65 P. 309 | Cal. | 1901
Action to foreclose lien for construction of a sewer in the city of Los Angeles, under the so-called Vrooman Act, passed March 18, 1885, as amended in 1889, 1891, and 1893.
The second amended complaint was demurred to for insufficient facts. It was overruled, and the appellant answered. Judgment was for plaintiff, and this appeal is from the judgment and from an order denying a new trial.
1. Most, if not all, points urged here arise upon the demurrer. The first is, that the authority given the contractor to collect is in violation of section 13 of article XI of the constitution. That section reads as follows: "The legislature shall not delegate to any special commission, private corporation, company, association, or individual any power to make, control, appropriate, supervise, or in any way interfere with any county, city, town, or municipal improvement, money, property, or effects, whether held in trust or otherwise, or to levy taxes or assessments, or perform any municipal functions whatever."
Upon a mere reading, it is perfectly obvious that there is here no delegation of a municipal function. The contractor acts only as the agent or servant of the city. He has no discretion, *104 and can create no liability, nor can he impose any duty or exercise any control or authority over any one. He makes no assessment, levies no tax, and performs no municipal function. The municipal officers who enforce the ordinances of the city do not perform municipal functions, and in the collection of the street-assessment the contractor does no more.
This precise point was decided in Davies v. Los Angeles,
2. The council proceeded under the provisions of the so-called Vrooman Act, and it is contended that the city charter should have controlled.
The freeholders' charter of Los Angeles was adopted in 1889.
At that time the Vrooman Act was in force, and, as was held inThomason v. Ashworth,
In Yarnell v. Los Angeles,
If void from the beginning, the amendment to section 6 of article XI of the constitution in 1896 did not give life to such provisions. That would give the amendment the effect of enacting laws, instead of merely authorizing the legislature to do so, and it would be to enact a law to which no reference was made, and which the people, in adopting the amendment, could not have had in mind. Such is not the ordinary function of a constitutional provision, and such effect will not be given to it, unless it is expressly so provided.
Byrne v. Drain,
3. The next point is, that the provision for the formation of an assessment district is in violation of section 14 of article I of the state constitution, and of article V of the constitution of the United States, because it may result in taking private property for public use without just compensation. The brief was filed before the case of Hadley v. Dague,
4. It is contended that the resolution does not declare that it is necessary to construct the sewer, nor the manner in which the costs and expenses shall be assessed, as it is alleged is required by section 27 of part XI of the Vrooman Act. It is not necessary that the resolution of intention, which is but a notice of contemplated action on the part of the board, shall state that the board finds the contemtemplated work necessary. The manner in which the assessment is to be made is prescribed by the act itself. The resolution did show that costs and expenses were to be assessed upon the district benefited, and the district was described.
5. The next point is that the specifications were too uncertain, and left much to the discretion of the street *106
superintendent, which the board should have determined for itself. There was no delegation of authority to the street superintendent, except what is necessarily involved in the power on the part of that officer to determine, in the first instance, whether the contract has been performed. What is to be done is specifically described, but the requirements, to some extent, vary according to the nature of the earth in which the sewer is to be constructed. For instance, when the ground is wet, the soft earth is to be removed and gravel filled in; but the specifications do not determine the amount of wet, soft ground to be removed, or the quantity of gravel required to fill the excavation. It is not left to the street superintendent to say how much shall be done in any case. The contractor must do the work as required by his contract, and the street superintendent cannot accept less or require more. The board on appeal must finally determine. As to the indefiniteness of detail, it may be said, that, however minute they may be, some unsettled points might yet be suggested. This matter was considered in the late case of Haughawout v. Hubbard,
On the appeal from the order denying a new trial it is contended, —
1. The contract was prematurely let. The notice of the award was published on the 8th and 9th of November. The contract was entered into on the 19th of November following. The law provides that the notice shall be posted for five days and published in a newspaper for two days. The owners of three fourths of the frontage may, "within ten days after the first posting or publication of said notice," etc., elect to do the work. This law does not require the lapse of one day before the ten days shall begin to run, and, excluding the first day, the time allowed was ample.
2. The diagram of the district benefited, required by subdivision 12 of section 7 of the Vrooman Act, was not made and approved before the work was let and in fact performed. It was made in time for the assessment. The district itself was described in the resolution of intention, and from that time owners of property knew whether they were interested in the proceeding. The diagram showing the amount owned by each person was in time to enable property owners to suggest corrections. The statute does not require it to be made sooner. *107
3. The demand is objected to. The contract had been assigned, and the assignee made the demand in person, but in his affidavit showing demand he states that he made it on behalf of the contractor. It does not appear that he so stated in his demand, but if he did, it is immaterial. He was the owner of the claim, and if he notified the lot-owner to pay to his agent or to any other person, or that he demanded payment for another, it did not injure the taxpayer. Under such a demand, payment to the contractor would have been sufficient.
The judgment and order are affirmed.
McFarland, J., and Henshaw, J., concurred.