Bank v. Thermo Elemental Inc.Bank v. Thermo Elemental Inc.
After trichloroethylene (TCE)
1. Background. What follows is a brief summary of the factual background of the case and the proceedings in the Superior Court
a. Corporate history. The various entities that operated on the site present a complicated corporate history. The first tenant, JAC, occupied and used the site from the commencement of the lease in August, 1963, to some time in 1968. In that year, JAC sold some of its assets to Fisher Scientific Company, a Pennsylvania corporation (Fisher Pennsylvania). Fisher Pennsylvania assumed the lease pursuant to a written assignment, and took over manufacturing at the site. In 1981, Fisher Pennsylvania was acquired by Allied Corporation (Allied).
In 1986, AHSPC sold its Jarrell Ash scientific instrumentation manufacturing business to Thermo Jarrell Ash Corporation (TJA),
In 1988, TJA signed a lease termination agreement (1988 agreement, or agreement) with the trustees that contained an indemnification provision in favor of the trustees. In the same year, TCE was discovered on the site. In 1991, Fisher Delaware II formed a subsidiary called Instrumentation Laboratory Company (IL Co.), which was sold later that year. Before the sale, Fisher Delaware II (formerly AHSPC) assigned to IL Co. the indemnity obligation that it owed to TJA under the 1986 asset sale agreement between AHSPC and TJA.
b. Discovery of TCE and ensuing response action. In 1985, the trust’s beneficial owner, MMBT, commissioned an environmental consulting firm, Haley & Aldrich, to conduct a preliminary site investigation at the property. The investigation revealed some broken sewer lines, as well as past discharges of chemicals into the floor drains, but it did not uncover any evidence of a discharge of chemicals into the ground. In 1987, MMBT commissioned Haley & Aldrich to conduct an additional investigation of the site, and the 1988 report of that work concluded that TCE was present in groundwater at the site in concentrations above recommended levels. As the owners of the property and therefore a hable party under
The trustees believed that TJA was liable for the response costs under the indemnity provision in the 1988 agreement. Accordingly, beginning in 1989, Thomas M. Dusel, one of the trustees, kept Earl R. Lewis, then TJA’s senior vice-president and later president, informed of the progress of the response action. In a 1989 letter, TJA informed Fisher Delaware II of the contamination found at the site and invoked Fisher Delaware EEs obligation to indemnify TJA for any liability TJA had for the cleanup costs. The parties met at least twice to discuss the response costs, once in 1991 and once in 1992. In December, 1995, the trustees sent a letter setting out a formal demand for reimbursement of response costs under
c. Procedural history. The trustees’ original complaint named the eight recipients of the
The case was tried by a third Superior Court judge in two parts in 2002. In September, 2002, the trustees’ claims to recover response costs pursuant to § 4 and to recover on the indemnity provision in the 1988 agreement were tried to a jury.
In October, 2002, the same judge conducted a jury-waived trial to determine the trustees’ entitlement to attorney’s fees under
2. Breach of contract claim. The trustees appeal from the allowance of TJA’s motion for entry of judgment n.o.v. on their contract claim for indemnification under their 1988 agreement with TJA.
a. Background In March of 1986, AHSPC was the lessee under the lease with the trust. On March 28, 1986, TJA, a subsidiary of Thermo Electron, purchased AHSPC’s scientific instrument manufacturing business operated on the property. AHSPC and TJA also executed an assignment of the lease, to which the trustees assented. TJA thus assumed all the lessee’s rights, duties, and liabilities as defined in the lease.
The lease, with its commencement date of August 2, 1963, had been extended once pursuant to one of two extension options, and was set to expire on April 1, 1989, if not extended for an additional five years under the second extension option. In 1987, TJA decided to move all its manufacturing operations to Franklin, and thus no longer intended to use the property in Waltham
The agreement recites that it is made between the trustees as lessor and TJA as lessee. It further recites that the parties, or their predecessors in interest, “entered into a certain lease dated August 2,1963 (the ‘Lease’) respecting the premises now known as 590 Lincoln Street. . . (the ‘Premises’),” and that the parties wish to terminate the lease “prior to the expiration of its stated term.” The indemnification provision relating to the release of hazardous materials, set out as a separate paragraph of the agreement, reads as follows:
“3. Lessee shall save Lessor harmless and indemnify (and shall defend Lessor with counsel reasonably approved by Lessor) against any claim, loss or cost arising out of any release of hazardous materials arising out of Lessee’s use or activities of Lessee, its employees and agents on the Premises during the term of the Lease in violation of [certain Federal and State environmental protection statutes and regulations, including G. L. c. 21E]. This provision shall not impose any requirement on Lessee with respect to activities off the Premises that result in a violation of any of [the listed environmental statutes or regulations] on or under the Premises without any involvement of Lessee, its employees or agents or with respect to conditions existing on, under or around the Premises prior to the Lease commencement date.”
The trustees’ position is that this provision, read as a whole, commits TJA to indemnify the trust with respect to any release
In his decision allowing the motion, the judge concluded that the words of the agreement were unambiguous.
b. Discussion. The issue presented by the trustees’ appeal, in the first instance, is whether the indemnity provision in the agreement is ambiguous. Determining the existence of a contract ambiguity presents a question of law for the court; when a trial judge undertakes the interpretation of an unambiguous contract, the judge’s ruling is subject to plenary review on appeal. See, e.g., President & Fellows of Harvard College v. PECO Energy Co.,
In the present case, an examination of the language used in the agreement’s indemnity provision indicates the existence of an ambiguity. The indemnity provision begins by stating that “Lessee” is to hold “Lessor” harmless “against any claim, loss or cost arising out of any release of hazardous materials arising out of Lessee’s use or activities of Lessee, its employees and agents on the Premises during the term of the Lease” (emphasis supplied). Given that TJA is identified in the first paragraph of the agreement as “Lessee,” and further that TJA was lessee only from 1986 to the lease termination date in 1988, the first part of this sentence appears at first blush to limit the promised indemnification to TJA’s use of and activities on the premises during the two years of its own tenancy.
That this possibility is indeed what the sentence was intended to convey finds support in the final sentence of the indemnity provision, which explicitly carves out two exceptions from the scope of the indemnification. The first exception is for activities taking place off the leased premises resulting in the release of hazardous wastes on or under those premises; the second, and the one of particular relevance here, is for “conditions existing on, under or around the Premises prior to the Lease commencement date” (emphasis supplied). The “Lease commencement date” again appears to be a reference to August 2, 1963, the commencement date of the defined term “Lease.” As the trustees point out, if indeed the earlier sentence in the indemnity provision that concerns the “Lessee’s use or activities of the Lessee ... on the Premises” was meant to limit the indemnification to TJA’s own activities while it was the lessee, there would be no need to carve out this second exception for activities occurring prior to 1963 — more than twenty years before TJA’s tenancy began.
By considering the language against the backdrop of a portion of the trial evidence, the judge relied, at least in part, on extrinsic evidence to conclude that there was no ambiguity in the contract to begin with. But extrinsic evidence may be used as an interpretive guide only after the judge or the court determines that the contract is ambiguous on its face or as applied. See General Convention of the New Jerusalem in the U.S., Inc. v. MacKenzie,
The indemnity provision unquestionably contains language that supports an interpretation restricting the indemnity to releases
Near the end of his ruling, the judge turned briefly to a review of the sufficiency of the trial evidence. He determined that the only reasonable conclusion this evidence permitted was that the indemnity provided by the agreement covered solely TJA’s activities on the site during its two-year tenancy. If the judge’s determination was correct, then the error concerning the agreement’s non-ambiguity would be immaterial. See Suffolk Constr. Co. v. Lanco Scaffolding Co.,
Our standard for reviewing a motion for judgment n.o.v. is “whether, ‘anywhere in the evidence, from whatever source derived, any combination of circumstances could be found from which a reasonable inference could be drawn in favor of the [other party].’ ” Masingill v. EMC Corp.,
3. Trustees’ compliance with the Massachusetts Contingency
General Laws c. 21E imposes liability for the release of hazardous material on a number of parties, including the owner of the property on which the release occurs, and anyone who caused the release.
“Simply put, G. L. c. 21E was drafted in a comprehensive fashion to compel the prompt and efficient cleanup of hazardous material and to ensure that costs and damages are borne by the appropriate responsible parties. To that end, the department has promulgated extensive regulations, known collectively as the Massachusetts Contingency Plan ... for purposes of implementing, administering, and enforcing G. L. c. 21E.” Taygeta Corp. v. Varian Assocs.,
The defendants argue that the private right of action created
“Nothing in this section shall preclude assessment, containment and removal by any person threatened or damaged by such release or threat of release, provided such assessment, containment and removal is conducted in accordance with the Massachusetts contingency plan and consistently with the assessment, containment and removal actions conducted by the department.”
G. L. c. 2IE, § 4, second par. They argue that because the trustees failed to comply strictly with the requirements of the MCP, they are completely barred from recovery of response costs under § 4.
The defendants identify two respects in which the trust’s response action failed to conform to the requirements of the MCP. The first concerns an assessment report prepared for the trust in 1991 by Haley & Aldrich, entitled, “Phase II — Comprehensive Site Assessment.” The 1988 MCP required all phase II comprehensive site assessments to include a section called a “scope of work,” 310 Code Mass. Regs. § 40.545(l)(b) (1988), that was supposed to contain, among other things, a schedule for implementation of the phase II comprehensive site assessment, a sampling plan and analytical protocols, a quality assurance control plan, and a health and safety plan. See 310 Code Mass. Regs. § 40.545(2) (1988). According to the defendants, the comprehensive site assessment report prepared for the trust did not include a scope of work section, in violation of the provisions in the MCP then in effect.
The second claimed violation concerned work done at the site after the expiration of a “Waiver of Approvals.” Under the 1988 version of the MCP, in an attempt to streamline G. L. c. 21E’s cleanup process, the department began granting waivers to low-risk cleanup operations, allowing them to proceed through the multiple cleanup phases outlined in the MCP without
The defendants assert that these two violations of the MCP preclude the trust from recovering any response costs incurred after October 3, 1988, when the MCP first went into effect.
“Any person who undertakes a necessary and appropriate response action regarding the release or threat of release of oil or hazardous material shall be entitled to reimbursement from any other person liable for such release or threat of release for the reasonable costs of such response action. . . . All claims and actions for contribution, reimbursement or equitable share by persons other than the commonwealth pursuant to this paragraph, except those pending in court on the effective date of section four A shall be subject to, and brought in accordance with, the procedures set forth insection 4A .”
We have consistently and specifically identified this third paragraph of § 4 as the statutory authorization for the type of pri-
For support of their claim, the defendants cite Black v. Coastal Oil New England, Inc.,
Furthermore, although the failure of a response action to comply with the MCP might, in some circumstances, tend to show
The defendants also challenge the judge’s jury instruction on this issue. The judge instructed the jury that the trustees’ response action must be reasonable, and incurred for services that were “necessary and appropriate.” He went on to define “necessary and appropriate” as conducted “in accordance with the MCP,” and explained that “[tjhe burden is on the plaintiff to show by a preponderance of the evidence that its response action was conducted in accordance with the MCP.” The judge explained that to be conducted “in accordance” with the MCP does not require “strict compliance or perfection.” He further explained:
“An immaterial or insubstantial deviation from the MCP would not mean that the response action was not conducted in accordance with the MCP.
“The question for you on this point is whether the trust deviated in some material way from the MCP as to any part of its response action. If the answer is yes, then it will be up to you to determine what effect that should have on the trust’s claim for response costs. If you have found that there was a deviation which increased the cost of the response action, for example, because non-compliant work was done and charged for that otherwise would not have been done and charged for, or because additional work was required to correct any non-compliant portion of the trust action — those are just examples — then any suchadditional costs should be deducted from the trust’s claim for response costs because they were not pursuant to a necessary and appropriate response action.”
The defendants argue that this instruction allowed the trustees to recover for even material deviations from the MCP. The defendants misinterpret the instruction. The import of the judge’s words were that over-all, substantial compliance with the MCP was required in order to demonstrate that the trust had conducted a response action that was “in accordance with the MCP.” This instruction expresses accurately the thrust of the authorizing language in the third paragraph of § 4, and if anything, is more favorable to the defendants than the statute required, insofar as it expressly defines a “necessary and appropriate” response action in terms of substantial compliance with the MCP, rather than presenting such compliance as one, albeit highly significant, criterion to consider. There was no error.
4. Attorney’s fees as response costs. The defendants also challenge the allowance, as a type of permissible response costs, of fees paid by the trust to its attorneys for work on the response action. Under
The jury awarded the trustees $90,214 for work undertaken by their attorneys, Hill & Barlow, to manage the response action. The judge instructed the jury that “[sjervices provided by a lawyer in connection with an environmental case may or may not qualify as response costs. To be recoverable as response costs, attorney’s fees must be for services that are closely tied to the response action . . . .”
This instruction accurately reflected the requirements of G. L. c. 21E. There is nothing in the statute to exclude otherwise
The United States Supreme Court has interpreted the analogous provision in the Federal Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA),
The defendants argue that, according to this court’s decision in Sanitoy, Inc. v. Ilco Unican Corp.,
The defendants also object to the specific items represented on Hill & Barlow’s billing records, arguing that even if some attorney’s fees might be recoverable as response costs, the objected-to fees were clearly neither necessary nor appropriate, and the jury’s conclusion to the contrary requires reversal.
An award of prejudgment interest is made “so that a person wrongfully deprived of the use of money” is “made whole for his loss.” See Sterilite Corp. v. Continental Cas. Co.,
The facts of this case present a similar dilemma. An application of the plain language of the statute would allow interest to accrue “from the date of commencement of the action” or “from the date of the breach,”
6. The defendants’ litigation fees. The defendants challenge the judge’s denial of attorney’s fee awards to any of them under
“If the court finds that (1) the plaintiff did not participate in negotiations or dispute resolution in good faith; (2) the plaintiff had no reasonable basis for asserting that the defendant was liable, or (3) the plaintiff’s position with respect to the amount of the defendant’s liability pursuant to the provisions of this chapter was unreasonable, it shall award litigation costs and reasonable attorneys’ fees to the defendant.”
In their response to the trustees’
Unquestionably, the defendants’ claim to recover litigation costs and attorney’s fees represents a claim for relief in the form of a monetary award. Under the Massachusetts Rules of Civil Procedure, a claim for relief is to be set forth in a pleading that contains “(1) a short and plain statement of the claim showing that the pleader is entitled to relief, and (2) a demand for judgment for the relief to which he deems himself entitled.”
The defendants argue that the denial of their
We fail to understand the significance of the fact that
Moreover, there is a particular reason for requiring a party seeking an award of litigation costs and attorney’s fees under § 4A — whether
The defendants also contend that by permitting the trustees to avoid a fee award against them based only on a “procedural technicality,” the judge contravened the section’s underlying legislative intent to sanction “opprobrious” conduct on the part of response action plaintiffs. The argument mixes apples and oranges. There is little doubt that
7. The litigation fees. The trust was awarded litigation fees
Fisher Delaware II argues
The jury’s findings in this case established that the trustees conducted a necessary and appropriate response action in accordance with the MCP, and that the trust was not responsible for causing the contamination. None of the alleged defects cited by Fisher Delaware II would result in a violation of the two remaining prerequisites of notice and good faith negotiation. The allegedly false statement cited by Fisher Delaware II, found in the trustees’
8. Jurisdiction. The defendants argue that the trustees’ failure
9. Environmental report. The defendants’ final argument is that an environmental report commissioned by the trust was erroneously admitted in evidence over the defendants’ objections. The report contained a speculative assertion that an above-ground storage tank was the probable source of the TCE contamination. Fisher Delaware II contends that the report suggested that it was responsible for the contamination because it was Fisher Delaware II (and its corporate predecessors) that operated the aboveground storage tank. According to this argument, the report was highly prejudicial, should not have been admitted for any purpose, and its admission was an error requiring a new trial. “Relevant evidence is admissible unless unduly prejudicial, and, ‘[i]n weighing the probative value of evidence against any prejudicial effect it might have on a jury, we afford trial judges great latitude and discretion, and we uphold a judge’s decision in this area unless it is palpably wrong.’ ” Commonwealth v. Arroyo,
10. Conclusion. That portion of the amended judgment relating to the trustees’ claims under G. L. c. 2IE, §§ 4 and 15, is affirmed. The entry of judgment n.o.v. on the trustees’ contract claim is vacated and the case is remanded for the entry of a judgment based on the jury’s verdict on that claim.
So ordered.
Notes
Trichloroethylene (TCE) is a type of industrial solvent used to clean and degrease metals and glass. The parties do not dispute that TCE qualifies as a “[hjazardous material” as defined in
We therefore vacate the trial judge’s allowance of the motion for judgment notwithstanding the verdict on the contract claim.
We acknowledge the receipt of amicus briefs filed by the Commonwealth, the LSP Association, Inc., and the Real Estate Bar Association for Massachusetts and the Abstract Club.
The jury trial in this case lasted three weeks, followed by a shorter trial on nonjury claims before the same trial judge. Thereafter, the parties filed extensive posttrial motions. The record reflects the very careful, thorough, and thought-
After a 1985 merger between Allied Corporation and the Signal Companies, Allied-Signal, Inc., was formed. We shall refer to both companies as “Allied.”
Thermo Jarrell Ash Corporation (TJA), the last lessee under the August 2,
The letter was sent to both Allied Corp. and Allied-Signal, Inc.
IL Co. was not itself a recipient of this demand letter, but was aware of its indemnification obligations to several of the recipients.
JAC had long since been dissolved and did not respond to the demand letter.
The trustees did not appeal from this decision. Accordingly, there is no claim before us concerning response costs paid before July 1, 1989, or relating to alleged property damage under
The
The amounts awarded by the jury against Fisher Delaware II under § 4
As mentioned, at the close of the trustees’ evidence at trial, the judge directed a verdict in favor of TJA on the trustees’ claim that TJA was responsible for any release of TCE. The trustees have not appealed from this determination.
The judge acknowledged that in reaching this decision he came to a result contrary to one reached before trial, when another judge had ruled that the language of the agreement’s indemnification provision was ambiguous, and had accordingly denied the parties’ cross motions for summary judgment on the contract claim.
See, however, note 19, infra.
Moreover, it is at least possible to read the language of the indemnity provision in a way that does restrict the meaning of the word “Lessee” to TJA, but nonetheless supports the view that the proffered indemnity covers contamination caused by earlier lessees. The indemnity provision states that the obligation to indemnify applies to any hazardous material release “arising out of Lessee’s use or activities of Lessee, its employees and agents on the Premises during the term of the Lease” (emphasis supplied). It also states that no requirement to indemnify is imposed “on Lessee with respect to activities off the Premises that result in [a hazardous material release] without any involvement of Lessee, its employees or agents” (emphasis supplied). These are the only two references to the “Lessee, its employees or agents” — as opposed to simply the “Lessee” — in the entire agreement. In light of the series of interconnected corporate mergers, asset purchases, and name changes among the various lessees of the property, and evidence that to some extent, the employees on the site did not change despite the corporate changes, it would not be unreasonable to construe the phrase “Lessee, its employees and agents” as referring to TJA and its predecessor lessees, rather than just TJA. Given such a reading, all the words of the indemnity provision can be read consistently to mean that TJA, as the “Lessee” in the agreement, is obligated to indemnify the trustees for releases arising from its own use of the property and also from activities conducted by the earlier lessees. Such a reading does “no violence to the language” of the agreement as a whole. Chapman v. Katz,
At trial, Lewis’s deposition testimony was read to the jury; Lewis did not
For example, there was evidence that when they were negotiating the terms to govern the agreement, Dusel and Lewis both understood that the 1963 lease contained an indemnification provision covering releases by all lessees. The jury also heard from Dusel that he discussed a draft of the agreement with the trustees’ attorney Taylor, and Dusel understood that the final version of the agreement, the one he signed, did indeed provide indemnification for releases going back to the beginning of the lease: the language “during the term of the Lease” that appeared in the indemnification provision of the agreement meant just that. Lewis, on the other hand, testified that he did not remember reviewing or discussing with Lambert any written drafts of the agreement or the final written version before he signed it. There was also evidence — again proffered by both Dusel and Lewis — that for the period of time extending from the signing of the agreement in the spring of 1988 up until 1992 (when a different lawyer for TJA became involved), TJA responded to the trustees’ requests for payment of remediation costs not by denying any responsibility, but instead by referring to the indemnification that AHSPC had provided to TJA — in other words, in a manner consistent with Lewis’ position that TJA could offer a broad indemnity to the trastees because TJA was in turn indemnified by AHSPC. In seeking to interpret the scope of the agreement’s indemnity provision, the jury were entitled to consider this evidence concerning the parties’ conduct following execution of the agreement. See, e.g., Keating v. Stadium Mgt.Corp.,
This language is quoted from the Massachusetts Contingency Plan (MCP) in effect after 1993. The MCP was substantially revised in 1993. See 310 Code Mass. Regs. § 40.0005 (1995). One of the trust’s alleged violations of the MCP occurred before 1993 and one occurred after. The purpose of the earlier version of the MCP was limited to establishing “requirements and procedures for the discovery, notification, assessment of, and response to, releases and threats of release of oil or hazardous materials,” and to identifying the “roles and responsibilities” of potentially responsible parties, govern
In this respect, § 4 differs from G. L. c. 21E’s Federal analogue, the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), which specifically allows a private party to recover response costs incurred that are “consistent with the national contingency plan.”
It bears noting that § 4’s second paragraph itself does not use the terms “strict compliance” or “exact compliance” with the MCR
As the trustees and the Commonwealth point out, acceptance of the defendants’ interpretation of § 4 could serve to discourage private parties from undertaking cleanup actions on their own in response to hazardous material contamination, because any mistake or misstep in meeting the MCP’s requirements, no matter how insignificant or immaterial, would preclude the parties from obtaining any reimbursement or cost-sharing from other private parties who were responsible in whole or in part for the contamination. As noted, two of the purposes of G. L. c. 21E are to “compel the prompt and efficient
For example, the defendants do not cite any deficiencies or expenses in the response action that would have been prevented if a scope of work had been prepared. And as to the “waiver” violation, it is significant that even after the department learned of this violation, the department chose to do nothing about it.
CERCLA includes a somewhat broader definition of a “response action,” including not only removal and remedial action, but also “enforcement activities related thereto.”
The defendants further argue that the records were improperly admitted hearsay because, having been redacted in preparation for litigation, they were not created in the ordinary course of business and therefore failed to conform to the requirements of the business records exception. See
Richard Rudman, the Hill & Barlow attorney primarily responsible for providing the legal response action services at issue, testified at length concerning the response-related work he performed, and the defendants had an opportunity to question him about the specific bills they now challenge.
This method of calculating interest is equally applicable to the trustees’ contract claim.
In this connection, the judge noted that while he had heard evidence on the merits of the defendants’
The trustees’ claim for attorney’s fees and costs under
In a related vein, we have held that where a party seeks the award of appellate attorney’s fees and costs in a case where a statute has authorized the award of such fees and costs to the prevailing party at the trial level, the party seeking the fees must include the request in the appellate brief. Fabre v. Walton,
Thus,
As has been stated, the judge denied TJA’s
The defendants’ final point about their
The judge also awarded litigation costs and attorney’s fees to the trust under
Because Fisher Delaware II was the only party found responsible under
While the jury eventually awarded the trustees $719,484.20 on the § 4 claim, that amount did not include interest or litigation fees, and $600,000 of which was to be paid over time without security. With interest, the jury award totaled $1,245,887.80, with fees and costs added in, the award is obviously much higher. (See note 41, infra.)
There is no question raised about the amount of fees awarded to the trust: the parties commendably stipulated to the reasonableness of the amount, while reserving arguments about the propriety of making an award. The fees awarded to the trustees were $1,100,000.
The trustees have requested an award of attorney’s fees and costs related to this appeal, pursuant to