Lead Opinion
Judge WESLEY dissents in'a separate opinion.
In this breach-of-contract action, plaintiff Bank of New York Mellon Trust Company, N.A. (“BNY” or “Trustee”) appeals an award of summary judgment in favor of defendant Morgan Stanley Mortgage Capital, Inc. (“Morgan Stanley”) entered, on June 17,2014, in the United States District Court for the Southern District of New York (Colleen McMahon, Judge). BNY argues that the.district court erred in concluding, as a matter of law, that Morgan Stanley was not contractually, obliged to repurchase a mortgage loan allegedly issued in breach of a contract .representation because (1) the Trustee’s duty to give “notice to cure” within three business days of becoming aware of a material breach was a condition precedent to the seller’s repurchase obligation, Bank of N.Y. Mellon Tr. Co. v. Morgan Stanley Mortg. Capital, Inc., No. 11 Civ. 0505(CM)(GWG) (“BNY /”), 2013 WL 3146824 (S.D.N.Y. June 19, 2013); and (2) that condition was not per-forméd within the specified three days, but two to four weeks later, see Bank of N.Y. Mellon Tr. Co. v. Morgan Stanley Mortg. Capital, Inc., No. 11 Civ. 0505(CM)(GWG) (“BNY II”), 2014 WL 2745011 (S.D.N.Y. June 16, 2014).
For reasons explained herein, we conclude that the contract at issue did not require notice to cure as a condition precedent to Morgan Stanley remedying breach.
On review of the record, we further conclude that the notice of breach and request for cure in this case cannot be held untimely as a matter of law, particularly when reviewed for substantial performance. Accordingly, we vacate the award of summary judgment in favor of Morgan Stanley, and we remand the' case to the district court for further proceedings consistent with this opinion.
I. Background
A. The Mortgage' Loan Purchase Agreement
The contract at issue is a May 1, 2007 Mortgage Loan Purchase Agreement (“MLPA”), pertaining to an. $81 million mortgage loan that Morgan Stanley issued to City View Center, LLC (the “City View Loan”) on December 29, 2006, for the purchase of a retail center in Garfield Heights, Ohio (the “City View Property”). Pursuant to the MLPA, Morgan Stanley sold the City View Loan to Morgan Stanley Capital I, Inc., which, pursuant to a Pooling and Servicing Agreement..(“PSA”) of the same date, placed the City View Loan into Morgan Stanley Capital I Trust 20Ó7-IQ14 (the “Trust”), then valued at nearly five billion dollars. The Trust was later securitized and sold to investors.
The PSA designated BNY as trustee of the Trust and, thus, the entity entitled to enforce various' agreements, including the MLPA here at issue. The PSA also designated Wells Fargo National Association (‘Wells Fargo”) as a Master Servicer, responsible for administering the Trust’s loans and collecting payments, and Center-line Servicing Inc. (“Centerline”) as Special Servicer, responsible for servicing any defaulted loans.
B. City Vieio’s Default on the Loan
On September 9, 2008, Master Servicer Wells Fargo informed Special Servicer Centerline that the City View Loan would likely go into default within 60 days because (1) City View had ,received numerous notices of lease default from Wal-Mart, the anchor tenant of the City View Property, based on methane gas intrusion into the store; (2) the' Ohio Attorney General had filed a complaint against City View (and others) for- regulatory violations on the City View Property, including the failure to control the migration of combustible gases; and (3) the Ohio Agency for Toxic Substances & Disease Registry had determined that conditions at the City View
C. Notice of Breach and Request for . , Cure
Upon transfer, Centerline’s Director of Special Servicing, Jennifer Wilkicki, began investigating Morgan Stanley’s possible breach of the MLPA.
Three days later, on February 19, 2009, Unell advised Wilkicki that she had reviewed pertinent materials and . agreed “that there [was] evidence that [Morgan Stanley] knew that there were material environmental conditions or circumstances affecting the Property that were not disclosed in the Phase I report.” Id. at 1266. Unell asked Wilkicki to call her “to discuss further,” concluding, “I think that the breach notice should be sent.” Id.
A breach notice was sent approximately one month later, on March 18, 2009. In the interim, Wilkicki secured an appraisal, which on February 27, 2009, valued the City View Property at $22.3 million, a steep decline from the $103.4 million appraisal of .two years earlier. Another appraisal, confirming the $22.3 million valuation, was received on March 13,2009.
Between receipt of these two appraisals, on March 3, 2009, Wilkicki sent Unell a more formally worded draft breach notice and ■ request. for cure, and solicited her comments. On March 13, Unell emailed Wilkicki her edits to the draft notice. The next day, Wilkicki sent the.revised draft to her supervisor, Chris Crouch, who approved it on March 16 and directed Wilk-icki to send it on to Centerline’s President, Paul Smyth, “fór go ahead to release,” Id. at 1347. After receiving Smyth’s ¿uthori-zation for release, Wilkicki sent- Morgan Stanley a formal notice of breach and request for cure» on. March 18, 2009. Tracking language in the MLPA and PSA,, the notice stated that if the material. breach were .not corrected or cured within 90 days of receipt, Morgan Stanley would be contractually obligated to repurchase or to replace the City View Loan. It is, in -fact, undisputed on this appeal that the breach was one that could-not be-cured.. :
Approximately two months later, by letter dated May 11, 2009, Morgan- Stanley replied that it disagreed with Centerline’s “characterization-of-the facts and circumstances” and “intended] to vigorously defend its underwriting and disclosures made in the PSA and the Mortgage Loan.” Id. at 1093. Thus, it did not repurchase or replace the.City View Loan. .,
On September 24, 2010, the Special Ser-vicer sent Morgan ’Stanley a “Second and Supplemental Notification.- of Material Breach.” In addition to alleging. more facts to support the earlier noticed breach of Representation 12, it asserted a breach of Representation 27, the MLPA’s No Material Default Representation.
D, District Court Proceedings
On January 25, 2011, ■ BNY filed this lawsuit against Morgan Stanley for breach of the MLPA. Following amended pleadings and discovery, both parties moved for summary judgment: Qn June 19, 2013, the district court granted Morgan Stanley partial summary' judgment on BNY’s breach claim as to the No Material Default Representation provision.
After discovery closed, the district court determined, as a. matter of law, "that BNY’s “Special Servicer became aware .of a material breach of the Environmental Representation more than three business days before March 18, 2009,” making its breach notice on that date untimely, thereby failing to satisfy that condition precedent to Morgan Stanley’s repurchase obligation. BNY II, 2014 WL 2745011, at *7-9. Accordingly, on June 17; -2014, the district court entered.summary judgment in favor of Morgan Stanley on- the Environmental Representation breach claim.
This timely appeal followed.
II.. Discussion
This appeal. presents two questions for de novo review: (1) whether the MLPA’s request-for-cure obligation- is a condition precedent that must be timely performed by the Servicer before Morgan Stanley has any obligation , to cure or to repurchase a noticed defective loan; - and (2) whether it can be determined.- as a matter of law on the existing record that the request for cure in this case was untimely. See Lynch v. City of New York, 737 F.3d 150, 156 (2d Cir.2013) (reviewing award of summary judgment de novo and upholding only if “there is no genuine issue of material fact” qnd “moving party is entitled to judgment as a matter of law”); Phillips v. Audio Active Ltd., 494 F.3d 378, 384 (2d Cir.2007) (interpreting contract de novo). We answer both questions , in the negative and, therefore, vacate the award of summary judgment in favor of Morgan Stanley and remand the case to the district court for further proceedings consistent with 'this opinion'.
A. MLPA Section 5’s Remedies Provision ■ ■
The district court derived the condition precedent it identified — an obligation to
[I]f there is a breach of any of the representations and warranties required to be made by the Seller regarding the characteristics of the Mortgage Loans and/or the related Mortgaged Properties ... and ... [such] breach, either (i) materially and adversely affects the interests of the- holders of the Certificates in the related Mortgage Loan, or (ii) both (A) the ... breach materially and adversely affects the value of the Mortgage Loan and (B) the Mortgage Loan is a Specially Serviced Mortgage Loan ..., [1] the party discovering such ... Material Breach shall promptly notify, in writing, the other party..[2] Promptly (but in any event within three Business Days) upon becoming aware of any such ... Material Breach, the Master Servicer shall, and the Special Servi-cer may, request that the Seller, not later than 90 days from the Seller’s receipt of the notice of siach ... Material Breach, cure such ... ' Material Breach____
[3], The Seller hereby covenants and agrees that, if any such ... Material Breach cannot be corrected or cured in all material aspects within the above cure period[ ], the Seller shall, on or before the termination of such cure period!], either (i) repurchase the affected Mortgage Loan ... from the Purchaser or its assignee at the Purchase Price as defined in the Pooling and Servicing Agreement, or (ii) if within the two-year period commencing on the Closing Date, at its option replace, without recourse, any Mortgage Loan ... to which such defect relates with a Qualifying Substitute Mortgage Loan. If such ... Material Breach would cause the Mortgage Loan to be other than a “qualified mortgage” (as"defined in the Code), then notwithstanding the previous sentence, such repurchase or substitution, must occur, within 90 days from the earlier of the date the.Seller discovered or was notified of the breach or defect.
J.A. 454-55 (emphasis added).
In fact, the quoted language identifies three obligations (corresponding to the inserted highlighted numbers). First, a notice-of-breach obligation, which requires any party — whether the Trustee, Master Servicer, Special Servicer, or even the Seller — “discovering” a material breach of representation promptly to notify the other party of its discovery of such breach. Second, a request-for-cure obligation, which requires the Master Servicer, and permits the Special Servicer, promptly, but in any event within three business days of “becoming aware” of the material breach, to request that the Seller cure' breach within 90 days of 'the receipt of notice. Third, a cure-or-repurchase obligation, which requires the Seller either (a) to cure the material breach within 90 days of receiving notice, or (b) if the breach cannot be cured, to repurchase or to replace the defective mortgage loan.
As this parsing demonstrates, Section 5 nowhere references “notice to cure.” We understand the district court to have used
B. Bequest for Cure Is Not a" Condition Precedent to Cure or Repurchase
Under New York law, which controls our construction of the MLPA, a condition precedent is “an act or event, other than a lapse of time, which, unless the condition is excused, must occur before a duty to perform a promise in the agreement arises.” Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co., 86 N.Y.2d 685, 690, 636 N.Y.S.2d 734, 737, 660 N.E.2d 415 (1995) (internal quotation marks omitted). Conditions precedent are not readily assumed. While specific, talis-manic. words are not required, the law nevertheless demands that conditions precedent be “ ‘expressed in unmistakable language.’ ” Id. at 691, 636 NY.S.2d at 737, 660 N.E.2d 415 (quoting Restatement (Second) of Contracts § 229, cmt. a, at 185). Thus, “[i]n determining whether a particular agreement makes an event a condition[,] .courts will interpret doubtful language as embodying a promise or constructive condition rather than an express condition.” Id.; see Unigard Sec. Ins. Co. v. N. River Ins. Co., 79 N.Y.2d 576, 581, 584 N.Y.S.2d 290, 292, 594 N.E.2d 571 (1992); see also Israel v. Chabra, 537 F.3d 86, 93 (2d Cir.2008) (citing Oppenheimer in acknowledging New York courts’ caution when interpreting contract clause as condition precedent). Applying these principles here, we conclude that, under the MLPA, the Servicer’s obligation to request cure within ■ three business days of becoming aware of a material breach is not unmistakably cast.as a condition precedent to Morgan Stanley’s cure-or-repurchase obligation, and, therefore, must be construed as a promise.
Certainly, the MLPA does not caption or otherwise label -the request-for-cure provision as a “condition precedent” to Section 5 remedies, as one might expect sophisticated parties to do if that were their intent. See, e.g., Lindenbaum v. Royco Prop. Corp., 165 A.D.2d 254, 259, 567 N.Y.S.2d 218, 220 (1st Dep’t 1991) (concluding that contract clearly imposed condition precedent where, under heading “Conditions of Loan Approval,” parties expressly noted that certain “conditions must be satisfied prior to "the issuance of Closing Instructions” (emphasis omitted)).
Nor does MLPA Section 5 employ any recognized “linguistic conventions” of condition — such as “‘if,’ ‘on condition that,’ ‘provided that,’ -‘in the event that/' and ‘subject to/ ” — to make plain that Morgan Stanley’s remedy obligations do not arise unless and until the ■ Servicer requests cure. Israel v. Chabra, 537 F.3d at 93 (quoting Ginett v. Comput. Task Grp., 962 F.2d 1085, 1100 (2d Cir.1992)) (identifying notice obligation introduced by under
The failure to couch the request-for-cure provision in the explicit languáge of condition is particularly significant here because the sophisticated drafters elsewhere employed precisely such language to establish undoubted conditions precedent. See, e.g., J.A. 448 (providing - in MLPA for certain actions “in the event that ... the Mortgage Loans ... are held to be the property of the Seller” (emphasis added)); id. at 450 (providing in MLPA for agent or designee to exercise purchaser’s rights “provided the Purchaser,has provided the Seller with prior notice of .the. identity of such designee or agent” (emphasis added)); see also id. at 264 (stating in PSA that “successor master servicer must assume all of the obligations of the terminated Master Servicer ... as a condition precedent to its becoming Master Servicer hereunder” (emphasis added)); id. at 341 (stating in PSA that, “as a condition precedent to the indemnification provided for in this Section,” indemnitee must “notify the applicable Indemnifying Party in writing” of commencement of any action (emphasis added)).
Indeed, even within MLPA Section 5, its drafters employed the unmistakable language of condition in detailing Morgan Stanley’s repurchase obligation. See id. at 455 (stating that Seller “covenants and agrees that, if any such ... Material Breach cannot be corrected or cured in all material aspects within the [90-day] cure period [ ■]; the’ Seller shall ... either (i) repurchase the affected Mortgage Loan ...: or (ii) ■ ... ’replace, without recourse, any Mortgage Loan” (emphasis added)). In short, Section 5 makes plain that Mor-gán Stanley is required to repurchase or replace a defective loan only if it is unable to cure the defective representation within the 90-day period afforded by the MLPA. There is no comparable contract language, however, that conditions this remedy obligation on a request for cure, much less on such a request being made within three business days. See Realtime Data, LLC v. Melone, 104 A.D.3d 748, 750-51, 961 N.Y.S.2d 275, 277-78 (2d Dep’t 2013) (invoking canon expressio unius est exclusio alterius to conclude that contract language conditioning employee bonus “upon” sale of assets implies that bonus does not apply to distributions otherwise based); see also International Fid. Ins. Co. v. County of Rockland, 98 F.Supp.2d 400, 412 (S.D.N.Y.2000) (recognizing that “[sophisticated lawyers ... must be presumed to know how to use parallel construction and identical wording to impart identical meaning when they intend to do so, and how tó use
Thus, the very contract language employed by the parties undermines our dissenting colleague’s conclusión'that Morgan Stanley cannot be expected to cure breaches of which it has been notified but for which it has not received a formal request for cure. See Dissenting Op., post at 315-17. In fact, its obligation to repurchase is. conditioned only on its inability to cure within the 90-day cure period. And, as the MLPA makes clear, that cure period is triggered exclusively by “the Seller’s receipt of the notice of ... Material Breach,” not the Servicer’s request for cure. J.A. 454 (emphasis added).
■While New York courts have construed some triggering events as conditions precedent, they have done so only when the trigger is necessary to a party’s ability to perform the obligation at issue. See, e.g., ALJ Capital I, L.P. v. David J. Joseph Co., 15 Misc.3d 1127(A), 2007 WL 1218355, at *2, *5 (Sup.Ct. Mar. 13, 2007) (holding notice of disallowance a condition precedent to defendant’s repayment obligation because, notice was necessary to afford defendant opportunity ■ to cure disallowance within cure period, upon failure of which plaintiff could demand repayment), aff'd 48 A.D.3d 208, 208, 851 N.Y.S.2d 154, 155 (1st Dep’t 2008); see also Assured Guar. Mun. Corp. v. DB Structured Prods., Inc., 33 Misc.3d 720, 731, 742-44, 927 N.Y.S.2d 880, 887-88, 895-97 (Sup.Ct. July 25, 2011) (assuming that notice of breach triggering 60-day cure period was condition precedent to repurchase obligation in holding notice adequate); Morgan Guar. Tr. Co. v. Bay View Franchise Mortg. Acceptance Co., No. 00 Civ. 8613(SAS), 2002 'WL 818082, at *4-5 (S.D.N.Y. Apr. 30, 2002) (applying New York law in recognizing request to cure as condition precedent where it was exclusive trigger for 30-day cure period, which, if not met, gave rise to repurchase obligation). -
Even if the MLPA’s notice-of-breach provision might be construed as a condition precedent because it is the necessary trigger for the cure period afforded Morgan Stanley,
In sum, because (1) the obligation to request cure within three business days is neither framed in conditional language nor a necessary trigger for Morgan Stanley’s remedy obligations; (2) notice of breach is, in fact, the exclusive trigger for the 90-day period within which, Morgan Stanley was obligated to cure or to repurchase; and (3) the timeliness of notice of breach is not contractually limited to three days, we conclude that the MLPA cannot be construed to make either notice of breach within three business days or request for cure conditions precedent to Morgan Stanley’s remedy obligations. See Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co., 86 N.Y.2d at 691, 636 N.Y.S.2d at 737, 660 N.E.2d 415. Rather, timely request Tor cure is properly construed as a promise, which on remand should be reviewed only for substantial performance. See Israel v. Chabra, 537 F.3d at 93.
C. The Timing of the Servicer’s Request for Cure Cannot Preclude. a Finding of Substantial Performance as a Matter of Law
The district court determined, as a matter of law, that the Servicer’s March •18, 2009 communication to Morgan Stanley of notice of breach and request for cure was untimely. See BNY II, 2014 WL 2745011, at *9.iWe here conclude that the timing of the Servicer’s request for cure cannot preclude a finding of 'substantial performance as- a matter of law. In explaining this conclusion, we first examine the reasoning informing the district court’s timeliness analysis, some of which we ac
As already detailed; the MLPA requires a party to give notice of breach promptly upon discovering a material breach of representation. It also requires a Servicer to act promptly in requesting cure after becoming aware of the breach. But it is only as to the latter obligation that the MLPA cabins promptness to three business days. The district court, however, appears to have concluded that where, as here,, the Servicer, is the discovering party, notice of breach is not prompt if not made within three days. See id. at *3 (“The MLPA gave the. Special Servicer three days to send out notice of any breach.”); id. at *9 (holding that, because Servicer’s notice to Morgan Stanley was not sent within three business days of what court found to be “absolute, drop-dead date” for awareness of breach, “breach notice was therefore untimely”). In view of the Servicer’s having discovered the breach, the district court concluded that (1) any difference in the obligations’ triggering words — “discovering,” and “becoming aware of’ — was “of no moment,” BNY I, 2013 WL '3146824, at *20; (2) awareness, like discovery, occurs only at the conclusion of an investigation of the suspected breach, provided the inyésti-gation is concluded within a reasonable time, see id. at *19-21; (3) the Servicer had reasonably concluded its investigation and, thus, become “aware” of Morgan Stanley’s alleged breach (a) by “February 16, when Wilkicki prepared‘her memorandum” to Unell, or certainly (b) “by February 19, when Unell agreed with Wilkieki’s assessment and instructed her to send the breach notice,” but in no event later than (c) “February 27, when the draft appraisal came in,” BNY II, 2014 WL 2745Ó11, at *9. Thus, the Servicer’s delay of some two weeks after the .last of these «lates to transmit a request for cure was held untimely as a matter of law. .
BNY faults this reasoning on several grounds. We focus- here on the argu-, ment it derives from the well established principle that,, where contract provisions use different language, courts must assume the parties--intended different meanings. See Frank B. Hall & Co. of N.Y. v. Orient Overseas Assocs., 48 N.Y.2d 958, 959, 425 N.Y.S.2d 66, 67, 401 N.E.2d 189 (1979). Thus, BNY argues, “discovering” breach must mean something different from “becoming aware” of breach, with “awareness” necessarily coming after “discovery” — indeed, -after communication of the notice of breach triggered by discovery — to avoid the absurdity of requiring a Servicer to' request cure (within three business days of awareness) before requiring the 'party discovering the breach to give notice (subject to an undefined promptness obligation), thereby triggering the cure period.
BNY’s argument makes sense when the Servicer is not the .party discovering the breach. In that circumstance, it will generally only be upon receipt of the discoverer’s notice of breach that the Servicer acquires the awareness necessary for it to request cure. Further, to the extent the discoverer conducted an investigation of the breach that the .Servicer has no need to duplicate, the latter can reasonably be expected to make its request for cure within three business days of receiving the notice of breach.
But, when- the Servicer is the party discovering breach, we cannot categorically conclude, as BNY urges, that it does not become aware of the breach until it transmits its own notice of breach to others. Dictionary definitions may admit the possibility of discovery without awareness. Compare Webster’s Third New Int’l Dictionary 656 (2002) («iefining “discover” as “to obtain for the first time
We therefore decline to hold as a matter of law that a Servicer who discovers a breach cannot be charged with awareness until it transmits notice. The fact that the Servicer in this case simultaneously transmitted its request for cure with its notice of breach does not necessarily mean that the former was filed within the requisite three business days. Rather, the timeliness of both notice of breach and request for cure may depend,_ as the district court recognized, on whether they were sent promptly after the Special Servicer reasonably concluded its investigation of breach.,
Where we depart from the district court is in its conclusion that notice of breach, as well as request for cure, had to be communicated within three business days to be deemed prompt. As already, discussed, the MLPA imposes a three-day limitation; on the word “promptly” only as to requests for cure. The absence of such a limitation from the notice-of-breach obligation indicates that the word is to be construed more flexibly in light of the totality of circumstances. See United States Fid. & Guar. Co. v. Annunziata, 67 N.Y.2d 229, 233, 501 N.Y.S.2d 790, 792, 492 N.E.2d 1206 (1986) (recognizing that where condition included in one provision is omitted from another, it “must be assumed to have been intentional under accepted canons of contract construction”); Sterling Inv’r Servs., Inc. v. 1155 Nobo Assocs., LLC, 30 A.D.3d 579, 581, 818 N.Y.S.2d 513, 516 (2d Dep’t 2006) (same).
We further conclude that the district court could not identify the reasonable conclusion date for the Special Servi-cer’s breach investigation — or even three possible conclusion dates — as a matter of law. Where the promptness of breach discovery is questioned, resolution depends on an assessment of the totality of circumstances, necessarily including the credibility of witnesses and the weight particular evidence will bear. ' Such matters are generally determined by the trier of fact rather than the court, particularly when the ultimate question is reasonableness. See Hartford Ins. Co. v. County of Nassau, 46 N.Y.2d 1028, 1030, 416 N.Y.S.2d 539, 541, 389 N.E.2d 1061 (1979) (noting that “question whether a notice ... has been sent ‘as soon as is reasonably possible’ is a question of fact which depends on all the facts and circumstances, especially the length of and. the, reasons for the delay,” and that “[i]t is only in the exceptional case that it may be decided as a matter of law”); Deso v. London & Lancashire Indem. Co. of Am., 3 N.Y.2d 127, 129, 164 N.Y.S.2d 689, 691, 143 N.E.2d 889 (1957) (explaining that “reasonableness of. a delay” in timely written notice is usually question for jury);
.Of course, even if a factfinder were to include chain:of-command review within a reasonable breach-investigation period, disputes- might persist as to whether other events — e.g., commissioning the initial or review appraisals — unreasonably prolonged the investigation. While the district court dismissed Wilkicki’s explanations for these appraisals as implausible, when we view the record hr the light most favorable to BNY, we' Cannot conclude that a reasonable factfinder was precluded as a matter of law from reaching any other conclusion. .Thus, the dispute cannot be resolved on summary judgment. See, e.g., Dillon v. Morano, 497 F.3d 247, 253-54 (2d Cir.2007) (vacating award of summary judgment where, permissibility of defendant’s conduct turned on explanation for it, which necessarily involved credibility determination that was question for jury).
Further, because request for cure is not a condition precedent, even if a factfinder were to conclude that the time for reasonable investigation of breach ended more than three business days before March 18, 2009, it would still have to decide the question of substantial performance. ■
“Substantial performance is performance, the deviations permitted being minor, unimportant, inadvertent, and unin
The question of' substantial performance is usually one “of fact and should be decided as a matter of law only where the inferences are certain.” Merrill Lynch & Co. v. Allegheny Energy, Inc., 500 F.3d 171, 186 (2d Cir.2007) (collecting cases, including Hadden v. Consol. Edison Co. of N.Y., 34 N.Y.2d 88, 96, 356 N.Y.S.2d 249, 255, 312 N.E.2d 445 (1974) (assessing substantial performance on basis of several factors such as absolute and relative magnitude of default, its effect on contract’s purpose, willfulness, and degree to which injured party was benefited under contract)). Thus, while .BNY points to a number of factors supporting substantial performance, we do not here decide the question in its favor as a matter of law. We conclude only that the record does not permit substantial performance to be rejected as a matter of law. See Jacob & Youngs, Inc. v. Kent, 230 N.Y. at 243, 129 N.E. 889 (explaining that substantial performance is question of degree, which, “if there is doubt,” must be answered by “triers of the facts”).
In reaching that conclusion, we reiterate certain undisputed facts. First, BNY did transmit a request for cure to Morgan Stanley; thus, the only performance issue is timeliness. Second, the delay in transmittal, even on the district court’s findings, was in the range of two to four weeks. Third, the noticed breach of representation was not curable, regardless of the date when BNY can be charged with awareness of the breach.
These circumstances strongly support substantial performance insofar as delay in requesting a cure that was never possible would likely be deemed trivial. As this court recently had occasion to note, “[w]hen contracting parties agree to a notice-and-cure provision, it is reasonable to assume that they do so with the assumption that the breaches which would be used to terminate the contract would be curable breaches.” Giuffre Hyundai, Ltd. v. Hyundai Motor Am., 756 F.3d 204, 210 (2d Cir.2014) (internal quotation marks omitted) (emphasis in original). Thus, “New York common law will pot require strict compliance with a contractual notice- and-eure provision if providing an opportunity to cure would be useless.” Id. at 209 (collecting eases),
Morgan Stanley attempts to distinguish Giuffre and the cases cited therein on the ground that they considered the propriety of actions taken by parties who, instead of providing opportunity to cure, terminated contracts or commenced actions for damages. It submits that the futility of cure here is no excuse for the Servicer’s failure timely to request cure because that “is the only mechanism for Morgan Stanley’s obligation to be triggered.” Appellee Br. 46. The argument fails because, as we have already concluded, notice of breach, not request for cure, is the singular trigger for Morgan Stanley’s remedy obligations. Further, it is by no means evident that the timeliness of notice is essential to this trigger because the 90-day cure period would not begin to run until notice was received and any harm to Morgan Stanley from a delay in notice could offset its remedy obligations. See 63 N.Y. Jur.2d, Guaranty & Suretyship § 134 (2006) (stating that where giving notice within specified time is not condition precedent to
Accordingly, because the timeliness of the Special Servicer’s request for cure should not. have been determined as a matter of law and because a reasonable jury could- find that, even if there was some delay in requesting cure, the Special Servi-cer substantially performed this MLPA obligation, these questions of timeliness and substantial performance cannot be decided in favor of Morgan Stanley on summary judgment but must be presented, to the factfinder at trial.
III. Conclusion
To summarize, we conclude as follows:
1. “Notice to. cure” is not a phrase that appears in the MLPA and, thus, cannot be identified as a condition precedent to Morgan Stanley’s MLPA cure-or-repurchase obligation.
2. The request-for-cure obligation that the MLPA imposes on the Special Servicer is properly construed as a promise rather than ás a condition precedent because it neither employs the linguistic conventions of condition nor serves as a trigger for the cure period at issue.
3. Even if the MLPA’s notice-of-breach obligation could be construed as a condition precedent because it triggers the 90-day cure period — a matter we need not decide as no party advances the argument — that rationale would not extend to the timeliness of the notice, which has no triggering effect, much less to a three-day time limitation, which doe's not cabin the notice-of-breach obligation as it does the request-for-cure obligation.
4. The fact that the notice-of-breach obligation arises upon a party’s “discovering” breach while the request-for-cure obligation, arises upon a Servicer’s “becoming aware” of the breach does not admit the categorical conclusion, urged by BNY, that the time for requesting cure cannot run before notice of breach is given, particularly where, as here, the Servicer is the party discovering breach.
5. Under New York law, a reasonable time for investigation is afforded before a party can be said to have discovered or become aware of a breach.
6. Questions of fact as to the reasonableness of time taken to investigate the alleged breach of the MLPA’s Environmental Conditions Representation preclude finding, as a matter of law, that request for cure was untimely, particularly when reviewed for substantial performance.
The .judgment of the district court is, therefore,: VACATED, and the case is REMANDED for- further proceedings consistent with this opinion.
. On May 10, 2010, pursuant to transactions not relevant here, C-III Asset Management LLC replaced Centerline as the Trust’s Special Servicer. For purposes of this appeal, we need only refer herein to the “Special Servi-cer,” without régard to the specific entity then serving in that capacity.
. As the district court detailed, Wilkicki was not then totally unfamiliar with the City View Loan. Prior to securitization, Centerline (and its predecessor) had acted--as Interim .Servicer at Morgan Stanley’s behest. Centerline’s parent company was then evaluating whether to invest in the Trust, and Wilkicki was among the Centerline employees who conducted, due diligence. See BNY I, 2013 WL 3146824, at *3, *25. The district court explained why the Trustee cannot be charged with knowledge obtained by Centerline when not acting on its behalf, see id, at *25-29, and the parties do not argue otherwise on this appeal. Thus, we . do not discuss that further.
. Representation 12 is entitled “Environmental Conditions” and states as follows:
(i) With respect to the Mortgaged Properties securing the Mortgage Loans ... an environmental site assessment, or an update of a previous such report, was performed with respect to each Mortgaged Property in connection with the. origination or the acquisition of the related Mortgage Loan; a report of each such assessment (or the most recent assessment with respect to each • Mortgaged Property) (an "Environmental Report") has been delivered to the Purchaser, and the Seller has no knowledge of any materiál and adverse environmental condition or circumstance affecting any Mortgaged Property that was-not disclosed in such report.
J.A. 473 (emphasis in original).
,On this appeal, we express ho view as to the merits of the Servicer's (and, therefore, Trustee BNY’s) breach conclusion.- We'consider only whether BNY failed to satisfy an MLPA condition-precedent for securing a remedy for breach.
. In Representation 27, Morgan Stanley war.rantied that, to its knowledge, there was "no material default, breach, .violation or event of acceleration, (and no event which, with the passage of time or the giving of notice, or both, would constitute any of the foregoing) under the documents evidencing or securing the Mortgage Loan” that would materially .and, adversely affect the value of the mortgage loan or property. J.A, 478-79. The Special Servicer asserted, that Morgan ..Stanley breached this representation because, by December 2006, at the latest, it knew, that Wal-Mart was claiming lease, default, and yet Mor
. The" district court concluded that the Special Servicer had possession of all facts necessary to investigate and bring a claim for breach of this representation by March 16, 2009, making its September 24, 2010 notice of .breach untimely, . See BNY I, 2013 WL 3146824, at *23. This conclusion is -not challenged on appeal and, thus, we do not discuss it'further.
. Section 2.3(a) of'the PSA contains similar, but not identical, breach and recourse language. See J.A, 121-22, The district court focused on the language in the MLPA as it was the only contract to which Morgan Stanley was a party. As neither party challenges that approach on appeal, we do the same without considering any language discrepancies between the MLPA and the PSA.
. There is no indication that BNY played any .part in drafting-the MLPA. Rather, Morgan .Stanley appears to have drafted this document, as the same Morgan Stanley Vice Presi- ' debt signed the agreement on behalf of both Morgan Stanley and Morgan Stanley Capital I, Inc., the sole contracting parties. See J.A. 465. While BNY, as the named Trustee, is a party to the PSA, there is no indication in the record as to its role in drafting that agreement. In any event, because the point is not raised, we .have no occasion to consider whether any ambiguities in MLPA provisions ate properly construed against Morgan Stanley as drafter. See Village of Ilion v. County of Herkimer, 23 N.Y.3d 812, 820, 993 N.Y.S.2d 648, 652, 18 N.E.3d 359 (2014). It suffices that the law requires ambiguous provisions to be construed as promises rather than conditions precedent. See Oppenheimer & Co., v. Oppenheim, Appel, Dixon & Co., 86 N.Y.2d at 691, 636 N.Y.S.2d at 737, 660 N.E.2d 415.
. We need not decide this question because, as earlier noted, Morgan Stanley defends the district court’s judgment only by reference to the contract’s request-for-cure obligation.
. Judge Wesley deems it implausible that Morgan Stanley would be obligated to cure in the absence of. a request. He maintains that because the Special Servicer was under no obligation to request cure, its request for cure provided essential signaling and demand functions. See Dissenting Op., post at 315-17, 316 n. 4. The conclusion is undermined not only by the 'MLPA’s express assignment of the signaling function to notice of breach, but also to its assignment of a mandatory request-for-cure obligation to the Master Servicer. See J.A. 454 (explaining that, upon becoming aware of any material breach, Master Servi-cer-must, and Special Servicer may, request cure). We need not parse the difference between the Master Servicer's and the Special Servicer’s request-for-cure obligations further because, in any event, the MLPA has not
. Thus, Columbus can be said to have .discovered the Americas without' being ■ aware that they were new continents, while Vespucci can be said to have been aware that the Americas were new continents without having discovered them.
. Judge Wesley disagrees, observing that, under New York law, a corporation is charged with the knowledge of its agents. See Dissenting Op., post at 318. ..But none of the cited cases reach that conclusion in the context of a corporate entity conducting a breach investigation, much less one doing so as the agent of a trustee. New York University v. First Financial Insurance Co., 322 F.3d 750 (2d Cir.2003), does not offer "precisely this situation," Dissenting Op., post at 320 n! 12, because that case involved neither an agent acting on behalf of a trustee nor a breach investigation similar in nature or scope to. the . one at issue here., Instead, an insurer was there charged with its investigative agent’s knowledge of breach' as of the date the insured conceded certain facts to the agent that effectively admitted the breach precluding recovery under the insurance contract. See New York Univ. v. First Fin. Ins. Co., 322 F.3d at 753 & n. 2. Here, Morgan Stanley did not similarly confirm its breach of the MLPA to Wilkicki. As already noted, in such circumstances, the law affords a reasonable time for investigation of breach to avoid creating an incentive for premature litigation. That concern supports including some chain-of-command review within a reasonable investigation, rather than demanding action as soon as any corporate agent reaches a conclusion regardless of his authority to act on it for the corporatiori. See Kirschner v. KPMG LLP, 15 N.Y.3d 446, 465, 912 N.Y.S.2d 508, 517, 938 N.E.2d 941 (2010) (acknowledging that, generally, only acts within scope of agents’ authority are "presumptively imputed to their principals”).
. See also 13 Williston on Contracts § 38:16 (4th ed.. 2000) ("Any words which, when properly inteipreted or construed by the court, make clear the notion that the performance of a promise in a contract is dependent on some other act or event will create an express condition.”).
Dissenting Opinion
dissenting:
In concluding that a request to cure was not a condition precedent to Morgan Stanley’s repurchase obligation and that issues of fact preclude summary judgment, the majority opinion both misapplies New York law and misreads the plain language of the contract. The result is, in essence, judicial reformation of the agreement, saving a sophisticated party from the requirements of the bargain it made following arms-length negotiation. Because I cannot agree with these conclusions, I respectfully dissent.
A recent case of the Court of Appeals confirms this analysis: the Court construed a provision requiring negotiation and execution of additional terms as an express condition precedent to a party’s obligation to supply fiber-optic capacity but relied on no conditional words, identifying the parties’ “clear intent” solely from the nature and structure of the agreement. See IDT Corp. v. Tyco Grp., S.A.R.L., 13 N.Y.3d 209, 212, 214, 890 N.Y.S.2d 401, 918 N.E.2d 913 (2009).
So what then does the language and structure of the contract — negotiated at arms’ léngth by sophisticated commercial entities — tell us' about breaches of the agreement and the remedies provided for those breaches? For ease of reference, here again are the three obligations as identified in the majority opinion, ante, at 304:
1. If a material breach exists, “the party discovering such ... Material Breach ■shall promptly notify, in writing, the other party....” >
*315 2. “Promptly (but in any event within three Business Days) upon becoming aware of any such ... Material Breach, the Master Servicer shall, and the Special Servicer may,- request thát the Seller, not later than 90 days from the Seller’s receipt of the notice of such ... Material Breach, cure such ... Material Breach____” •
3. “The Seller hereby • covenants and agrees that, if any such ... Material Breach cannot be corrected or cured in all material aspects within the above cure period[], the Seller shall, on or before the- termination of such cure periodic], either (i) repurchase the affected Mortgage Loan ... or (ii) ... at its option replace, without recourse, any Mortgage Loan ... to which such defect relates with a [substitute mortgage].”
J.A. 454-55. We can all agree the third clause clearly conditions Morgan Stanley’s repurchase-or-replace obligation on the existence of a particular circumstance: that “any ... Material Breach cannot be corrected or cured in all material aspects within the above cure period [ ].” J.A. 455 (emphasis added); see Majority Op.,, ante, at 306 (identifying this clause as an example of “unmistakable language of condition”). Similarly, we agree that this language makes the repurchase obligation dependent on the obligation to cure within the cure period. But where the majority opinion and I depart is whether that obligation to cure within the cure period arises from the notice of breach or from the request to cure.
The majority opinion concludes that because the ninety-day period is calculated from the date of the notice of breach, the cure period must be triggered by the notice. See Majority Op., ante, at 307 (“[A]s the MLPA makes clear, that cure period is triggered exclusively by ‘the Seller’s receipt of the notice of ... Material breach,’ not the Servicer’s request for cure.” (quoting J.A. 454)). I cannot agree: A ninety-day clock may count down from the notice of breach, but it is only the request to cure that gives, that clock any legal meaning. The ninety-day cure period is written as a clause in the middle of the request provision, which states that “the Special Servi-cer may[ ] request that the Seller, not later than 90 days from the Seller’s receipt of the notice of such ... Material Breach, cure such ... Material Breach.” J.A. 454 (emphasis added). In other words, the ninety day's and their legal significance are a part of the Special Servicer’s request.' If there were no' request, ninety days' would pass — in time’s typical fashion — but it would not be a legally significant “cure period” for purposes of the repurchase obligation because no .one had requested cure by that date.
The' majority opinion seems disturbed by the fact the deadline for cure is not counted down from the request for cure and so concludes that the request itself has no conditional force over the repurchase obligation. But the repurchase obligation depends on the Seller not curing the breach within the cure period; that circumstance can only exist if the Special Servicer first makes a request to cure, which includes (and creates) the obligation to cure and the legal deadline for it. Nothing about the fact that the deadline is established ninety days after another event changes the fact that it is the request that brings it into existence. For example, imagine two parties enter into a contract that reads: “Upon, becoming aware of a material breach, the Special Servicer may request'that the Seller,’not later than ten days following the next full, moon, cure such material breach.” An. obligation to cure within the cure period does not come into existence as a result of the lunar cycle; it is triggered by the request — the “not later than” clause simply provides a way to determine the deadline by which
This interpretation is confirmed by a simple counterfactual: If the Special Ser-vicer had exercised its option not to request cure, would Morgan Stanley still have been obliged to cure or repurchase the loan? The answer — on the plain face of the contract — must be “no.” The contract is conspicuously lacking any language making cure of every material breach .obligatory on the Seller absent a request to cure.
Compare-this framework with the provisions considered by district courts-in our
In sum, regardless of whether the parties used any particular conditional words, the language of the repurchase obligation is “clear” and “unmistakable” that it arises only when cure does not occur within the cure period — and cure within the. period is an obligation that arises only out of the Special Servicer’s request. See ALJ Capital, 48 A.D.3d at 208, 851 N.Y.S.2d 154.
Express conditions precedent are subject to “the requirement of strict compliance,” in contrast to promises or constructive conditions, with which only “substantial compliance” is required. Oppenheimer, 86 N.Y.2d at 690, 692, 636 N.Y.S.2d 734, 660 N.E.2d 415 (internal quotation marks omitted). Further, “no mitigating standard of materiality or sub-stantiality [is] applicable to the non-occurrence of [an express condition precedent].” Id. at 692, 636 N.Y.S.2d 734, 660 N.E.2d 415 (internal quotation marks omitted). Consequently, once we determine that a request to cure “within three Business Days[] upon becoming aware” of the material breach, J.A. 454,- is an express condition precedent to the repurchase obligation, the only remaining question on summary judgment is whether there exists any genuine issue of material fact as -to the Special Servicer’s strict compliance with that condition. Under longstanding New York law, no reasonable factfinder could determine that the Special Servicer only became aware of
As the majority opinion; explains, the material breach identified here is premised on .Morgan Stanley’s representation that it had no knowledge , of any “material- and adverse environmental condition or circumstance affecting any Mortgaged Property that was not disclosed in such report.” J.A. 625; see also Majority Op., ante, at 301 & n. 3. The Special Servicer’s conclusion that a breach of this representation had occurred .rested primarily on a document showing that Morgan Stanley’s counsel knew the environmental report neither addressed a relevant state regulation, nor the notices of violation, issued thereunder; in fact, this was the only piece of evidence identified in the formal, notice of breach and request to cure. See J.A. 625-26. However, in a document sent to the Special Servicer’s Associate General Counsel on February 16, 2009, the Director of Special Servicing — and the woman who ultimately signed the notice of breach and request to cure — identified, “additional facts ,.. to demonstrate the material and adverse effect” of the breach, including the anchor tenant’s departure -and subsequent lease terminations by other tenants, “discontinued ... loan payments to the Trust in November 2008 as a- direct result of insufficient operating income,” and rejection of the borrower’s insurance claim under a pollution legal liability policy. J.A. 896-98.
The majority opinion’s approach places great weight on the internal governance structure of,the Special Servicer, essentially permitting the corporation to deny its “awaréness” of a fact simply because it required authorization by the president to issue the notice. See Majority Op., ante, at 310-12. But “a fundamental principle that has informed the law of agency and corporations for centuries” is that “the acts of agents, and the knowledge they acquire while acting within the scope of their authority are presumptively imputed to their principals.” Kirschner v. KPMG LLP, 15 N.Y.3d 446, 465, 912 N.Y.S.2d 508, 938 N.E.2d 941 (2010); accord Corrigan v. Bobbs-Merrill Co., 228 N.Y. 58, 68, 126 N.E. 260 (1920) (explaining that, if the employee of a corporation obtains knowledge “while acting within the scope of his authority, on behalf of [the corporation], for its benefit, [the corporation] is chargeable with his knowledge”).
[Njotice of facts to an agent is constructive notice thereof to the principal himself, where it arises from or is at the time connected with the subject-matter of his agency, for, upon general principles of public policy, it is presumed that the agent has -communicated such facts*319 to the principal, and, if he has not, still the principal having- .[ejntrusted the agent .-with the particular business, the other party has a right to deem his acts and knowledge obligatory upon the principal.
Hyatt v. Clark, 118 N.Y. 563, 569, 23 N.E. 891 (1890); accord N.Y. Univ. v. First Fin. Ins. Co., 322 F.3d 750, 753 & n. 2 (2d Cir.2003) (applying these principles to a timeliness inquiry and calculating the insurer’s delay in notice from the date its investigator discovered grounds for liability); Apollo Fuel Oil v. United States, 195 F.3d 74, 76-77 (2d Cir.1999) (applying the same rule to conclude the corporation knew of intentional misconduct through its' employees’ knowledge). This rule applies even where such. knowledge works the waiver of a contractual right and the corporate agent does not have any authorization under the contract to make such a waiver affirmatively. See, e.g., Hurley v. John Hancock Mut. Life Ins. Co., 247 A.D. 547, 550, 288 N.Y.S. 199 (4th Dep’t 1936).
Put simply, as a matter of law, the Special Servicer knew the facts of the breach and their material and adverse effect on the loan well before March 15, 2009,. The Director of Special Servicing drafted a memorandum containing sufficient facts to constitute awareness of both the breach and its material and adverse. effects on February 16, 2009.
Just as importantly, none of the post-February 16 activities described by the majority opinion.contributed in any material way to the Special Servicer’s “awareness” of any breach. None of the internal “chain of command” reviéws — not the removal of one paragraph of supporting facts from the notice and request to cure by the Associate General Counsel, see J.A.
(1) The loan was in default;
(2) The anchor tenant had departed, which precipitated rent reductions, lease terminations, and discontinued rent payments by other tenants;
(3) An Ohio regulatory body had filed a lawsuit against the borrower arising from the same environmental regulatory violations at issue in the breach;
(4) The borrower’s insurance claim for the legal liability was denied;
(5) The Trust was seeking receivership for the property; and
(6) The Trust would have to fund any legal costs associated with attempts to recoup value.
See J.A. 619, 897-98. The substantive portion of the February 16, 2009 memorandum concluded with these words: “All of the above results, stem from the state code violations which were present prior to, during and after the sale of the Mortgage Loan to the Trust. The Mortgage Loan should be repurchased pursuant to the terms and conditions set forth in the PSA and the applicable MLPA.” J.A. 898. It exceeds all bounds of credulity to think that, in the face of all these known facts, the Special Servicer was anything but aware of the circumstances of the breach as well as its material and adverse consequences.
The majority opinion’s approach thus drastically departs from New York law governing corporate knowledge and timely request obligations under a contract. Under the majority opinion, all any corporation need do now is require authorization for such requests at its highest level — and regardless of the facts known by employees below the highest executive officer, the corporation cannot be charged with “awareness” of those facts.
The Oppenheimer Court considered and rejected a rule that would obviate the harsh consequences of an express condition precedent, concluding that strict compliance was necessary. See 86 N.Y.2d at 691-92, 636 N.Y.S.2d 734, 660 N.E.2d 415. Yet the majority opinion here releases a sophisticated party from thé burden of complying with the agreement it made. At the risk of stating the- obvious, if the corporation’s internal governance did not permit a three-day turnaround between awareness of breach and a request ‘to cure, it should have bargained for more time.
1 respectfully dissent.
. Oppenheimer itself also relied on a case in which absolutely no conditional language appeared; the contract simply required notice of' shipment of goods, and the failure to provide such notice was deemed a “failure to ‘perform[ ] all conditions precedent’ ” and "barred [plaintiff] from recovery.” 86 N.Y.2d at 693-94, 636 N.Y.S.2d 734, 660 N.E.2d 415 (first alteration in original) (quoting Jungmann & Co. v. Atterbury Bros., 249 N.Y. 119, 122, 163 N.E. 123 (1928)).
. Stepping back, it makes sense that the request to cure calculates its deadline from the notice of breach. Either party — -the Seller or the Special Servicer — may be the one to discover the breach in the first instance and must then notify the other party. See J.A. 454. If the Seller discovers the breach and provides notice, the Special Servicer then has three days to decide whether to request cure or lose its right to do so. If it chooses to exercise its right to request cure on day three, there may be only eighty-seven days until the end of the cure period — but the Seller already had three days of notice, by its own discovery, of the nature and circumstances of the breach. By contrast, if the Special Servicer discovers the breach, it can both notify the Seller of breach and request cure in the same document, in which case the Seller has the same ninety days of notice. In either event, , this system ensures that the .Seller has exactly ninety days of knowing about the breach, no more and no less, before the deadline occurs.
. The majority opinion suggests this consideration is irrelevant because the MLPA-assigned the signaling function to -the notice of breach and because the Master Servicer had a "mandatory request-for-cure obligation.” Majority Op., ante, at 307 n. 10. However, the loan at ' issue was transferred to the Special Servicer ,in-November 2008, see Majority Op., ante, at 301, at which point the Master Servicer ceased to be "obligated to service and administer” the loan except as to certain specified functions, none of which include requesting cure, see J.A, 217. Only the Special Servi-cer’s contractual rights and obligations are therefore relevant, and while the MLPA provided that the Master Servicer "shall” request cure, it provided only that the Special Servi-cer "may” request cure. J.A. 454. "May” in this context can only possess a permissive, rather than mandatory, meaning, see N.Y. State Elec. & Gas Corp. v. Aasen, 157 A.D.2d 965, 967, 550 N.Y.S.2d 223 (3d Dep’t 1990), and the MLPA thus imposed no obligation on the Special Servicer to request cure. As I have explained, notice of a breach does not trigger the obligation to cure the breach — the request to cure, is what obliges the Seller to cure within the defined cure period. A request to cure by the Special Servicer,, therefore told the Seller that the former was exercising its option to demand cúre, providing exactly the same signaling and demand functions as the notice of disallowance in ALJ .Capital. See infra note 7; see also Majority Op., ante, at 307 (acknowledging AU Capital’s notice as a condition precedent).
. ■ As described above, if the Special Servicer decides not to request a cure, then the date of the notification of breach has no legal .significance — ninety days later, nothing happens, and no one cafes.
, The majority opinion appears distracted by the District Court’s "notice.to cure” misnomer — but we are engaged in de novo review, and even if we were applying a more deferential standard, we are certainly not obligated to accept the District Court’s labels.
. In fact, AU concerned just such a timely notice provision triggering a cure period, after which time the plaintiff was permitted to -seek recovery-in court. See ALJ Capital I, L.P. v. David J. Joseph Co., 15 Misc.3d 1127(A), 2007 WL 1218355, at *4-5 (N.Y.Sup.Ct. Mar. 13, 2007). The First Department affirmed the trial court’s conclusion that timely notice was "a condition precedent "despite the lack of explicitly conditional language” because the written notice "whs unmistakably required by the agreement’s 'Cure Period’ provision prior to the assertion of a claim for repayment.” ALJ Capital, 48 A.D.3d at 208, 851 N.Y.S.2d 154.
. Because the majority opinion concludes the request to cure was merely a promise, it analyzes the facts under the rubric of substantial compliance and concludes summary judgment, is inappropriate because reasonable factfinders may differ as to the extent of any "reasonable investigation” including "some , degree of chain-of-command review.” Majority Op., ante, at 310-12. Even under a substantial compliance analysis, however, as explained infra, New York law and the undisputed facts would require us to conclude that the Special Servicer became aware of the breach as of at least February 16, 2009.
. As' a corporate legal entity, the Special Ser-vicer "necessarily functions through human actors — its officers, agents and ■ employees— whose knowledge and conduct may be imputed to the entity under the doctrine of respon-deat superior.” Prudential-Bache Sec., Inc. v. Citibank, N.A., 73 N.Y.2d 263, 276, 539 N.Y.S.2d 699, 536 N.E.2d 1118 (1989).
. Note also that this memorandum was based on an investigation of the loan’s status beginning in November 2008. See J.A. 1109-15. Thus," we are not even considering a situation in which the corporation merely had access to (and thus only arguably constructive notice of) these facts — the February 16/2009 memorandum memorializes facts actually known by the Director of Special Servicing. See J.A. 1111-17. To borrow the majority opinion’s analogy, see Majority Op., ante, at 311 n. 11, she was aware both that she had found the Americas (the fact) and that they were new (its significance).
. Even accepting the dubious proposition that confirmation of the loan valuation somehow moved the Special Servicer from "unaware” to "aware,” that appraisal was confirmed on March 13, 2009. See J.A. 1730; Majority Op,, ante, at 302. It took another five days for the Special Servicer to send the notice of breach and request to cure. See J.A, 624-26.
. The majority opinion criticizes this dissent for not citing cases related to investigations by agents and employees. See Majority Op., ante, at 311 n. 12. However, our prior decision in New York University offers precisely this situation; a line investigator at a company contracted as an insurer’s agent discovered grounds for denying coverage, and that knowledge was imputed to the insurer for purposes of determining timeliness. See 322 F.3d at 753 & n, 2. The majority opinion’s error arises from its failure to recognize that investigation was clearly within the scope of the Director of Special Servicing’s employment, regardless of her ability to take some subsequent external action on behalf of the company. The results of her investigation— i.e., knowledge of the facts and significance of breach — are therefore imputed to the Special Servicer, who must then take whatever steps are necessary in its internal governance structure to act within the time provided by the contract.
. “Freedom of contract prevails in an arm's length transaction between sophisticated par- . ties such as these, and in the absence of countervailing public policy concerns there is no reason to relieve them of the consequences of their bargain. If they are dissatisfied with the consequences of their agreement, the time to say so was at the bargaining table.” Oppenheimer, 86 N.Y.2d at 695, 636 N.Y.S.2d 734, 660 N.E.2d 415 (alteration and internal quotation marks omitted).
