91 N.Y. 32 | NY | 1883
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *34 [EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *36 The plaintiff in this action claims to recover the value of a portion of a cargo of wheat which the defendants, as common carriers, transported from Toledo to the city of Oswego, and which it is claimed they never delivered to the plaintiff, who was the consignee of the wheat. There is no doubt as to the fact that the plaintiff never received a portion of the wheat, and the principal question presented upon this appeal relates to the liability of the defendants for its non-delivery. It appeared upon the trial, and by the finding of the referee, *37 that Cheney Ames, one of the defendants, was one of the owners of the vessel upon which the wheat was transported, and also a member of the firm of Cheney Ames Co., who were proprietors of the elevator and warehouse at which the schooner was moored; and that prior to the 23d of March, 1876, said Cheney Ames Co. had taken and removed from the schooner the balance of the wheat remaining on board, and took and converted it to their own use, without the knowledge or consent of the plaintiff. On the last-named day plaintiff's cashier went on board of the schooner and demanded the wheat of the master, who then and there informed him that there was no wheat on board to answer the demand, and that, therefore, he was unable to deliver it.
The referee, after various findings of fact, found as a conclusion of law that the plaintiff waived a formal notice and readiness to deliver by the master, by consenting to treat with Cheney Ames instead of the master in relation to the delivery of the said wheat under a bill of lading. He also held that the vessel was ready or in a condition to be unloaded, after it was lightened and had reached the wharf where it was moored, as the plaintiff well knew by communication with the said Cheney Ames, and that by its consent to have the wheat remain longer on board, the plaintiff released the defendants, the Doyles, from their liability, under the bill of lading, as common carriers; that Ames, even if he had contracted to store the wheat in said vessel after its arrival, could not bind his co-owners by such contract without their consent or authority, and there being no proof of any agreement or consent by such co-owners that the wheat might remain on board the vessel after the arrival at the place of destination they are not liable to the plaintiff as warehousemen. The opinion of the General Term holds that there was a waiver by the plaintiff of notice of readiness to unload and deliver the wheat, and the plaintiff having had notice from Ames of the arrival of the vessel, and its action being such as to imply its assent that the cargo might remain on the vessel, the liability of the defendants as carriers was terminated and the wheat remained on board the schooner *38 for the accommodation of Cheney Ames Co., with the knowledge and assent of the plaintiff, and there being no agreement on the part of the defendants, or either of them, to store the wheat, and none on the part of the plaintiff to pay for storage or demurrage, the Doyles, not being parties to the understanding between the plaintiff and Ames, in pursuance of which the wheat remained on the vessel, are not liable for the loss.
By the contract contained in the bill of lading the master was bound to deliver the wheat to the plaintiff unless prevented by the dangers that were excepted, namely, dangers of navigation, fire and collision. He failed to deliver the wheat as required, and unless some lawful cause is shown his principal should be held liable to the plaintiff for the damage sustained by reason of non-delivery. A carrier in possession of goods intrusted to his charge remains liable as insurer until a delivery in fact, or until he has performed some act which indicates his purpose to terminate his relation as carrier. (Goold v. Chapin,
The appellant's counsel claims that the conclusion of the referee, that formal notice was waived, was not warranted by the evidence. There is testimony showing that Cheney Ames informed the cashier of the plaintiff that the vessel had arrived, and that the cashier inquired of him what he should do with the wheat, and Ames replied that the vessel would have to lighten to get up the river and was not ready to unload yet, and that the cashier then said, if she did not unload immediately she would require a harbor insurance, that he wanted to take care of the wheat, to which Ames replied, that she would have to lighten at one of the elevators below to come up to one of their elevators, and that the cashier told him to bring the warehouse receipts to him. The cashier received *39 the warehouse receipts for the grain, which was taken out in lighters, from Cheney Ames, and made no objection and gave no direction except requiring insurance. He also received a certificate of insurance running to December 30th following and he gave to Ames orders on the schooner for three parcels of grain sold, which were paid for to him. He also had knowledge of the arrival of the schooner. Cheney Ames testified that the cashier acquiesced in the wheat remaining on the vessel and it remained there at his request. There is no direct proof of an agreement to waive notice of a readiness to deliver, but it cannot perhaps be insisted that there was no evidence from which it might be inferred that there was such waiver, and that the referee was not justified in his finding in this respect.
But, even if there was a waiver of such notice, we do not think that that fact is to control the disposition of the case. The testimony of Cheney Ames shows that when the agreement was made for the advancement of the money to purchase the wheat it was understood that it could lay in the schooner and be paid for as it was taken out. This agreement was carried out in part by the payment for such portion of the wheat as was sold and disposed of at the time when delivery was made, and under the arrangement, as well as under the legal obligation which was assumed by the owners of the schooner that the wheat should not be disposed of without being paid for. This was an important element in the contract for the security of the advancement made by the plaintiff, and it is fair to assume, in view of the fact that the bill of lading was held by the plaintiff as a part of its security, that but for this the advancement would not have been made.
The referee has found, as a conclusion of fact, that the schooner, with the balance of the wheat, was moored at the instance and request of Cheney Ames Co., for their accommodation, to enable them to sell and market the same subject to the lien of the plaintiff and its order, before it could be removed and delivered to the purchaser, and the plaintiff and Cheney Ames Co. both understood and assented that the *40 wheat might remain in the vessel for that purpose, although there was no binding contract to allow it to remain for any length of time, or any agreement to pay the owners of the schooner compensation for the storage of the wheat until it could be discharged; but we are unable to discover any direct evidence which establishes an arrangement of this character between the plaintiff and Cheney Ames. The only testimony bearing on the subject is to the effect that Cheney Ames made the arrangement, and it does not appear that he acted directly for the firm of Cheney Ames Co., and that he did not act for the owners of the schooner. In the absence of such direct proof, there is no ground for claiming that there was proof to sustain the finding of the referee in this respect. The most that can be claimed is that plaintiff acquiesced in the vessel remaining where she was moored, and this fact does not establish that the wheat remained on the vessel under the charge or direction of Cheney Ames Co., or that they had control of it. It may also be remarked that the conclusion of the referee, that the vessel was ready or in a condition to unload after it was lightened and had reached the wharf, and the plaintiff knew it, is not material; and we think that the conclusion that the plaintiff released the defendants Doyles by its consent that the wheat should remain on board the schooner is not warranted and was erroneous.
Even if the wheat was ready or in a condition to be unloaded and the plaintiff knew it, it does not follow that the carrier was released from his duty and liability to moor the vessel at the wharf and to deliver or offer to deliver the cargo to the consignee. A tacit consent that the wheat should remain on board after the arrival of the vessel in port did not discharge the original undertaking, as it was proved on the trial that the wheat was to be paid for when delivered. Such being the contract, defendants have no right to dispose of the wheat although they had offered to deliver the same to the plaintiff, even if the plaintiff was in fault by neglecting or refusing to receive it. The carrier to relieve himself from liability was authorized to deposit the wheat in some suitable warehouse, if *41
any could be found, or by making some equivalent disposition of it for the owner, and his responsibility as carrier continued until this was done. (Hathorn v. Ely,
The other questions presented by the respondents' counsel have been considered and examined, and we are unable to find any ground upon which the judgment can be upheld, it should, therefore, be reversed and a new trial granted, costs to abide the event.
All concur, except RAPALLO, J., absent.
Judgment reversed.