Jоhn H. and Mary E. Banks, along with thirty-five other plaintiffs, seek review of final decisions of the United States Court of Federal Claims dismissing their individual complaints as barred by the statute of hmitations. See Banks et al. v. United States,
BACKGROUND
The thirty-six plaintiffs own property in Michigan along a four and one-half mile stretch of the eastern shoreline of Lake Michigan south of St. Joseph Harbor. On July 9, 1999, sixteen original plaintiffs, invoking jurisdiction under the Tucker Act, 28 U.S.C. § 1491, brought claims “based on the prohibition of the Fifth Amendment of the United States Constitution against taking of private property without just compensation.” After the denial of class certification, additional plaintiffs were named and each of the thirty-six plaintiffs filed complaints in the Court of Federal Claims.
Plaintiffs allege that the defendant, through the Army Corps of Engineers (“Corps”), constructed and maintained jetties at the St. Joseph Harbor that have interfered with the natural littoral flow of sand аnd river sediment and caused damage to the lakebed, resulting in “a gradual and continued taking of their property without just compensation, and such taking is continuing intermittently without permanent stabilization.” Plaintiffs complain that the construction and maintenance of the jetties have altered the supply of sand to the lakebed and interrupted the natural flow of sand from the north, resulting in a deficit of sand on the plaintiffs’ property. Plaintiffs further complain that the dredging and barging of river and littoral sand has permanently removed sand from the littoral ecology and resulted in the down-cutting of the shoreline south of the St. Joseph Harbor at а rate of about two feet per year.
The Corps activities impacting the St. Joseph Harbor and shoreline began in the 1830s. Banks,
In an effort to address the additional erosion caused by the jetties, the Corps proposed to mitigate the erosion pursuant to Section 111 of the River and Harbor Act of 1968, 90 Pub.L. No. 9(M83, § 111, 82 Stat. 731, 735 (1970). Section 111 authorizes the Secretary of the Army “to investigate, study, and construct projects for the prevention or mitigation of shore damages attributable to Federal navigation works.” The Corps outlined its proposal in its Final Environmental Stаtement on the Mitigation of Shore Damage Attributed to the Federal Navigation Structures at St. Joseph Harbor, Michigan, dated November, 1974 (“Proposal”). The Corps’ plan “propose[d] to mitigate shore erosion in the vicinity of St. Joseph Harbor ... that is attributable to the Federal navigation structures at the harbor. Studiеs have determined that erosion attributable to the navigation project is approximately 30% of the total erosion due to all causes.” The Proposal included the provision of feeder beaches “to nourish the areas suffering shore damage” in coordination with the annual dredging program. “[This] pеriodic nourishment plan ... would give protection to the shore erosion area affected by the navigation structures and be within the limits of the Section 111 author
The Corps’ mitigation efforts involved more than fifteen years of beаch nourishment with fine sand. Banks,
The evidence before the Court of Federal Claims included three technical reports issued by the Corps on the progress of the Corps’ mitigation efforts in St. Joseph, which collectively indicate that the erosion was permanent and irreversible. The first of three technical reports, a June 1996 Technical Report on the Geologic Effects on Behavior of Beach Fill and Shoreline Stability for Southeast Lake Michigan (“1996 Report”), however, expressed some uncertainty as to the impact of the beach nourishment program at St. Joseph. The 1996 Report stated that the mitigation program “may provide at least partial protection to the underlying glacial till along and offshore of the feeder beach and waterworks revetment section of shore. It is unclear whether thе beach nourishment is having any negative or positive impact along the 3.5-km revetment section of shoreline south of the waterworks.”
A July 1997 Technical Report on the Effectiveness of Beach Nourishment on Cohesive Shores, St. Joseph, Lake Michigan (“1997 Report”) acknowledged the irretrievable nature of the erosion while noting positive changes in the amount of sand in three zones south of St. Joseph. The 1997 Report noted “that the beach nourishment has been successful in maintaining the profile volumes in all three zones: beach/nearshore bar, offshore bar, and offshore.” Specifically with regard to the period between 1964 and 1991, the 1997 Report noted that the “trend for this period suggested that the Section 111 Program was successful in mitigating the lake bed lowering rates” for at least some of the sectors south of the harbor. A January 2000 FY-1999 Annual Report on the Section 111 Beach Nourishment Monitoring Program (“1999 Report”) emphasized the irreversible and potentially permanent nature of the erosion.
The defendant moved to dismiss for lack of jurisdiction, alleging that any takings occurred more than six years prior to plaintiffs’ complaints, and the plaintiffs’ complaints, therefore, were untimely under the statute of limitations of 28 U.S.C. § 2501. The plaintiff landowners argued that their cause of action for a continuing taking did not accrue until the late 1990s, when they learned that the observed shoreline erosion was permanent and irreversible. Banks,
Plaintiffs appealed. This court has exclusive appellate jurisdiction. 28 U.S.C. § 1295(a)(3) (2000).
DISCUSSION
A. Standard of Review
This court reviews de novo decisions of the Court of Federal Claims on matters of law and reviews for clear error findings of fact. Yancey v. United States,
B. Analysis
The issue before this court on appeal is whether the Court of Federal Claims erred in finding that the plaintiffs’ claims fell outside the applicable statute of limitations. Generally, claims against the government must be filed “within six years after such claim first accrues.” 28 U.S.C. § 2501 (2000). The accrual of a takings claim where the government leaves the taking of property to a gradual physical process occurs when the situation has “stabilized.” See Boling v. United States,
The plaintiffs argue that the permanence of any damage to their property attributable to the Corps’ activities in St. Joseph remained uncertain until the late 1990s. Plaintiffs contend that this uncertainty resulted from the potential for mitigation of any damage by the Corps’ nourishment and sand transfer plan and from the fact that the subsurface processes responsible for the erosion'of their shorelines were not understood. Plaintiffs also assert that the government concealed the existеnce of a takings claim and that the Court of Federal Claims relied on evidence that did not apply to their particular property. The defendant argues, and the Court of Federal Claims found, that by 1989, the Corps’ actions resulted in a permanent taking of which plaintiffs were on inquiry notice and the extent of the dаmage was reasonably foreseeable. Banks,
The Supreme Court, in United States v. Dickinson,
In Applegate v. United States,
Throughout the 1970s, the Corps announced different delays in the building of the sand transfer plant. In 1988, the Corps again proposed plans for a sand transfer plant. By 1992, the sand transfer plant had not yet been built, and plaintiff landowners filed suit alleging a taking. The government moved to dismiss, arguing that the suit was untimely under the six-year statute of limitations. This court held that the alleged taking did not stabilize more than six years before the filing of plaintiffs’ claims where “[t]he gradual character of the natural erosion process set in motion by the Corps, compounded by the Government’s promises of a sand transfer plant, have indeed made accrual of the landowner’s claim uncertain.” Id. at 1582.
The court emphasized the slow and gradual “continuous physical taking process” and the Corps’ promise of a sand transfer plant. “Authorized in 1962 and proposed again in 1988, the sand transfer plant would rеverse the continuous erosion process. With a sand transfer plant in place, the landowners would encounter little, if any, permanent destruction of their shoreline property.” Id. Because of these renewed promises, “the landowners did not know when or if their land would be permanently destroyed.” Id. Thus, “uncertainty has stayed accrual of the claim” where the “Government’s promises to restore the littoral flow destroyed any predictability of the extent of damage to the land.” Id. at 1583.
The Court of Federal Claims distinguished Applegate on the grounds that “two critical factors” present in Applegate are not present here: “repeated and unequivocal promises by the Corps to cure the erosion problem and a cоngressional appropriation to cover the cost of the cure.” Banks,
Applying these principles to the present cаse, the question is whether the “predictability [and permanence] of the extent of damage to the [plaintiffs’] land” was made justifiably uncertain by the Corps’ mitigation efforts. Applegate,
CONCLUSION
Because the Court of Federal Claims misapplied the standard for claim accrual under Applegate, and because plaintiffs remained uncertain as to the permanent nature of the taking until the Corps reported that the erosion was permanent and irreversible, we conclude that the claims were not time-barred. We, accordingly, reverse the judgments dismissing the cases for lack of jurisdiction and remand for further proceedings. We need not and do not consider plaintiffs’ alternative arguments regarding the timeliness of their complaints.
COSTS
Costs are taxed against the government, to the extent authorized by law.
REVERSED AND REMANDED.
