Aftеr a series of settlements and party realignments, Plaintiffs Bancamerica Com *795 mercial Corp. (“Baneameriea”) and ASAR-CO, Inc. (“ASARCO”) sued Defendants Trinity Industries, Inc. and a subsidiary, Mosher Steel Co., (collectively “Trinity”) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 for contribution to costs the Plaintiffs incurred in an environmental cleanup of an industrial site. Additionally, Baneameriea asserted a pendant state law breach of contract claim. The district court held Trinity partially responsible for the site’s environmental contamination, and ordered Trinity to reimburse Baneameriea and ASARCO for the $555,-293.55 in expenses attributable to cleanup of Trinity’s pollution. It also held Trinity liable to Baneameriea for $70,178.07 in unpaid taxes on Baneamerica’s breach of contract claim. We reverse and remand the district court’s refusal to grant Baneameriea and ASARCO prejudgment interest on the Comprehensive Environmental Response, Compensation, and Liability Act award, and affirm the remainder of the district court’s opinion.
The district court’s opinion, found at
Bancamerica Commercial Corp. v. Trinity Indus.,
Trinity and Baneameriea canceled the lease in 1987, at which time Trinity discontinued operations at the site. In conjunction with this cancellation, Baneameriea contracted to purchase certain cranes located on the site from Trinity for $200,000:00. Trinity claims Baneameriea has not yet paid this sum, and argues this alleged debt offsets the $70,178.07 it owes Baneameriea for unpaid taxes.
Upon entry on and investigation of the site, Baneameriea discovered a variety of contamination problems. Trinity left approximately 300 barrels on the site, some of which were leaking and/or contained hazardous substances. Trinity had buried approximately eighty of these barrels in a pit. Three underground storage tanks were leaking gasoline into the soil. Most seriously, the site was highly contaminated with lead. The lead originated from three sources: slag and smelter ash (for which ASARCO was solely responsible), and lead-based paint (for which the nonparties and Trinity were responsible). Id. at 1449.
In 1989, the Environmental Protection Agency notified Baneameriea, ASARCO, and Trinity of their potential liability under the Comprehensive Environmental Response, Compensation, and Liability Act. In 1990, the Environmental Protection Agency and Baneameriea entered into an Administrative Consent Order that required Baneameriea to engage in a cleanup of the site. Thereafter, in 1991, the Environmental Protection Agency issued a Unilateral Comprehensive Environmental Response, Compensation, and Liability Act § 106 Order to ASARCO, requiring it to assist in the- completion of the cleanup. Baneameriea and ASARCO, without assistance from Trinity, completed the cleanup. They then brought this suit seeking contribution from Trinity.
The parties raise seven issuеs on appeal. The first four, raised by Trinity, .are: (1) whether the Environmental Protection Agency orders required Baneameriea and ASAR-CO to meet the public comment requirements of the national contingency plan; (2) if the district court should have decided whether the cleanup was a “remedial” or a “removal” action; (3) whether Baneameriea was entitled to recover costs incurred in 1988 and 1989, prior to the Administrative Consent Order; and (4) whether Trinity was entitled to an offset against Bancameriea’s claim for unpaid taxes. The issues raised by Bane-america and ASARCO are: (5) whether Baneameriea and ASARCO were entitled to prejudgment interest; (6) whether the district court еrred in considering only toxicity and volume in allocating responsibility (and *796 liability) for cleanup of the lead contamination; and (7) whether Trinity breached its lease with Bancamerica through improper maintenance or operation of the underground storage tanks. We reverse the district court’s refusal to award Bancamerica and ASARCO prejudgment interest, and affirm the district court on all other issues. We address these issues in the order presented to us.
I
Did the Environmental Protection Agency orders require Bancamerica and ASARCO to comply with the public comment requirements of the national contingency plan?
In order for Bancamerica and ASARCO to obtain contribution from Trinity, their response actions
1
must have been “consistent with the national contingency plan.” 42 U.S.C. § 9607(a)(4)(B) (1994).
2
Importantly, a regulation in the national contingency plan provides that “[a]ny response action carried out in compliance with the terms of an order issued by [the Environmental Protection Agency] pursuant to section 106 of [the Comprehensive Environmental Response, Compensation, and Liability Act] ... will be considered ‘consistent with the [national contingency plan].’ ” 40 C.F.R. § 300.700(c)(3)(ii) (1995). Both of the orders under which Bancamerica and ASARCO acted were issued by the Environmental Protection Agency pursuant to § 106, and the district court found that Bancamerica and ASARCO complied with the terms of these orders.
Bancamerica,
On appeal, Trinity contends Bancamerica and ASARCO faded to comply with all of the terms of their orders, and, therefore, the regulation’s presumption of consistency with the national contingency plan is inapplicable. In particular, Trinity claims that language in the orders required Bancamerica and ASARCO to satisfy the national contingency plan’s public comment requirements, 3 and that Bancamerica and ASARCO failed to do so. We review this issue de novo, 4 and finding Trinity’s argument unconvincing, affirm the district court’s holding.
Trinity relies on a provision in the Environmental Protection Agency order to Banc-america that states “all actions required to be taken pursuant to the terms of this Order shall be undertaken in accordance with the requirements of all applicable local, state, and Federal laws and regulations,” and an analogous provision in the Environmental Protection Agency’s order to ASARCO. Trinity contends these provisions required Bancamerica and ASARCO to comply with all the regulations of the national contingency plan (including the public comment requirements) to comply with the Environmental Protection Agency orders. That is, only by satisfying all the requirements of the national contingency plan сould Bancamerica and ASARCO comply with the terms of their orders so as to obtain the regulation’s pre *797 sumption of acting “consistent with the national contingency plan.”
We decline to accept this argument because, as the district court correctly noted, such an interpretation of the Environmental Protection Agency orders “would in effect render meaningless the regulation that deems actions taken in compliance with such orders to be consistent with the [national contingency plan].” Id. The fallacy of Trinity’s argument is obvious. To obtain the regulation’s presumption of consistency with the national contingency plan, Bancamerica and ASARCO would actually need to satisfy every requirement of the plan, thus eliminating any need for the presumption. Furthermore, in the order to Bancamerica, the Environmental Protection Agency expressly stated the work to be performed pursuant to the order, if properly performed, would be “consistent with the provisions of the National Contingency Plan.” Thus, Trinity’s interpretation of the “applicable law” provisions similarly would render meaningless this provision of the Environmental Protection Agency order.
Contrary to Trinity’s allegations, our holding does not make meaningless the “applicable law” provisions. Such provisions protect the Environmental Protection Agency from fоreclosing additional enforcement options and ensure private persons engaged in a cleanup comply with applicable state and local laws and regulations. Our holding does not impair the accomplishment of these goals.
The Environmental Protection Agency’s comments on its regulations, which are entitled to substantial deference,
Martin v. Occupational Safety & Health Review Comm’n,
Accordingly, we find the correct reading of the “applicable law” provisions of the Environmental Protection Agency orders to Bane-america and ASARCO to be that they refer to laws and regulations other than the national contingency plan, and did not require Bancamerica and ASARCO to meet the requirements of the national contingency plan. Therefore, we affirm the district court’s holding that the orders did not require Banc-america and ASARCO to comply with the national contingency plan’s public comment requirements.
II
Was it necessary for the district court to decide whether the cleanup was a “removal” or a “remedial” action?
The Comprehensive Environmental Response, Compensation, and Liability Act contemplates two different types of environmental cleanups, referred to as “removal actions” and “remedial actions.”
See
42 U.S.C. § 9601(23), (24) (defining removal and remedial actions). “Generally speaking, a removal is a short-term limited response to a more manageable problem, while a remedial action involves a longer term, more permanent and expensive solution to a more complex problem.”
Tri-County Business Campus Joint Venture v. Clow Corp.,
Because of the regulation presuming consistency with the national contingency plan for response actions performed according to the terms of an Environmental Protection Agency order, see 40 C.F.R. § 300.700(c)(3)(ii) (1995), whether Baneamerica and ASARCO’s response actions are better characterized as removal or remedial is irrelevant. In order for their response actions to be consistent with the national contingency plan, Baneamerica and ASARCO did not need to satisfy any of the plan’s regulations governing either removal or remedial actions; they needed only to satisfy the duties and obligations set forth in the Environmental Protection Agency’s orders. Accordingly, a determination by the district court of whether the response action was a removal or a remedial action was unnecessary.
Ill
Did the district court erroneously allow Baneamerica 7 to recover for response costs incurred in 1988 and 1989?
Trinity next contends, for a number of alternative reasons, the 1990
8
national contingency plan’s presumption of consistency for response actions taken in compliance with Environmental Protection Agency orders,
see
40 C.F.R. § 300.700(c)(3)(h) (1995), does not apply to Bancamerica’s actions taken in 1988 and 1989. Baneamerica responds that because Trinity did not present this argument to the district court, we should not consider it on appeal.
See Lyons v. Jefferson Bank & Trust,
Contrary to their assertion on appeal, at no time did Trinity raise this argument before the district court. Indeed, Trinity fails to point to any placе in the record where it argued the district court should consider Bancamerica’s 1988 and 1989 response costs separately from the remainder of Bancamerica’s costs.
See County Line,
“[Vjague, arguable references to [a] point in the district court proceedings do not ... preserve the issue on appeal.”
Lyons,
IV
Did the district court err in concluding that Trinity was not entitled to an offset against their breach of contract liability to Bancamerica?
The district court held Trinity liable to Bancamerica for failure to pay property taxes on the site, which Trinity was obligated to do under' the lease.
Bancamerica,
V
Are Bancamerica and ASARCO entitled to prejudgment interest?
Bancamerica and ASARCO contend the district court erred in refusing to grant them prejudgment interest on the response costs for which it held Trinity liable. Indeed, they claim § 107(a) of the Comprehensive Environmental Response, Compensation and Liability Act, 42 U.S.C. § 9607(a), mandates the award of such interest. Trinity responds that Baneameriea’s and ASARCO’s contribution action was pursuant to § 113(f), -42 U.S.C. § 9613(f) (1994), not § 107(a),
see Bancamerica,
We review the issue of whether prejudgment interest may be granted in § 113(f) contribution actions de novo.
See United States v. Diaz,
In arriving at this holding, we must revisit the relationship between cost recovery actions under § 107(a) and contribution actions under § 113(f). Previous opinions have laid much of the groundwork.
See Colorado & E. R.R. Co.,
[The Comprehensive Environmental Response, Compensation, and Liability Act] *800 made no express provision for contribution actions among parties held jointly and severally liable under its section 107 liability scheme. As a result, a potentially liable party under section 107 faced the prospect of being singled out as a defendant in a government or private cost recovery action without any apparent means of fairly apportioning [Comprehensivе Environmental Response, Compensation, and Liability Act] costs awarded against it to other persons liable for these costs under the statute. The courts responded to the inequity of this situation, and its negative implications for encouraging private parties to undertake voluntary [Comprehensive Environmental Response, Compensation, and Liability Act] cleanups, by recognizing an implicit federal right to contribution under [the Comprehensive Environmental Response, Compensation, and Liability Act], Congress ratified these efforts in 1986 by amending [the Comprehensive Environmental Response, Compensation, and Liability Act] section 113 to expressly, recognize a right of contribution under the statute.
Id.
at 1515-16 (citations omitted). We have since held an action between potentially liable persons such as Baneameriea, ASARCO and Trinity to apportion Comprehensive Environmental Response, Compensation, and Liability Act response costs between them is “the quintessential claim for contribution” and proceeds pursuant to § 113 rather than § 107, regardless of how pled.
Colorado & E. R.R.,
However, although such cost apportionment actions must be brought under the rubric of § 113(f), that section does not of itself create any new liabilities. Rather, it simply confirms the right of a person potentially jointly and severally liable under § 107(a) to obtain contribution from other potentially liable persons.
See
H.R.Rep. No. 99-253(1), 99th Cong., 2d Sess. 79,
reprinted in
1986 U.S.Code Cong. & Admin.News 2835, 2861 (citations omitted),
quoted in County Line,
Understanding of this relationship and review of the statutory language of § 107(a) leads us to the inescapable conclusion that prejudgment interest must be awarded in § 113(f) cases just as it is in § 107(a) cases. Section 107(а) makes certain enumerated persons hable for:
(A) all costs of removal or remedial action incurred by [government entities and]
(B) any other necessary costs of response incurred by any other person consistent with the national contingency plan.
42 U.S.C. § 9607(a)(4). It further states “[t]he amounts recoverable in an action under this section shall include interest on the amounts recoverable under subparagraphs (A) through (D).” Id. Accordingly, the liability to be apportioned in a § 113(a) contribution action is that set forth in subpara-graph (B) of § 107(a), which amount includes *801 interest. Although § 107 apparently refers only to “actions under this section,” because § 113(f) incorporates the liability provisions of § 107, in that sense a § 113(f) action for contribution is an action under § 107.
Our holding is consistent with logic, policy, and case law. The purpose of contribution is to equitably apportion response costs among liable parties. Failure to grant prejudgment interest on contribution awards may instead result in
inequitable
apportionment, because parties awarded contribution will still have lost the time value of the money they spent on behalf of other liable persons, and those persons will have gained an equal amount. Further, refusal to grant prejudgment interest is a disincentive for private parties to voluntarily undertake cleanup actions because they will lose the time valuе of the money they spend on behalf of other persons. Indeed, it would create a perverse incentive for responsible parties to delay involvement in cleanups, because as they delay, they gain the time value of the funds they should be investing in the cleanup. Finally, other courts have awarded prejudgment interest in § 113(f) contribution actions,
see, e.g., Browning-Ferris Indus, v. Ter Moat,
No. 92 C 20259,
Our holding that § 113(f) incorporates the prejudgment interest provision of § 107(a) does not end discussion of whether Banc-america and ASARCO are entitled to such interest. Section 107(a) states:
interest shall accrue from the later of (i) the date payment of a specified amount is demanded in writing, or (ii) the date of the expenditure concerned. . The rate of interest on the outstanding unpaid balance of the amounts recoverable under this section shall be the same rate as is specified for interest on investments of the Hazardous Substance Superfund established under subchapter A of chapter 98 of title 26.
42 U.S.C. § 9607(a)(4).
The district court, applying § 107, refused to grant Bancamerica and ASARCO prejudgment interest for two reasons. First, correctly noting that “prejudgment interest does not accrue until written demand for a specific dollar amount is made,” it found Bancamerica and ASARCO had failed to make such a demand.
Bancamerica,
We hold the district court abused its discretion in finding Bancamerica and ASARCO failed to meet the demand requirement of § 107(a). On January 20, 1989, Bancamerica sent a letter to Trinity stating Bancamerica had incurred $45,818.31 for environmental work performed on the site, and that it believed Trinity to be responsible for these costs. The letter further requested, that Trinity mail Bancamerica a check for $45,-818.31. This letter is clearly a written demand for a specific dollar amount and therefore satisfies the statute.
10
ASARCO made demand on August 13,1993, when Bancamerica and ASARCO filed their Third Amended Complaint. In this Complaint, ASARCO notified Trinity it had incurred response costs “in excess of $1 million,” for which it was seeking reimbursement (plus interest from the date of expenditure). This demand of at least $1 million in response costs satisfies § 107(a)’s requirement of a written demand of a specific dollar amount.
See In re Bell Petroleum Servs., Inc.,
*802
We also hold the district court’s refusal to grant Bancamerica and ASARCO prejudgment interest because they had not provided the court with interest rates or a method with which to compute the appropriate interest was an abuse of its discretion. Such a requirement is stated nowhere in the statute. Rather, § 107(a) speaks in mandatory terms: “The amounts recoverable ...
shall
include interest.” 42 U.S.C. § 9607(a)(4). Furthermore, the statute itself provides the applicable interest rates, stating the interest rate shall be the same as that for Superfund investments.
Id.
The rates for 1989 through 1998 were identified in
Hatco Corp. v. W.R. Grace & Co.
—Conn.,
We do agree with the district court that it is appropriate to require those requesting prejudgment interest to provide the court with proper calculations setting forth, the interest they seek. However, we also agree with Bancamerica and ASARCO that, because interest determinations are compounded calculations, it may be impossible for parties to provide accurate calculations prior to the court’s allocation of response cost liability. In such instances, parties may submit their interest calculations to the court subsequent. to thаt finding.
See United States v. Hardage,
Accordingly, we hold Bancamerica and AS-ARCO are entitled to prejudgment interest on the response costs awarded them, accruing from the later of the dates Bancamerica and ASARCO made their respective demands upon Trinity or the date of the expenditure concerned. See 42 U.S.C. § 9607(a)(4). We remand to the district court for determination of the appropriate amount of such interest.
VI
Did the district court err in considering only toxicity and volume in allocating liability for the site’s lead contamination?
In deciding contribution claims, a district court “may allocate 'response costs among liable parties using such equitable factors as the court determines аre appropriate.” 42 U.S.C. § 9613(f)(1). Here, the district court considered “the approximate volume of total lead at the Site contributed by [Trinity], and the degree of toxicity of the lead,” and held Trinity responsible for five percent of the total response costs related to lead contamination.
Bancamerica,
The district court has “considerable discretion in apportioning equitable shares of response costs.”
FMC Corp. v. Aero Indus., Inc.,
Although courts have looked to a number of factors in making such allocations,
see, e.g., Environmental Transp. Sys., Inc. v. ENSCO, Inc.,
VII
Did the district court err in failing to award Bancamerica damages on its breach of contract claim regarding the underground storage tanks?
Bancamerica’s final contention on appeal is that Trinity breached its lease contract with Bancamerica by operating leaking underground storage tanks and failing to repair- them. The tanks leaked gasoline into the surrounding earth, necessitating-removal of the contaminated soil. We review the district court’s finding that no breach of contract existed under the clearly erroneous standard.
Production Credit Ass’n v. Alamo Ranch Co.,
The tanks were present on the site when Trinity entered its lease with Bancamerica, and the district court found Trinity used only one of the three tanks, and it only for a short time at the inception of the lease.
Bancamerica,
AFFIRMED in part, REVERSED in part, and REMANDED for farther consideration consistent with this opinion.
Notes
. “Response actions" refer to cleanup actions taken in response to a release of hazardous substances into the environment. See 42 U.S.C. § 9601(23), (24), (25) (1994).
. The national contingency plan is a set of regulations promulgated by the Environmental Protection Agency that “establish[es] procedures and standards for responding to releases of hazardous substances, pollutants and contaminants.'' 42 U.S.C. § 9605; see 40 C.F.R. Part 300 (1995).
. The national contingency plan requires private parties engaged in a cleanup to provide the general public an opportunity to comment on the selection of the response action.
County Line Inv. Co. v. Tinney,
.In
United States v. Colorado & E. R.R. Co.,
. The Environmental Protection Agency first promulgated the national contingenсy plan in 1982, reissued it in 1985, and then substantially revised it in 1990.
Analytical Measurements, Inc. v. Keuffel & Esser Co.,
. Trinity excepts Bancamerica's actions related to the barrels from this assertion.
. This issue does not involve ASARCO because its response actions did not begin until 1991.
.Trinity argues in part that the 1985 version of the plan governed Bancamerica's 1988 and 1989 actions, and that that version did not contain a presumption of plan consistency.
. Although this was not one of the reasons for which the district court refused to award Banc-america and ASARCO prejudgment interest,
see Bancamerica,
. Trinity argues that the district court admitted this letter into evidence for the limited purpose of showing notice only, and thus Bancamerica cannot use it to show demand. This argument is meritless, because what the letter shows notice of is that Bancamerica made demand upon Trinity for a specified dollar amount.
. It is noteworthy that some of the factors Bancamerica and ASARCO contend the district court should have considered were in fact subsumed into the two factors the district court explicitly contemplated. For example, although the district court refused to expressly consider the greater bioavailability of lead from paint versus lead from slag and smelter ash, such a consideration was inherent in the court’s weighing of the greater toxicity of lead from paint.
