Opinion by
1. Aрpellant’s counsel contend that, the contract having provided a method for ascertaining the value of the extra labor and materials necessitated by a change in the plans and specifications, no suit to recover the amount due on account thereof can be maintained until the plaintiff has ascеrtained it according to the terms of the contract, or, at least, till he has made an ineffectual attempt to do so. On the other hand it is contended for plаintiff that he may, at his option, disregard the mode of settlement agreed upon, and resort directly to the tribunals provided by the state for the determination of questions in сontroversy. It is undoubtedly true that no person can be bound to deprive himself of his constitutional right to have his cause
In an exhaustive note to the case of Kinney v. Baltimore & Ohio Employes Association, 35 W. V. 385, 15 L. R. A. 142,
2. Another question presented is whether the agreement to refer would deprivе the plaintiff of his right to recover the balance of the amount expressly agreed to be paid for the building. It was agreed that the last installment of the contract price, being twenty-five per cent, thereof, should be withheld thirty-five days after the satisfactory completion and acceptance of the building, which amount wаs to be applied, under the direction of the architect, in satisfying and discharging liens, and in liquidation of damages. This would probably mean such damages as the owner might sustain in consequence of a failure to complete the building within the agreed time, from defective material and from faulty workmanship. If the contract had containеd no provision to deduct from the agreed price the deficiency caused by alterations in the plans and specifications, there can be no doubt thаt the lien might have been claimed, and a suit maintained to foreclose it, for the balance due, if the claimant honestly contended that the contract had bеen fully executed, without referring the question to arbitrators; and the damages sustained by the owner, if any, could then have become an issuable fact in the suit, and the deсree could have settled the amount due under the express contract to pay five thousand dollars for the completion of the building according to the plans and specifications. The owner agreed to pay seventy-five per cent, of the contract price as the work progressed, but reserved the right tо make such alterations therein as he chose. If the changes made had lessened the cost of constructing the building twenty-five per cent., then there would have been nothing due under the contract; and in such case, had the contractors claimed more, they would have to submit the question of difference between the cоst of constructing
3. The remaining question is whether the defendant has waived her right to insist upon this defense. The plaintiff having set out a copy of the contract, and not having alleged a compliance with its conditions, his complaint was demurrable: Meyers v. Pacific Construction Company,
Reversed.
