument had been written by him. Some eight years thereafter the testimony of experts was taken as to the genuineness of this writing. One of these experts, comparing it with writings admitted to be those of M. J. Bannon, testified that it was written and signed by him. Another expert, having like advantage, after a painstaking examination, testified that the writing and signature were not those of the complainant M. J. Bannon. A number of persons who have been familiar with the handwriting of this party for many years were examined as witnesses, and with one accord they testified that they were satisfied that this instrument and the signature thereto were not written by M. J. Bannon.
It is unnecessary for us to determine whether this paper is genuine or not; but it is urged by the defendants, as strongly corroborating their insistence that it is genuine, and strongly points to the fact of corrupt
Many authorities may be found where it is held that, notwithstanding such a- limitation in a contract, yet the contractor has been permitted to recover for extra work done by agreement with the owner or upon the order of the architect with his knowledge and consent. This, however, is upon the principle that the parties to the contract may, if they see proper, waive any provision made in the interest of either. Such cases, however, cannot be invoked where the record presents such facts as we have in this. In the absence of a waiver by the owner, as above indicated (and there is no pretense of either an actual or constructive waiver by the owner, or owners, of this contract provision), we understand it to be settled, by the overwhelming weight of authority, that a recovery cannot be had for extra work in the face of a requirement such as we find in the article in question.
In 30 Am. and Eng, Ency. of Law, 1285, the rule with regard .to such a provision is thus stated: “Contracts conferring upon the architect, or the engineer, power to order extra work, frequently provide that the power shall be execised only in a certain manner, and in such case a compliance with the particular provision is necessary in order to bind the builder.” In 6 Cyc., 16, it is said that “a provision that the builder is not to execute any extra work, or make any modifications or alterations in the work mentioned in the specifications
In 2 Page on Contracts, sec. 785, it is said:
“If the contract requires a written order from the architect for extra work, no recovery can be had for extra work without such order, if the owner, or his authorized agent, have neither of them waived such a provision.”
The rule thus announced is recognized, among others, in Langley v. Rouss, supra; White v. San Rafael, etc., Railroad, 50 Cal., 417; O’Keefe v. Corporation, etc., 59 Conn., 557, 22 Atl. 325; Beers v. Wolf, 116 Mo., 179, 22 S. W., 620; Cooper v. Hawley, 60 N. J. Law, 560, 38 Atl., 964; Stuart v. Cambridge, 125 Mass., 102; Condon v. Jersey City, 43 N. J. Law, 452; Sheyer et al. v. Pinkerton Construction Co. (N. J., 1904), 59 Atl., 462.
It is insisted, however, inasmuch as by another article in the contract it was provided that the architects were made the supervisors of this building, with authority to order and direct in its" construction, that the sixth article is so modified by this other provision as that the owners were bound by an oral order, given by these architects, for this extra work. This insistence, however, is obviously unsound. The architects, by the provision thus invoked, were the agents and representatives of the owners in superintending the work within
We are unable to discover any ambiguity in this sixth article. It contains a clear restriction upon the authority of the architects, made for the protection of the owner. If it he, as insisted by the counsel of complainants, that the writing required could he as well given after the work as prior thereto, within the terms of the article, then there w'ould he no occasion for it, as the extra work might as w'ell he included in the final certificate, signed by the architect, as provided for in another part of the contract.
Without an analysis of the various cases referred to by the respective counsel in this case, we are satisfied, from an examination, that the rule, which, in the absence of a wrniver upon the part of the owner or his authorized agent, requires a strict compliance with, and enforcement of, the provision found in the sixth article
This leaves open for determination only the claim made for the balance alleged to be due on the original contract, and that for damages sustained in their materials and work at the hands of other contractors upon the building. As to the first of these, it is conceded that the defendants are entitled to large credits upon it; the amount of these, however, not being definitely shown in the record. Waiving this, however, we are .satisfied that this claim must also be rejected. By one of tiie articles in the contract, between complainants and the owners of the building, as has been seen, it was provided “that in each case of payment a certificate shall be obtained from and signed by Henry J. Dudley & Son, architects, to the effect the work is done with strict accordance with the drawings and specifications, and that they consider the payment properly due. . . .”
The authorities hold, save in certain exceptional cases, that where a provision of this sort exists, the obtaining of a certificate is a condition precedent to the maintenance of a suit by the builder against the owner for compensation. 30 Am.- and Eng. Ency. of Law, p. 1239.
As is said in 6 Cyc., p. 88: “Where the contract, either expressly or impliedly, makes a reference to arbitration, or a certificate, decision, or estimate of an architect, a condition precedent to the right of the
In the present bill no reference is made to this provision, and no excuse is offered for a failure to obtain a certificate from the architect as to the balance alleged to be due on the original contract. The answer, with other grounds for resisting recovery, distinctly avers the failure of complainants to obtain this certificate. To meet this, in the progress of the cause, and in the taking of the testimony, the complainants disclosed the paper signed by the architects, executed, not only long after the completion of the building, but some six months after the institution of this suit; and this is done by them without bringing the instrument forward, by supplemental bill or otherwise. Thus it is complainants sought in their bill a recovery for this balance upon the averments, independent of and with
To like effect will be found Gibson’s Suits in Chancery, secs. 431, 782, and 683, and 4 Elliott on Evidence, sec. 213.
This leaves open for consideration only that part of complainants’ claim for compensation for damage al
“The owners will not in any manner be responsible, or accountable, for any loss or damage that shall or may happen to the said works, or part or parts thereof, respectively, or for any of the materials, or other things used and employed in the finishing and completing said works. . . . Where there are different contractors employed on the works, each shall be responsible to the other for damage to work and person, or for loss caused by neglect, by failure to finish work at proper times.
But it is said that, on an order of the architect, W. H. Jackson paid a part of this claim, and that in doing so he waived the benefit of this provision. As these damages were inflicted by independent contractors, and, so far as this record shows, without any concert of action on the part of either of the owners, it is difficult to see upon what ground the doctrine of waiver can be invoked. The owners were not liable in view of this provision, and a promise bv them to compensate the complainants for such loss after its infliction, without more, would have been nudum pactum and unenforceable; and a fortiori a mere payment of a part of such claim cannot be regarded either as an implied promise to discharge the remainder of as a waiver of the protection of the contract provision.
It follows that the decree of the chancellor, in dismissing the hill of complainants, is affirmed.
The costs of the court below, and those incident to this appeal, will he paid by the complainants and their sureties.